11-Doc 00 45 10-Bidders Acknowledgement Form.pdf

PDF 72 KB Posted

Attached to
Horsham Business Park Lighting - Phase II
Solicitation number
US.199180
Issued by
Montgomery County, Pennsylvania

View the file

Other files

File Type Posted
31-Sec 01 33 00-Submittals.pdf PDF
22-Doc 00 01 15-List of Drawing Sheets.pdf PDF
7-Doc 00 45 53-Agreement of Surety Company.pdf PDF
25-Doc 00 01 10-Table of Contents.pdf PDF
17-Doc 00 11 13-Advertisement for Bids.pdf PDF
24-Doc 00 61 13.13-Performance Bond.pdf PDF
29-Sec 01 56 39-Landscape Protection.pdf PDF
8-Doc 00 52 00-Agreement.pdf PDF
18-Doc 00 73 00-Supplementary Conditions.pdf PDF
4-Doc 00 62 16-Certificate of Insurance.pdf PDF
23-Doc 00 72 00-General Conditions.pdf PDF
35-Sec 01 11 13-Summary of Work.pdf PDF
33-Sec 01 70 00-Contract Closeout.pdf PDF
12-Doc 00 45 19-Non-Collusion Affidavit.pdf PDF
42-Sec 03 30 00-Cast in Place Concrete.pdf PDF
15-Doc 00 21 13.1-Instructions for Electronic Bidding.pdf PDF
5-Doc 00 73 00-Appendicies.pdf PDF
3-Doc 00 73 00 01-Appendix A - Prevailing Wage Rates.pdf PDF
14-Doc 00 45 13 - Bidder Qualification Statement.pdf PDF
45-Electrical Plans - For Permit Horsham Pedestrian Lts Elec 07312025.pdf PDF
41-Sec 01 42 13-Organization Reference Acronyms.pdf PDF
46-SITE PLAN FOR BID 2025 07 28.pdf PDF
32-Sec 01 40 00-Quality Control.pdf PDF
20-Doc 00 01 01-Cover.pdf PDF
37-Sec 01 31 00-Coordination and Meetings.pdf PDF
9-Doc 00 91 13-Addenda.pdf PDF
30-Sec 01 50 00-Construction Facilities and Temp. Controls.pdf PDF
21-Doc 00 65 19.19-Consent of Surety to Final Payment.pdf PDF
2-Doc 00 61 13.16-Payment Bond.pdf PDF
19-Doc 00 65 19.16-Contractors Release of Liens.pdf PDF
1-Doc 00 21 13-Instructions to Bidders.pdf PDF
27-Doc 00 43 13 Bid Bond (penal sum form).pdf PDF
16-Doc 00 73 00 02-Appendix B - Public Works Employment Verification.pdf PDF
38-Sec 01 29 00-Contract Considerations.pdf PDF
36-Sec 01 71 13-Mobilization.pdf PDF
43-Sec 32 92 00-Finish Grading, Seeding and Sodding.pdf PDF
40-Sec 01 55 26-Traffic Regulation.pdf PDF
6-Doc 00 41 00-Bid Form PennBid.pdf PDF
28-Sec 01 60 00-Material and Equipment.pdf PDF
26-Doc 00 65 19.13-Contractors Affidavit.pdf PDF
13-Doc 00 41 00-Bid Form.pdf PDF
39-Sec 01 22 00-Measurement Payment.pdf PDF
44-Sec 03 20 00 Concrete Reinforcement.pdf PDF
10-Doc 00 61 19-Maintenance Bond.pdf PDF
34-Sec 01 57 13-Soil Erosion and Sediment Control.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BIDDER’S ACKNOWLEDGEMENT FORM

00 45 10-1

DOCUMENT 00 45 10

BIDDER’S ACKNOWLEDGEMENT FORM

PROJECT IDENTIFICATION: HORSHAM BUSINESS PARK DECORATIVE PEDESTRIAN LIGHTING

PROJECT – PHASE II

CONTRACT IDENTIFICATION AND NUMBER: CONTRACT NO. 2017-06047-02

ARTICLE 1 – BID RECIPIENT

1.01 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an

Agreement with OWNER in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS

2.01 Bidder accepts all of the terms and conditions of the Advertisement or Invitation to Bid and

Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. The Bid will remain subject to acceptance for sixty (60) days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of OWNER.

ARTICLE 3 – BIDDER’S REPRESENTATIONS

3.01 In submitting this Bid, Bidder represents, as set forth in the Agreement, that:

A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Documents, and the following Addenda, receipt of all of which is hereby acknowledged.

Addendum No. Addendum Date

B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local and Site conditions that may affect cost, progress, and performance of the Work.

C. Bidder is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress and performance of the Work.

D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in the Supplementary Conditions as provided in paragraph 4.02 of the General Conditions, and (2) reports and drawings of a Hazardous Environmental Condition, if any, which has been identified in the Supplementary Conditions as provided in paragraph 4.06 of the General Conditions.

E. Bidder has obtained and carefully studied (or assumes responsibility for having done so) all additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, 00 45 10-2 and procedures of construction expressly required by the Bidding Documents to be employed by Bidder, and safety precautions and programs incident thereto.

F. Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.

G. Bidder is aware of the general nature of work to be performed by OWNER and others at the Site that relates to the Work as indicated in the Bidding Documents.

H. Bidder has correlated the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents.

I. Bidder has given ENGINEER written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by ENGINEER is acceptable to Bidder.

J. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance of the Work for which this Bid is submitted.

ARTICLE 4 – BIDDER’S CERTIFICATION

4.01 Bidder certifies that:

A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;

B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;

C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and

D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01 D.:

1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process;

2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;

3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and

4. “coercive practice” means harming or threatening to harm directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

ARTICLE 5 – BASIS OF BID

5.01 Bidder will adhere to the following:

A. Bidder will complete the Work in accordance with the Contract Documents for the submitted bid amount.

B. Unit Prices have been computed in accordance with paragraph 11.03.B of the General Conditions.

00 45 10-3

C. Bidder acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities provided, determined as provided in the Contract Documents.

D. Bidder is aware that the Total Bid Price is to include rock removal required to accomplish construction of the proposed Work.

ARTICLE 6 – TIME OF COMPLETION

6.01 Bidder agrees that the Work will be substantially complete within 150 calendar days after the date when the Contract Times commence to run as provided in paragraph 2.03 of the General Conditions, and completed and ready for final payment in accordance with paragraph 14.07.B of the General Conditions within 180 calendar days after the date when the Contract Times commence to run.

6.02 Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the times specified above, which shall be stated in the Agreement.

ARTICLE 7 – ATTACHMENTS TO THIS BID

7.01 The following documents are submitted along with this document and made a condition of this

Bid:

A. Required Bid security;

B. Bidder’s Acknowledgement Form;

C. Required Bidder's Qualification Form with supporting data;

D. Non-Collusion Affidavit;

E. Required Agreement of Surety;

F. Public Works Employment Verification Form G. List of Proposed Subcontractors, Proposed Suppliers and other individuals and entities required to be identified in this Bid

ARTICLE 8 – COMMUNICATIONS

8.01 Communications concerning this Bid shall be addressed to the following individual:

If the address, telephone number, and fax number of the above individual is different than noted at the end of the Bid Form, note the address, telephone number, and fax number of the above individual:

Business Address:

Telephone No.: (____)

Fax No. (____)

Email:

00 45 10-4

8.02 The terms used in this Bid with initial capital letters have the meanings indicated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

SUBMITTED on , 20___.

Name of Bidder:

� Corporation State of Incorporation:

Date of Qualification to do Business:

� Partnership General Partner:

� Individual Doing Business as:

Business Address:

Telephone No.:(____)

Fax No.: (____)

Name of Person authorized to sign (typed or printed):

Title of Person authorized to sign (typed or printed):

(Authorized Signature)

SEAL Affix Corporate Seal if Corporation

Attested by Corporate Secretary or an Assistant Secretary if Corporation

END OF DOCUMENT