MEASUREMENT AND PAYMENT
01 22 00-1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Measurement and payment criteria applicable to the Work performed under a unit price payment method.
1.02 PROCEDURE
A. All measurements for payment will be based on completed work, performed in strict accordance with the Drawings and Project Manual, and with the Agreement’s “Schedule of Bid Items”.
B. The Resident Project Representative shall take all measurements and compute quantities relative to all work completed under the Agreement in accordance with the methods included in this section. Contractor shall assist by providing necessary equipment and personnel as required.
C. In cases where the payment clause for an item in this section relating to any unit or lump sum price requires that the said unit or lump sum price cover and be considered compensation for certain work or material essential to the item, this same work or material shall not be measured or paid for under any other item which may appear elsewhere in this section.
PART 2 - PRODUCTS
This section not used.
PART 3 - EXECUTION
3.01 DECORATIVE PEDESTRIAN LIGHT FIXTURE
A. Measurement
Measurement for this item shall be as determined in the field for EACH decorative pedestrian light fixture installed.
B. Payment
Payment for the installation of Decorative Pedestrian Light Fixture shall be made at the contract unit price as listed in the Bid Schedule. This price and payment will constitute full compensation for mobilization, furnishing all labor, materials, equipment, traffic control, roadway, driveway and lawn restoration necessary to install Decorative Pedestrian Light Fixture, including, but not limited to concrete footing, concrete reinforcement, ornamental pole, luminaire and all hardware necessary for installation as recommended by the manufacturer and detailed in construction drawings. All concrete work shall be in accordance with the latest editions of PennDOT Publication 408, and Publication 72, RC-64, and RC-67. Contractor is responsible for verifying that the final grades, slopes and dimensions are in compliance with the above publications.
01 22 00-2
3.02 ELECTRICAL CONDUIT & WIRE
A. MEASUREMENT
Measurement for this item will be as determined in the field per LINEAR FOOT of conduit and wire placed in accordance with the size and specifications provided in the electrical drawings.
B. PAYMENT
Payment for the Electrical Conduit & Wire shall be made at the contract unit price listed in the Bid Schedule. The work bid consists of all labor, equipment, materials and traffic control necessary to install the Electrical Conduit & Wire. Work shall be in accordance with the latest editions of PennDOT Publication 408 and include necessary trenching, backfill, soil stabilization and restoration.
3.03 ELECTRICAL CONTROL CABINET & METER
A. MEASUREMENT
Measurement for this item will be LUMP SUM for the installation of the Electrical Control Cabinet & Meter.
B. PAYMENT
Payment for the Electrical Control Cabinet shall be made at the contract unit price as listed in the Bid Schedule. This price and payment will constitute full compensation for mobilization, furnishing all labor, materials, equipment, traffic control, utility coordination necessary to install the Electrical Control Cabinet, connect to the existing power grid and energize the new light fixtures. Work shall be in accordance with the latest editions of PennDOT Publication 408 and electrical design plans.
3.04 MOBILIZATION
There will be no separate line item for Mobilization. Mobilization includes assembly, set-up, general operation, and removal of any Contractor's offices/trailer, shops, plants, storage areas, and sanitary or other facilities, furnishing adequate material and equipment, and obtaining the required permits, insurance, bonds, any other initial items required for the start of the work, any items required for payment requests and processing, and any other items required for the closeout of the project. Payment for Mobilization will not be made as Mobilization will be made incidental to all other Work.
3.05 MAINTENANCE AND PROTECTION OF TRAFFIC
There will be no separate line item for Maintenance and Protection of Traffic. Maintenance and Protection of Traffic includes full payment for furnishing all labor, materials, and equipment, flaggers, and traffic control (erection or placement and maintenance in good condition, of barricades, warning signs, lights, flares, approved yellow-flashing light units, rubber traffic cones, and other warning and danger signals and devices, appropriate and adequate for the specific needs at the project site) necessary for the safe operation of the roadway and all other public facilities. Pedestrian and vehicular traffic controls during construction are the responsibility and liability of the Contractor. Flaggers shall be certified, trained and equipped. Payment for Maintenance and Protection of Traffic will not be made as Maintenance and Protection of Traffic will be made incidental to all other Work.
3.06 LAWN RESTORATION
There will be no separate line item for Lawn Restoration. Lawn Restoration, backfill and clean-up
01 22 00-3 must be completed as soon as possible but no later than seven (7) working days of the last concrete pour. Lawn Restoration includes a minimum of 6” of topsoil followed by seeding and mulching. All areas of cut and fill shall be graded so they are no steeper than 3:1. Payment for Lawn Restoration will not be made as Lawn Restoration will be made incidental to all other Work.
3.07 EROSION AND SEDIMENT CONTROL, GRADING, SEEDING, AND RESTORATION
There will be no separate payment for Erosion and Sediment Control, Grading, Seeding, and Restoration as Erosion and Sediment Control, Grading, Seeding, and Restoration is incidental to all other Work. Erosion and Sediment Control, Grading, Seeding and Restoration includes all labor, materials, and equipment necessary for erosion and sediment control, grading, seeding, and in-kind restoration of any and all existing features damaged during construction, including fine grading, topsoil, and seeding. Any exposed soil shall be stabilized at the end of each work day. Payment for E&S will not be made as E&S will be made incidental to all other Work.
END OF SECTION