McClellan Old Magpie Creek Channel Volume Estimates
Contaminated volume
Work Unit 1 = 217 cy
Work Unit 2 = 337 cy
Work Unit 3 = 154 cy
Work Unit 4 = 124 cy
Work Unit 5 = 423 cy
Work Unit 6 = 423 cy
Clean volume
Work Unit 1 = 2.925 cy
Work Unit 2 = 4,545 cy
Work Unit 3 = 2.070 cy
Work Unit 4 = 1,665 cy
Work Unit 5 = 5,701 cy
Work Unit 6 = 5,701 cy
FA890323R0020
Attachment #5
Backup Info
Length of work units
Work Unit 1 = 195 ft
Work Unit 2 = 303 ft
Work Unit 3 = 138 ft
Work Unit 4 = 111 ft
Work Unit 5 = 380 ft
Work Unit 6 = 380 ft
Area of work units at the surface
Work Unit 1 = 8,775 ft2 [= 195 ft x 45 ft]
Work Unit 2 = 13,635 ft2 [= 303 ft x 45 ft]
Work Unit 3 = 6,210 ft2 [= 138 ft x 45 ft]
Work Unit 4 = 4,995 ft2 [= 111 ft x 45 ft]
Work Unit 5 = 17,100 ft2 [= 380 ft x 45 ft]
Work Unit 6 = 17,100 ft2 [= 380 ft x 45 ft]
Area of work units at the bottom
Work Unit 1 = 2,925 ft2 [= 195 ft x 15 ft]
Work Unit 2 = 4,545 ft2 [= 303 ft x 15 ft]
Work Unit 3 = 2,070 ft2 [= 138 ft x 15 ft]
Work Unit 4 = 1,665 ft2 [= 111 ft x 15 ft]
Work Unit 5 = 5,700 ft2 [= 380 ft x 15 ft]
Work Unit 6 = 5,700 ft2 [= 380 ft x 15 ft]
Contaminated volume
Work Unit 1 = 217 cy [= (195 ft x 2 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 2 = 337 cy [= (303 ft x 2 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 3 = 154 cy [= 138 ft x 2 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 4 = 124 cy [= 111 ft x 2 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 5 = 423 cy [= 380 ft x 2 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 6 = 423 cy [= 380 ft x 2 ft x 15 ft) /27 ft3/cy, rounded up]
Clean overburden volume (layer 12 ft thick and 15 feet wide)
Work Unit 1 = 1,300 cy [= (195 ft x 12 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 2 = 2,020 cy [= (303 ft x 12 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 3 = 920 cy [= (138 ft x 12 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 4 = 740 cy [= (111 ft x 12 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 5 = 2,534 cy [= (380 ft x 12 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 6 = 2,534 cy [= (380 ft x 12 ft x 15 ft) /27 ft3/cy, rounded up]
Clean lay-back volume (assumes a 1:1 lay-back)
Work Unit 1 = 1,625 cy [= (195 ft x 15 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 2 = 2,525 cy [= (303 ft x 15 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 3 = 1,150 cy [= (138 ft x 15 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 4 = 925 cy [= (111 ft x 15 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 5 = 3,167 cy [= (380 ft x 15 ft x 15 ft) /27 ft3/cy, rounded up]
Work Unit 6 = 3,167 cy [= (380 ft x 15 ft x 15 ft) /27 ft3/cy, rounded up]