About this file
Attached are Microsoft Word Versions of Sections B to the Combined Synopsis/Solicitation.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART I - THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
Qty Unit Price
ITEM
SUPPLIES OR SERVICES
Purch Unit Total Item Amount
Contract Phase-In/Transition Period
Noun:
CONTRACT PHASE-IN/TRANSITION PERIOD
PSC:
DD1423 is Exhibit:
A
Contract type:
J - FIRM FIXED PRICE
Start Date:
01 JAN 2016
Completion Date:
31 MAR 2016
Item project mgr.:
F1SRQR
Descriptive Data:
The contractor shall provide all qualified personnel, supplies, etc. to assume full responsibility for performance by the end of the contract phase-in/transition period to ensure a smooth transition of uninterrupted services in accordance with Section J, Attachment 1, Aerospace Systems Technical Research & Operations Support Services (ASTROS) Performance Work Statement.
Technical Effort (Direct Labor) - Basic Period
TECHNICAL EFFORT (DIRECT LABOR) - BASIC PERIOD
R - COST PLUS AWARD FEE
01 APR 2016
31 MAR 2019
The contractor shall provide qualified personnel (both prime and subcontract labor) for the ASTROS requirement in accordance with Section J, Attachment 1, ASTROS Performance Work Statement.
ITEM
SUPPLIES OR SERVICES
Purch Unit Total Item Amount
Other Direct Costs (ODC) - Basic Period
OTHER DIRECT COSTS (ODC) - BASIC PERIOD
S - COST
The contractor shall provide material, travel IAW The Joint Travel Regulations (JTR), equipment, training and other direct costs in accordance with Section J, Attachment 1, ASTROS Performance Work Statement.
The Contracting Officer (CO) may unilaterally increase or decrease the total estimated cost of this CLIN, as necessary in order to meet contract requirements.
No fee shall be included in the calculation of Award fee pool in association with this CLIN.
Total Cost: $33,576,426 Award Fee (AF) #1 - Basic Period
AWARD FEE POOL - BASIC PERIOD
The award fee pool consists of _____%* of the total labor cost for CLIN 0002.
Award-Fee Pool: $_____________.*
*Percent and Amount to be proposed by Offerors
ITEM
SUPPLIES OR SERVICES
Purch Unit Total Item Amount
Data - Exhibit A
Lot
DATA - EXHIBIT A
ACRN:
U
NSN:
N - Not Applicable
Inspection:
DESTINATION
Acceptance:
FOB:
The contractor shall furnish data in accordance with Section J, Exhibit A, Contract Data Requirements List (CDRL), DD Form 1423, A001 thru A017. All data is Not Separately Priced (NSP). The price of this item is included in CLIN 0002.
Technical Effort (Direct Labor) - Option #1
OPTION CLIN (service)
TECHNICAL EFFORT (DIRECT LABOR) - OPTION #1
The contractor shall provide qualified personnel (both prime and subcontract labor) for the ASTROS requirement in accordance with Section J, Attachment 1, ASTROS Performance Work Statement.
Estimated Cost: $TBD
ODCs - Option #1
OTHER DIRECT COSTS (ODC) - OPTION #1
The contractor shall provide material, travel IAW The Joint Travel Regulations (JTR), equipment, training and other direct costs in accordance with Section J, Attachment 1, ASTROS Performance Work Statement.
The Contracting Officer (CO) may unilaterally increase or decrease the total estimated cost of this CLIN, as necessary in order to meet contract requirements.
No fee shall be included in the calculation of Award fee pool in association with this CLIN.
Estimated Cost: $36,067,778
ITEM
SUPPLIES OR SERVICES
Purch Unit Total Item Amount
Award Fee #2 - Option #1
AWARD FEE POOL - OPTION #1
The award fee pool consists of _____%* of the total labor cost for CLIN 1002.
Award-Fee Pool: $_____________.*
*Percent and Amount to be proposed by Offerors Technical Effort (Direct Labor) - Option #2
TECHNICAL EFFORT (DIRECT LABOR) - OPTION #2
The contractor shall provide qualified personnel (both prime and subcontract labor) for the ASTROS requirement in accordance with Section J, Attachment 1, ASTROS Performance Work Statement.
Estimated Cost: $TBD
ODCs - Option #2
OTHER DIRECT COSTS (ODC) - OPTION #2
The contractor shall provide material, travel IAW The Joint Travel Regulations (JTR), equipment, training and other direct costs in accordance with Section J, Attachment 1, ASTROS Performance Work Statement.
The Contracting Officer (CO) may unilaterally increase or decrease the total estimated cost of this CLIN, as necessary in order to meet contract requirements.
Estimated Cost: $52,287,270
ITEM
SUPPLIES OR SERVICES
Purch Unit Total Item Amount
Award Fee Pool - Option #2
AWARD FEE POOL - OPTION #2
The award fee pool consists of _____%* of the total labor cost for CLIN 2002.
Award-Fee Pool: $_____________.*
*Percent and Amount to be proposed by Offerors Extension of Service (6 months)
EXTENSION OF SERVICE
This Option CLIN is incorporated IAW FAR 52.217-08, Option to Extend Services. The price of this CLIN consists of Technical Effort, ODCs, and Award Fee as specified below. If exercised, the following cost elements (Technical Effort, ODCs, Award Fee) will be funded on different information sub-CLINs. The price of this option was evaluated at contract award.
Option Cost Elements:
Technical Effort (Direct Labor): The contractor shall provide qualified personnel (both prime and subcontract labor) for the ASTROS requirement in accordance with Section J, Attachment 1, ASTROS Performance Work Statement.
Estimated Cost: $TBD Other Direct Costs (ODS): The contractor shall provide material, travel IAW The Joint Travel Regulations (JTR), equipment, training and other direct costs in accordance with Section J, Attachment 1, ASTROS Performance Work Statement.
The Contracting Officer (CO) may unilaterally increase or decrease the total estimated cost of this CLIN, as necessary in order to meet contract requirements.
Estimated Cost: $6,852,418 Award Fee Pool: The award fee pool consists of ___%* of the total labor cost for this Option CLIN 3000.
Award-Fee Pool: $________________.*
*Percent and Amount to be proposed by Offerors