37-Sec 01 31 00-Coordination and Meetings.pdf

PDF 51 KB Posted

Attached to
Horsham Business Park Lighting - Phase II
Solicitation number
US.199180
Issued by
Montgomery County, Pennsylvania

View the file

Other files

File Type Posted
31-Sec 01 33 00-Submittals.pdf PDF
22-Doc 00 01 15-List of Drawing Sheets.pdf PDF
7-Doc 00 45 53-Agreement of Surety Company.pdf PDF
25-Doc 00 01 10-Table of Contents.pdf PDF
17-Doc 00 11 13-Advertisement for Bids.pdf PDF
24-Doc 00 61 13.13-Performance Bond.pdf PDF
29-Sec 01 56 39-Landscape Protection.pdf PDF
8-Doc 00 52 00-Agreement.pdf PDF
18-Doc 00 73 00-Supplementary Conditions.pdf PDF
4-Doc 00 62 16-Certificate of Insurance.pdf PDF
23-Doc 00 72 00-General Conditions.pdf PDF
35-Sec 01 11 13-Summary of Work.pdf PDF
33-Sec 01 70 00-Contract Closeout.pdf PDF
12-Doc 00 45 19-Non-Collusion Affidavit.pdf PDF
42-Sec 03 30 00-Cast in Place Concrete.pdf PDF
15-Doc 00 21 13.1-Instructions for Electronic Bidding.pdf PDF
5-Doc 00 73 00-Appendicies.pdf PDF
3-Doc 00 73 00 01-Appendix A - Prevailing Wage Rates.pdf PDF
14-Doc 00 45 13 - Bidder Qualification Statement.pdf PDF
45-Electrical Plans - For Permit Horsham Pedestrian Lts Elec 07312025.pdf PDF
41-Sec 01 42 13-Organization Reference Acronyms.pdf PDF
46-SITE PLAN FOR BID 2025 07 28.pdf PDF
32-Sec 01 40 00-Quality Control.pdf PDF
20-Doc 00 01 01-Cover.pdf PDF
9-Doc 00 91 13-Addenda.pdf PDF
30-Sec 01 50 00-Construction Facilities and Temp. Controls.pdf PDF
21-Doc 00 65 19.19-Consent of Surety to Final Payment.pdf PDF
2-Doc 00 61 13.16-Payment Bond.pdf PDF
19-Doc 00 65 19.16-Contractors Release of Liens.pdf PDF
1-Doc 00 21 13-Instructions to Bidders.pdf PDF
27-Doc 00 43 13 Bid Bond (penal sum form).pdf PDF
16-Doc 00 73 00 02-Appendix B - Public Works Employment Verification.pdf PDF
38-Sec 01 29 00-Contract Considerations.pdf PDF
36-Sec 01 71 13-Mobilization.pdf PDF
43-Sec 32 92 00-Finish Grading, Seeding and Sodding.pdf PDF
11-Doc 00 45 10-Bidders Acknowledgement Form.pdf PDF
40-Sec 01 55 26-Traffic Regulation.pdf PDF
6-Doc 00 41 00-Bid Form PennBid.pdf PDF
28-Sec 01 60 00-Material and Equipment.pdf PDF
26-Doc 00 65 19.13-Contractors Affidavit.pdf PDF
13-Doc 00 41 00-Bid Form.pdf PDF
39-Sec 01 22 00-Measurement Payment.pdf PDF
44-Sec 03 20 00 Concrete Reinforcement.pdf PDF
10-Doc 00 61 19-Maintenance Bond.pdf PDF
34-Sec 01 57 13-Soil Erosion and Sediment Control.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COORDINATION AND MEETINGS

01 31 00-1

SECTION 01 31 00

COORDINATION AND MEETINGS

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of this Section Includes:

1. Coordination and Project conditions.

2. Field engineering.

3. Preconstruction meeting.

4. Progress meetings.

1.02 RELATED SECTIONS

A. Section Not Used

1.03 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

1.04 FIELD ENGINEERING

A. Employ a Land Surveyor registered in the Commonwealth of Pennsylvania and acceptable to Engineer.

B. Contractor shall protect survey control and reference points and provide stakeout as required for construction activities. Contractor is responsible for the protection of survey control and reference points and will compensate Owner for re-establishment of survey control and reference points.

C. Control datum for survey is that established by Owner provided survey.

D. Verify set-backs and easements; confirm drawing dimensions and elevations.

E. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.

F. Construct Work based on elevations, lines and locations as established, utilizing recognized survey control points and stakeout.

1.05 PRECONSTRUCTION MEETING

A. Engineer will schedule a meeting at the Project site after the Effective Date of the Agreement and prior to commencement of Work and Contractor occupancy, prepare an agenda with copies for participants, and preside at the meeting.

B. Attendance Required: Owner, Engineer, Resident Project Representative, Contractor, Contractor’s Superintendent and major Subcontractors.

C. Agenda:

1. Designation of personnel representing the parties in Contract, and the Engineer.

COORDINATION AND MEETINGS

01 31 00-2

2. Distribution of Contract Documents.

3. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.

5. Scheduling.

6. Use of premises by Owner and Contractor.

D. Engineer shall record minutes and distribute copies within five (5) working days after meeting to Owner and all other participants.

1.06 PROGRESS MEETINGS

A. Meetings shall be scheduled throughout progress of the Work on an as-needed basis.

B. Resident Project Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance Required: Contractor's superintendent, major Subcontractors and suppliers, Owner, Engineer, as appropriate to agenda topics for each meeting.

E. Resident Project Representative shall record minutes and distribute copies within five (5) working days after meeting to Owner, Engineer and all other participants.

PART 2 - PRODUCTS

2.01 Section not used.

PART 3 - EXECUTION

3.01 CONSTRUCTION COORDINATION REQUIREMENTS

A. Coordination of Contractor’s and Owner’s Workmen

1. Contractor is advised that construction of other contracts may be in progress at the same time that this Contract is under construction. Contractor shall schedule his work so as not to conflict or interfere with these other contracts.

2. Contractor shall conduct his operations so as not to interfere with or injure the work of other contractors or workmen performing work for Owner. Contractor shall promptly repair, at his own expense, any injury or damage which may be done to such work by him or his employees, agents, or subcontractors.

3. Contractor shall suspend such part of the Work, or shall carry on the same in such a manner as may be ordered by Engineer when necessary, to facilitate the work of such other contractors and workmen of Owner.

4. Any difference which may arise between Contractor and any other contractors or workmen of Owner in regard to their Work shall be determined and adjusted by Owner insofar as Owner has authority.

5. Contractor shall not claim any extra compensation or damages as a result of delays or hindrances which may be caused by the work of such contractors or workmen of Owner, unless specifically permitted elsewhere in the Contract documents.

END OF SECTION