COORDINATION AND MEETINGS
01 31 00-1
SECTION 01 31 00
COORDINATION AND MEETINGS
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of this Section Includes:
1. Coordination and Project conditions.
2. Field engineering.
3. Preconstruction meeting.
4. Progress meetings.
1.02 RELATED SECTIONS
A. Section Not Used
1.03 COORDINATION AND PROJECT CONDITIONS
A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.
1.04 FIELD ENGINEERING
A. Employ a Land Surveyor registered in the Commonwealth of Pennsylvania and acceptable to Engineer.
B. Contractor shall protect survey control and reference points and provide stakeout as required for construction activities. Contractor is responsible for the protection of survey control and reference points and will compensate Owner for re-establishment of survey control and reference points.
C. Control datum for survey is that established by Owner provided survey.
D. Verify set-backs and easements; confirm drawing dimensions and elevations.
E. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.
F. Construct Work based on elevations, lines and locations as established, utilizing recognized survey control points and stakeout.
1.05 PRECONSTRUCTION MEETING
A. Engineer will schedule a meeting at the Project site after the Effective Date of the Agreement and prior to commencement of Work and Contractor occupancy, prepare an agenda with copies for participants, and preside at the meeting.
B. Attendance Required: Owner, Engineer, Resident Project Representative, Contractor, Contractor’s Superintendent and major Subcontractors.
C. Agenda:
1. Designation of personnel representing the parties in Contract, and the Engineer.
COORDINATION AND MEETINGS
01 31 00-2
2. Distribution of Contract Documents.
3. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.
4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.
5. Scheduling.
6. Use of premises by Owner and Contractor.
D. Engineer shall record minutes and distribute copies within five (5) working days after meeting to Owner and all other participants.
1.06 PROGRESS MEETINGS
A. Meetings shall be scheduled throughout progress of the Work on an as-needed basis.
B. Resident Project Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.
C. Attendance Required: Contractor's superintendent, major Subcontractors and suppliers, Owner, Engineer, as appropriate to agenda topics for each meeting.
E. Resident Project Representative shall record minutes and distribute copies within five (5) working days after meeting to Owner, Engineer and all other participants.
PART 2 - PRODUCTS
2.01 Section not used.
PART 3 - EXECUTION
3.01 CONSTRUCTION COORDINATION REQUIREMENTS
A. Coordination of Contractor’s and Owner’s Workmen
1. Contractor is advised that construction of other contracts may be in progress at the same time that this Contract is under construction. Contractor shall schedule his work so as not to conflict or interfere with these other contracts.
2. Contractor shall conduct his operations so as not to interfere with or injure the work of other contractors or workmen performing work for Owner. Contractor shall promptly repair, at his own expense, any injury or damage which may be done to such work by him or his employees, agents, or subcontractors.
3. Contractor shall suspend such part of the Work, or shall carry on the same in such a manner as may be ordered by Engineer when necessary, to facilitate the work of such other contractors and workmen of Owner.
4. Any difference which may arise between Contractor and any other contractors or workmen of Owner in regard to their Work shall be determined and adjusted by Owner insofar as Owner has authority.
5. Contractor shall not claim any extra compensation or damages as a result of delays or hindrances which may be caused by the work of such contractors or workmen of Owner, unless specifically permitted elsewhere in the Contract documents.
END OF SECTION