30-Sec 01 50 00-Construction Facilities and Temp. Controls.pdf

PDF 55 KB Posted

Attached to
Horsham Business Park Lighting - Phase II
Solicitation number
US.199180
Issued by
Montgomery County, Pennsylvania

View the file

Other files

File Type Posted
31-Sec 01 33 00-Submittals.pdf PDF
22-Doc 00 01 15-List of Drawing Sheets.pdf PDF
7-Doc 00 45 53-Agreement of Surety Company.pdf PDF
25-Doc 00 01 10-Table of Contents.pdf PDF
17-Doc 00 11 13-Advertisement for Bids.pdf PDF
24-Doc 00 61 13.13-Performance Bond.pdf PDF
29-Sec 01 56 39-Landscape Protection.pdf PDF
8-Doc 00 52 00-Agreement.pdf PDF
18-Doc 00 73 00-Supplementary Conditions.pdf PDF
4-Doc 00 62 16-Certificate of Insurance.pdf PDF
23-Doc 00 72 00-General Conditions.pdf PDF
35-Sec 01 11 13-Summary of Work.pdf PDF
33-Sec 01 70 00-Contract Closeout.pdf PDF
12-Doc 00 45 19-Non-Collusion Affidavit.pdf PDF
42-Sec 03 30 00-Cast in Place Concrete.pdf PDF
15-Doc 00 21 13.1-Instructions for Electronic Bidding.pdf PDF
5-Doc 00 73 00-Appendicies.pdf PDF
3-Doc 00 73 00 01-Appendix A - Prevailing Wage Rates.pdf PDF
14-Doc 00 45 13 - Bidder Qualification Statement.pdf PDF
45-Electrical Plans - For Permit Horsham Pedestrian Lts Elec 07312025.pdf PDF
41-Sec 01 42 13-Organization Reference Acronyms.pdf PDF
46-SITE PLAN FOR BID 2025 07 28.pdf PDF
32-Sec 01 40 00-Quality Control.pdf PDF
20-Doc 00 01 01-Cover.pdf PDF
37-Sec 01 31 00-Coordination and Meetings.pdf PDF
9-Doc 00 91 13-Addenda.pdf PDF
21-Doc 00 65 19.19-Consent of Surety to Final Payment.pdf PDF
2-Doc 00 61 13.16-Payment Bond.pdf PDF
19-Doc 00 65 19.16-Contractors Release of Liens.pdf PDF
1-Doc 00 21 13-Instructions to Bidders.pdf PDF
27-Doc 00 43 13 Bid Bond (penal sum form).pdf PDF
16-Doc 00 73 00 02-Appendix B - Public Works Employment Verification.pdf PDF
38-Sec 01 29 00-Contract Considerations.pdf PDF
36-Sec 01 71 13-Mobilization.pdf PDF
43-Sec 32 92 00-Finish Grading, Seeding and Sodding.pdf PDF
11-Doc 00 45 10-Bidders Acknowledgement Form.pdf PDF
40-Sec 01 55 26-Traffic Regulation.pdf PDF
6-Doc 00 41 00-Bid Form PennBid.pdf PDF
28-Sec 01 60 00-Material and Equipment.pdf PDF
26-Doc 00 65 19.13-Contractors Affidavit.pdf PDF
13-Doc 00 41 00-Bid Form.pdf PDF
39-Sec 01 22 00-Measurement Payment.pdf PDF
44-Sec 03 20 00 Concrete Reinforcement.pdf PDF
10-Doc 00 61 19-Maintenance Bond.pdf PDF
34-Sec 01 57 13-Soil Erosion and Sediment Control.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

01 50 00-1

SECTION 01 50 00

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

PART 1 GENERAL

1.01 GENERAL

A. The Work of this Section shall be the responsibility of the contractor as noted in the Summary of Work (Section 01 11 13).

1.02 SECTION INCLUDES

A. Temporary Utilities: Electricity, lighting, heat, ventilation, communications service, water and sanitary facilities.

B. Temporary Controls: Barriers, enclosures and fencing, protection of the Work, water control and dust control.

C. Construction Facilities: Access roads, parking, progress cleaning, project signage, and temporary buildings.

1.03 RELATED SECTIONS

A. Section 01 55 26: Traffic Regulation.

B. Section 01 57 13: Soil Erosion and Sediment Control.

C. Section 01 70 00: Contract Closeout: Final cleaning.

1.04 TEMPORARY ELECTRICITY

A. Cost: By Contractor; provide and pay for power service required from utility source.

1.05 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES

A. Provide and maintain lighting for construction operations and for security purposes.

1.06 TEMPORARY HEATING

A. Section not used.

1.07 TEMPORARY VENTILATION

A. Section not used.

1.08 COMMUNICATIONS SERVICE

A. Section not used.

1.09 TEMPORARY WATER SERVICE

A. Section not used.

1.10 TEMPORARY SANITARY FACILITIES

01 50 00-2

A. Provide and maintain sanitary facilities for employees for duration of the project. Provide at time of project mobilization. Coordinate the location of required facilities with the Owner.

B. At end of construction, return facilities to same or better condition than originally found.

1.11 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Provide protection for plants designated to remain. Replace damaged plants.

C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.12 FENCING

A. Section not used.

1.13 WATER CONTROL

A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.

B. Protect site from puddling or running water.

1.14 EXTERIOR ENCLOSURES

A. Section not used.

1.15 INTERIOR ENCLOSURES

A. Section not used.

1.16 PROTECTION OF INSTALLED WORK

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed Products. Control activity in immediate work area to prevent damage.

C. Prohibit traffic from landscaped areas.

1.17 SECURITY

A. Provide security and facilities to protect Work, and existing facilities, and Owner's operations from unauthorized entry, vandalism, or theft.

1.18 ACCESS ROADS

A. Section not used.

1.19 PARKING

01 50 00-3

A. Coordinate with the Owner to determine the location of temporary parking areas to accommodate construction personnel.

1.20 PROGRESS CLEANING AND WASTE REMOVAL

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.

B. Collect and remove waste materials, debris, and rubbish from site and dispose off-site.

1.21 PROJECT IDENTIFICATION

A. No signs are allowed without Owner permission except those required by law.

1.22 FIELD OFFICES AND SHEDS

A. Section not used.

1.23 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Clean and repair damage caused by installation or use of temporary work.

B. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.

1.24 DUST CONTROL

A. Execute Work by methods to minimize raising dust from construction operations.

B. Provide positive means (i.e. use of sprinkling water or other methods approved by the Resident Project Representative) to prevent air-borne dust from dispersing into atmosphere.

C. Dust control measures shall be employed when required in the opinion of the Resident Project Representative at no additional cost to Owner.

PART 2 PRODUCTS

Section not used.

PART 3 EXECUTION

Section not used.

END OF SECTION

SECTION 01 50 00