23F0020 - Attach 1 - OMCC SOW -09182023.pdf

PDF 725 KB Posted

Attached to
McClellan AFB Radiological Remediation Federal contract opportunity
Solicitation number
FA8903-23-R-0020
Issued by
Department of the Air Force Materiel Command Installation and Mission Support Center Installation Contracting Agency

View the file

Other files for this federal contract opportunity

Other files attached to McClellan AFB Radiological Remediation, newest first.
File Type Posted
23R0020 - Government Response to Questions - 12Oct2023.pdf PDF
Solicitation Amendment FA890323R00200002 SF 30.pdf PDF
Solicitation Amendment FA890323R00200001 SF 30.pdf PDF
23R0020 - Attach 11 - Section M.pdf PDF
23R0020 - Attach 10 - Section L.pdf PDF
23R0020 - Attach 14 - Field Trailer Sites Util.pdf PDF
23R0020 - Attach 3 - Key Personnel and Qualifications Revised.pdf PDF
23R0020 - Government Response to Questions - 25Sept2023.pdf PDF
23R0020 - Attach 4 - As Builts Part 3 of 10.pdf PDF
23R0020 - Attach 4 - As Builts Part 9 of 10.pdf PDF
23R0020 - Attach 4 - As Builts Part 4 of 10.pdf PDF
23R0020 - Attach 4 - As Builts Part 1 of 10.pdf PDF
23R0020 - Attach 4 - As Builts Part 5 of 10.pdf PDF
23F0020 - Attach 1 - OMCC SOW -04142023.pdf PDF
23R0020 - Attach 3 - Key Personnel and Qualifications.pdf PDF
23R0020 - Attach 4 - As Builts Part 2 of 10.pdf PDF
23R0020 - Attachment 11 - Section M.pdf PDF
23R0020-Attach_7_Transmittal_Letter.docx DOCX document
23R0020-Attach_9_Cross-Reference-Matrix.docx DOCX document
23R0020-Attach_6_Client_Authorization.docx DOCX document
23R0020 - Attach 2 - Past Performance Questionaire.docx DOCX document
23R0020 - Attach 4 - As Builts Part 10 of 10.pdf PDF
23R0020 - Attach 4 - As Builts Part 8 of 10.pdf PDF
23R0020 - Attach 4 - As Builts Part 6 of 10.pdf PDF
23R0020 - Attach 13 - Wage Determination.pdf PDF
Solicitation - FA890323R0020.pdf PDF
23R0020 - Attachment 10 - Section L.pdf PDF
23R0020 - Attachment M-1 - OMCC Relevancy Matrix.pdf PDF
23R0020-Attach_8_Consent_Letter.docx DOCX document
23R0020 - Attach 12 - CDRLS.xlsx XLSX spreadsheet
23R0020 - Attach 4 - As Builts Part 7 of 10.pdf PDF
23R0020 - Attach 5 - OMCC Estimated Volumes.pdf PDF
McClellan OMCC Tour.pdf PDF
Industry Day Attendees.pdf PDF
OMCC Industry Day 11-16-2022 v2.pptx PPTX presentation
23R0020 - DRAFT SOW Old Magpie Creek 04142023.pdf PDF
23R0020-Industry Day QnA.pdf PDF
Part 3 of 10.pdf PDF
Part 6 of 10.pdf PDF
Part 8 of 10.pdf PDF
Part 9 of 10.pdf PDF
Part 7 of 10.pdf PDF
Part 10 of 10.pdf PDF
Part 1 of 10.pdf PDF
Part 5 of 10.pdf PDF
Part 4 of 10.pdf PDF
Part 2 of 10.pdf PDF
McClellan OMCC SOW 02 NOV 2022 - DRAFT.pdf PDF
Show all 48

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment #1

FA8903-22-F-0020

18 SEPTEMBER 2023

REMEDIATION AND RELEASE OF MCCLELLAN AIR FORCE BASE (AFB)

OLD MAGPIE CREEK CHANNEL SOUTH OF MAGPIE CREEK

STATEMENT OF WORK

FOR

EXCAVATION OF RADIUM-CONTAMINATED SOIL IN SD290/OMCC SOUTH OF

THE CURRENT MAGPIE CREEK, DISPOSAL OF EXCAVATED SOIL,

RADIOLOGICAL FINAL STATUS SURVEY OF THE EXCAVATED SITE, SURFACE

RESTORATION, RESTORATION/PRESERVATION OF BUILDING 690,

UNRESTRICTED RADIOLOGICAL RELEASE, CERTIFICATION OF REMEDY

COMPLETION

AT

FORMER MCCLELLAN AFB, CA

PROJECT: PRJY20237231

CONTRACT NUMBER: FA8903-23-C-XXX

18 September 2023

TABLE OF CONTENTS

1.0 INTRODUCTION

1.1 SITE DESCRIPTION

1.2 GENERAL SCOPE

1.3 LIST OF ATTACHMENTS

1.4 APPLICABLE DOCUMENTS

1.5 GOVERNMENT FURNISHED INFORMATION (GFI)

1.6 GOVERNMENT FURNISHED EQUIPMENT (GFE)

2.0 PROJECT MANAGEMENT

2.1 PROJECT MANAGEMENT PLAN (PMP)

2.2 CONTRACTOR’S PROGRESS, STATUS, AND MANAGEMENT REPORT

2.3 MEETING/TELECONFERENCE SUPPORT

2.4 REGULATORY/PROFESSIONAL INTERFACE

2.5 NOTIFICATION REQUIREMENTS

2.6 DATA AND DELIVERABLE MANAGEMENT

2.7 RECORD KEEPING

2.8 KEY PERSONNEL AND QUALIFICATIONS

3.0 PLANS AND REPORTS

3.1 QUALITY PROGRAM PLAN

3.2 REMEDIAL ACTION WORK PLAN AND REMEDIAL DESIGN

3.3 QUALITY ASSURANCE PROJECT PLANS

3.4 SAMPLING AND ANALYSIS PLANS

3.5 CONSTRUCTION WORK PLAN

3.6 CONSTRUCTION QUALITY PLAN

3.7 HEALTH AND SAFETY PLAN

3.8 OTHER PLANS

3.9 ENGINEERING STUDY REPORT FOR B690

3.10 BIOLOGICAL RESOURCES FIELD INVESTIGATION REPORT

3.11 PRE-EXCAVATION SAMPLING REPORTS

3.12 FINAL STATUS SURVEY REPORTS

3.13 BACKFILL SUITABILITY REPORTS

3.14 FINAL INSPECTION REPORTS

3.15 REMEDIAL ACTION COMPLETION REPORT

3.16 CONSTRUCTION DRAWINGS AND SPECIFICATIONS

4.0 REMEDIAL ACTION

4.1 BIOLOGICAL RESOURCES FIELD INVESTIGATION

4.2 PRE-EXCAVATION SAMPLING

4.3 ENGINEERING STUDY FOR B690

4.4 DEMOLITION

4.5 EXCAVATION AND DISPOSAL

4.6 FINAL STATUS SURVEYS

4.7 SITE RESTORATION AND INSPECTION

4.8 SITE RELEASE

4.9 PERMITS AND LICENSES

4.10 WORKSITE ACCESS AND COORDINATION

4.11 WORKSITE CONTROL

4.12 HEALTH, SAFETY, UNEXPLODED ORDNANCE, AND EMERGENCY RESPONSE

4.13 PHOTO DOCUMENTATION

5.0 QUALITY ASSURANCE

5.1 DATA QUALITY ASSURANCE

5.2 LABORATORY SELECTION AND ANALYSIS

5.3 CONSTRUCTION QUALITY ASSURANCE

6.0 GOVERNMENT POINTS OF CONTACT

ATTACHMENTS

1 FIGURES

1.0 INTRODUCTION

This statement of work (SOW) defines the requirements for remediation of radium-226 (Ra-226) contamination at the Old Magpie Creek Channel (OMCC) (SD290) site at the former McClellan

Air Force Base (AFB) located in Sacramento County, California. The purpose of this work is to implement the excavation remedy selected by the Follow-on Strategic Sites (FoSS) Record of

Decision (ROD) for Ra-226 contaminated soil in the OMCC. The ROD also selected an institutional control (IC) remedy for other contaminants found at the site, but it is not the purpose of this SOW to implement the ICs or address contamination other than Ra-226.

The Contractor shall furnish the personnel, services, equipment, materials, facilities, and other requirements necessary for, and incidental to, the performance of work set forth herein. Primary technical services shall be performed by individuals who are credentialed members of architectural, planning, science, and engineering professions. Generally, a credentialed professional (a) is licensed (e.g., registered professional engineer) to practice in the state where the work is being performed and/or (b) commands the necessary expertise, in terms of knowledge and experience, to undertake the specified task.

1.1 Site Description

The OMCC is a former creek bed, now buried beneath about 12 feet of clean fill, located in the western portion of McClellan AFB south of the current Magpie Creek channel in the vicinity of

Building 690 (B690) and MAT K (also referred to as the Sun Gro Lot). The capital letter B followed by a number is used throughout this SOW to identify buildings. In plan view (Figure 1, Attachment 1) the buried channel forms a V-shape which intersects the current Magpie Creek east of B690, runs southwest beneath B690 to about the middle of MAT K, and then runs northwest until it intersects Magpie Creek again. The creek bed was contaminated with Ra-226 and various chemicals. A contaminated layer of soil approximately two (2) feet thick exists at about 12 feet below ground surface (bgs). The cross-section of the buried channel is a crescent shape approximately 15 feet wide at the floor of the former channel. The contaminated soil layer is dark in color. Because of its darker color with respect to the soil above and below it, the contaminated layer is referred to as the gray layer. In much of the former creek bed there is hard pan beneath the gray layer. Soil above the gray layer and the hard pan beneath it appear to be uncontaminated. This gray layer probably consists of sediment from the old creek channel and can be used as a marker for the creek bed. The eastern end of the site, from the current Magpie

Creek to 13 feet east of B690 has been remediated and granted unrestricted radiological release.

The portion of the site still needing remediation is about 1,500 feet long, from 13 feet west of

B690 through MAT K to the current Magpie Creek. The dimensions provided above are good faith estimates based on all information currently available about the site. The Air Force does not represent that those estimates constitute a definitive limit on the extent of contamination.

The remedy selected in the FoSS ROD is excavation for Ra-226 and engineering/institutional controls for chemical contamination. This SOW addresses the Ra-226 contamination only.

Successful completion of this project requires (1) all soil contaminated with Ra-226 greater than

2.0 picoCuries per gram (PCi/g) to be excavated and disposed in an approved facility, (2) a radiological final status survey to be done in accordance with the Multi-Agency Radiation

Survey and Site Investigation Manual (MARSSIM), (3) a final status survey report (FSSR) to be completed, (4) the grade, surfacing, utilities, and infrastructure to be restored to pre-remediation condition, (5) a Remedial Action Completion Report (RACR) to be completed, (6) the Air Force

Radioisotope Committee (RIC) to remove the OMCC from the McClellan AFB Multi-Sites

Radioactive Materials (RAM) Permit (Applicable Document 6 in Section 1.4 of this SOW), and

(6) the California Department of Health Services (CDPH) to issue a recommendation for unrestricted radiological release (RURR) of the site.

Contamination is known to be present in three locations: (1) Trench 1 which is about 13 feet east of B690 where the previous excavation of the OMCC ended, (2) Trench 2 which is an exploratory trench dug about 15 feet west of B690 following the previous OMCC excavation, and (3) Trench 3 which is an exploratory trench dug approximately 30 feet west of B708 in

MAT K following the previous OMCC excavation. All three trenches were dug, sampled, backfilled, and repaved in 2015. The western end of Trench 1 is marked by a subsurface slurry wall at the depth of the gray layer. The trenches are shown in Figure 1, Attachment 1 to this

SOW. Based on the contamination in Trenches 1 and 2, the Air Force presumes there is contamination beneath B690. However, that contamination has not been confirmed. It is uncertain whether contamination is continuous between Trenches 2 and 3 and how far downstream contamination extends from Trench 3. Since all soil that exceeds the Ra-226 cleanup level must be excavated, the Contractor shall be responsible for determining the bounds of the contamination and demonstrating that all contamination has been excavated.

Building 690 is a slab-on-grade ribbed metal structure 127 feet wide (east-west) and 424 feet 10 inches long (north-south). It has two main bays (North and South) separated by a 31-foot-wide plenum. Each bay has a peaked roof with the ridges oriented east-west at the center lines of the bay. The roofs slope from a maximum height of 41 feet 10 ¾ inches to a minimum height of 34 feet. The west side of each bay has hangar doors that open to a width of 144 feet with a vertical clearance of 29 feet. The hangar doors are rail-mounted at the top and bottom. The surrounding area is paved with asphalt (2-inch coarse bituminous surface over a 6-inch aggregate base compacted to 97%) on the east, north, and south and concrete (10-inch concrete over 6-inch aggregate base compacted to 97% over 6-inch subgrade compacted to 92%) on the west. The floor of the building is the same construction as the pavement to the west (10-inch concrete over

6-inch aggregate base compacted to 97% over 6-inch subgrade compacted to 92%). The roof of

B690 is supported by columns running around the perimeter of the building and a double row of support columns running east-west through the plenum. OMCC runs beneath B690 from northeast to southwest, starting about 13 feet west of the North Bay and running beneath parts of the North Bay, Central Plenum, and South Bay. Eight of the support columns, two on the east edge of the building and six inside the plenum, lie inside the OMCC boundary. It is unknown whether there is Ra-226 contamination beneath these support columns. Detailed drawings of the building are available in Applicable Documents 7 and 8 (Section 1.4 of this SOW).

1.2 General Scope

Work shall be divided into the following six work units (Figure 1, Attachment 1):

• Work Unit 1 from Trench 1 to Trench 2

• Work Unit 2 from Trench 2 to Trench 3

• Work Unit 3 from Trench 3 to the east end of a set of the tent-covered berms set up by the MAT K tenant (Sun Gro Tents)

• Work Unit 4 underneath the Sun Gro Tents

• Work Unit 5 running northwest from the west end of Work Unit 4 for 380 feet

• Work Unit 6 from the north end of Work Unit 5 to Magpie Creek.

The Contractor shall perform the following for each work unit:

1) Identify an appropriate technical approach to satisfy the requirements of this SOW.

2) Coordinate the technical approach with the Air Force Civil Engineer Center (AFCEC) and other key stakeholders.

3) Execute the approved approach in such a manner as to meet the ROD cleanup level, request an RURR from the State of California, and prepare an request to amend the radioactive material permit to remove OMCC from the permit, obtain concurrence from the United State Environmental Protection Agency (USEPA) that the remedy is complete.

4) Complete the design, remediation, demolition, and construction activities needed to satisfy the requirements of this SOW.

5) Provide complete, accurate, on-time, quality deliverables.

6) Identify and comply with the substantive requirements of all relevant federal, state, and local statutes and regulations in effect on the date of issuance of this contract, including but not limited to Department of Defense (DoD) and Air Force instructions, manuals, handbooks, regulations, guidance, and policy letters, Executive Orders, American Society for Testing and Materials, National Association of Corrosions

Engineers, National Fire Protection Association, Steel Structures and Painting

Counsel, National Electrical Code, Uniform Fire Code, Occupational Safety and

Health Administration (OSHA) regulations, California Division of Occupational

Safety and Health (Cal/OSHA) regulations, International Building Code, and state and local building codes.

7) Identify to the Contracting Officer (CO), Contracting Officer’s Representative

(COR), and Base Realignment and Closure (BRAC) Environmental Coordinator

(BEC) in a timely manner any problems or impediments to successful project execution, and work with the key stakeholders to resolve those issues in an efficient and timely manner.

8) Coordinate work with the following key stakeholders as necessary to meet the requirements of this SOW:

• AFCEC

• The Air Force RIC

• USEPA

• The California Department of Toxic Substances Control (DTSC)

• The California Central Valley Regional Water Quality Control Board (RWQCB)

• CDPH

• Sacramento County (serving as the Local Redevelopment Authority)

• McClellan Business Park (MBP)

• MBP tenants

• Sacramento Metropolitan Fire District

• Local utilities, including but not limited to Sacramento Metropolitan Utilities

District for electrical services, Pacific Gas and Electric for gas services, Sacramento Suburban Water District for water service, Sacramento County

Regional Sanitation District for sewer, Sacramento County Water Resources for storm water, and Consolidated Communications and ATT for Phone/Internet

Other stakeholders who are not directly involved with this project but have an interest in its outcome are the Nuclear Regulatory Commission (NRC), the McClellan AFB Restoration

Advisory Board, and the public.

It is the Contractor’s responsibility to identify and comply with all applicable requirements and to identify and coordinate with utilities owners who will be affected by this project.

1.3 List of Attachments

The Contractor shall comply with following attachments to this SOW:

1) Old Magpie Creek Channel Work Units

2) Key Personnel and Qualifications

1.4 Applicable Documents

The Contractor shall refer to and comply with the versions in effect at the time work is performed of the following reference documents:

1) McClellan AFB Interagency Agreement (IAG), USEPA, State of California, Air Force, May 1990, AR # 1521

2) Follow-on Strategic Sites Record of Decision, CH2MHill, April 2014, AR# 420534

3) Air Force Manual (AFMAN) 40-201, Radioactive Materials (RAM) Management, Air Force Medical Command, March 2019

4) Focused Strategic Sites Record of Decision, CH2MHill, February 2012, AR# 7522

5) Basewide Quality Assurance Project Plan (QAPP), Revision 7, AFCEC, July 2022, AR # 619178

6) Radioactive Material Permit CA-00366-02/02AFP, Air Force Radioisotope Committee, September 2022

7) McClellan Air Force Base ADAL Corrosion Control Facility, drawings, Capital

Engineering Consultants, Inc., September 1992

8) McClellan Air Force Base ADAL Corrosion Control Facility, drawings, Capital

Engineering Consultants, Inc., September 1995

9) Comprehensive Plan Composite Utilities McClellan Air Force Base California, Tab G-11, drawing, Air Force Logistics Command, January 1993

10) Uniform Federal Policy for Quality Assurance Project Plans (UFP-QAPP), EPA-505-B-

04-900A / DTIC ADA 427785, Intergovernmental Data Quality Task Force, March 2005

11) Optimized UFP-QAPP Worksheets, Intergovernmental Data Quality Task Force, March 2012

12) Guidance on Systematic Planning Using the Data Quality Objectives (DQO) Process, EPA/240/B-06/001, USEPA, February 2006

13) Old Magpie Creek Channel Project, video, https://youtu.be/g-bAD_7AHyI, AFCEC, August 2022

14) Old Magpie Creek Channel Trench 1 Final Status Survey Report, URS, June 2016, AR # 538391

15) Follow-on Strategic Sites Remedial Action Status Report Old Magpie Creek Channel, URS, September 2016, AR # 540129

16) Radiological Non-time Critical Removal Action Final Status Survey Report for Eight

Finding of Suitability for Early Transfer (FOSET) 3 Sites, CH2M HILL, February 2014, AR # 301088

17) Appendix 9 Final Status Survey Report Old Magpie Creek Channel South SU 01, CH2M HILL, June 2015, AR # 461828

18) Radiological Non-time Critical Removal Action for 17 of the 19 Finding of Suitability for

Early Transfer (FOSET) 3 Sites, CH2M HILL, May 2013, AR # 7830

19) Revised Reference Area Report Final Status Survey Report, Cabrera Services, November

2004, AR # 5777

1.5 Government Furnished Information (GFI)

GFI is provided in the Administrative Record (AR) at http://afcec.publicadmin-record.us.af.mil/Search.aspx and in reference documents 7, 8, and 9 (Section 1.4 of this SOW).

Documents shown with “AR #” in Section 1.4 of this SOW are available in the AR.

https://youtu.be/g-bAD_7AHyI http://afcec.publicadmin-record.us.af.mil/Search.aspx http://afcec.publicadmin-record.us.af.mil/Search.aspx

1.6 Government Furnished Equipment (GFE)

The Air Force will provide no GFE in support of this SOW.

2.0 PROJECT MANAGEMENT

2.1 Project Management Plan (PMP)

The Contractor shall prepare a PMP that will describe the management approach to perform the work required by this SOW and demonstrate the work has been completed successfully. The

PMP shall include a description of the project management team and reporting relationships, a work breakdown structure (WBS), and an integrated management schedule (IMS). The WBS shall include all tasks required to complete the work specified in this SOW. The IMS shall take the form of a Gantt chart showing the schedule for all tasks identified in the WBS. The

Contractor shall update the IMS monthly to show progress on each WBS task and any changes to the schedule. The Contractor shall include the updated IMS in the monthly Contractor’s

Progress, Status, and Management Report (CPSMR) described below. The PMP shall be delivered in draft and final versions. The AFCEC will have 30 days to review the draft, and the

Contractor will have 30 days to address AFCEC comments and issue the final version. (CDRLs

B001)

2.2 Contractor’s Progress, Status, and Management Report

The Contractor shall prepare and submit a CPSMR monthly. The CPSMR shall include a summary of the events that occurred during the reporting period, discussion of performance, identification of problems, proposed solutions, corrective actions taken, outstanding issues, and projected tasks occurring in the next reporting period. The CPSMR shall also include the monthly update of the IMS. The report shall be prepared in a format coordinated and approved by the COR and on a day of each month coordinated and approved by the COR. (CDRL B002)

2.3 Meeting/Teleconference Support

The Contractor shall participate in the following meetings:

• 1 kick-off meeting with the Air Force

• Weekly project management meetings with the Air Force

• Monthly meetings of the McClellan AFB BRAC Cleanup Team (BCT)

• Up to 10 comment resolution or problem resolution meetings with the regulatory agencies or other key stakeholders

At the Air Force’s discretion, other key stakeholders may be invited to the weekly project management meetings.

The Contractor shall prepare an agenda and presentation materials for the kick-off, project management, and comment/problem resolution meetings. If requested by the Air Force, the

Contractor shall prepare presentation materials for BCT meetings. Presentation materials and agendas for the kick-off, comment/problem resolution, and BCT meetings shall be submitted to the Air Force for review not less than five (5) working days prior to the meeting (unless otherwise approved by the Air Force). Presentation materials and agendas for project management meetings shall be submitted to the Air Force for review not less than one (1) working day prior to the meeting (unless otherwise approved by the Air Force). At a minimum, presentation materials for comment resolution meetings shall include a response to comments table. The Contractor shall prepare summaries/minutes for the kickoff and comment/problem resolution meetings not less than 10 working days after the meeting has occurred. (CDRLs

B003, B004, B005).

2.4 Regulatory/Professional Interface

The Contractor shall coordinate with the key stakeholders as necessary to accomplish the work specified in this SOW. Coordination may take the form of informal day-to-day interactions, informal meetings, formal meetings, or exchange of documents and/or data. Coordination may be in person, by teleconference or remote meeting (e.g., TEAMS), by email or text, or with written documents. The Air Force will be present for all meetings with the regulatory agencies and other key stakeholders. The Contractor shall not contact, nor take direction from, any regulatory agency or other key stakeholder without prior notification and approval by the

Air Force.

2.5 Notification Requirements

The Contractor is required to notify the CO, COR, and BEC of critical issues that may affect contract performance and/or human health and the environment. The types of issues that require notification include, but are not limited to health risks, spills, medical, fire, or law enforcement incidents, unexploded ordnance (UXO) discoveries, Notices of Violation (received or anticipated), and changes in key personnel. On critical issues, verbal notification shall be made within 24 hours, followed by written notification within three working days. (CDRL A001)

In the event of a dispute with or enforcement action from a regulatory agency arising from performance of work specified in this SOW, regardless of whether the Air Force is a named party, the Contractor shall notify the BEC and CO or COR within 24 hours. If the Air Force is a named party in the dispute or enforcement action, the Contractor shall provide support to the

Air Force as necessary to resolve the dispute or enforcement action. If the Air Force is not a named party in the dispute or enforcement action, the Contractor shall provide its proposed response to the dispute or enforcement action to the Air Force for review and comment prior to submission.

2.6 Data and Deliverable Management

The Contractor shall deliver all plans, reports, meeting agendas and minutes, presentation materials, GIS files (including layers), CADD files, and data necessary to complete the work specified in this SOW. Agendas, minutes, and presentation materials shall be prepared in draft and final versions. Plans and reports are primary documents under the McClellan AFB IAG unless otherwise noted in this SOW or negotiated between the Air Force and regulatory agencies.

Primary documents shall be prepared in Internal Draft (Working Copy), Draft, Draft Final, and

Final versions. Based on the IAG and standing agreements with the regulatory agencies, the normal time to finalize a primary document from the date the working copy is issued is eight months. The IAG review periods for primary documents are as follows unless otherwise negotiated with the Air Force and regulatory agencies:

• Working Copy (Air Force review) – 30 days

• Draft (regulatory agency review) – 60 days

• Draft Final (regulatory agency review) – 30 days

The Contractor will have the following periods to respond to comments and prepare the next document version unless otherwise negotiated with the Air Force and regulatory agencies:

• Working Copy to Draft – 30 days

• Draft to Draft Final – 60 days

• Draft Final to Final – 30 days

Regulatory agencies may unilaterally grant themselves a 30-day extension for review of draft documents and may request extensions for review of draft final documents. The Air Force may request extensions for preparation of draft, draft final, and final documents. Any party to the

IAG may dispute a document at the draft final stage. If any party invokes dispute, the Contractor will coordinate with the BEC and CO/COR concerning the dispute’s effect on contract scope, schedule, and cost.

Some technical reports prepared for this SOW may be classified as IAG secondary documents.

All secondary documents must be associated with a primary document. Secondary documents shall be prepared in Working Copy, Draft, and Final versions. Based on the IAG and standing agreements with the regulatory agencies, the normal time to finalize a secondary document from the date the working copy is issued is four months. The IAG review periods for secondary documents are as follows unless otherwise negotiated with the Air Force and regulatory agencies:

• Working Copy (Air Force review) – 30 days

• Draft (regulatory agency review) – 30 days

The Contractor shall have the following periods to respond to comments and prepare the next document version unless otherwise negotiated with the Air Force and regulatory agencies:

• Working Copy to Draft – 30 days

• Draft to Final – 30 days

Unless otherwise specified by the Air Force, primary and secondary documents shall be delivered to the following recipients in the form specified:

• Air Force AR – electronic on CD or DVD

• AFCEC – hard copy and electronic

• CDPH – hard copy and electronic

• DTSC – hard copy and electronic

• MBP – electronic

• RIC – electronic

• RWQCB – electronic

• Sacramento County – electronic

• USEPA – 2 hard copies and electronic

• USEPA Support Contractor – electronic

The electronic versions will be in the form of portable document format (pdf) files unless otherwise negotiated with the Air Force. The pdf of the final version shall include electronic bookmarks. Final documents must be accompanied by a metadata sheet and the pdf must meet the Air Force’s requirements in effect at the time of submittal for inclusion in the AR. The

Contractor shall deliver the electronic files on CD or DVD to the address the Air Force has on file for each reviewer and using the DoD Safe Access File Exchange (SAFE) site

(https://safe.apps.mil/). Uploading files to SAFE requires a DoD Common Access Card (CAC).

If the Contractor does not have personnel to make this upload who have a CAC then the

Contractor shall coordinate with the BEC to arrange for SAFE upload.

Copies sent to MBP and Sacramento County are for their information because they are the most directly-involved key stakeholders. They do not normally provide comments. The Air Force will determine on a case-by-case basis whether the Contractor needs to respond to any comments received from them.

The Contractor shall submit all field and laboratory data to ERPIMS unless otherwise authorized by the BEC. The Contractor shall prepare and submit ERPIMS deliverables as specified in the latest ERPIMS Data Loading Handbook (DLH) using the latest version of the ERPIMS software utility (ERPTools). The AFCEC website offers the latest DLH, ERPTools software, ERPIMS policy, Help Desk contact info, data submission requirements, and ERPTools training schedules, (https://www.afcec.af.mil/What-We-Do/Environment/Restoration/ERPIMS/Registration-

Process/). Data submissions shall be error-free, pass all validation checks and be fully comply with the ERPIMS DLH. The Contractor shall ensure that any required corrections are accomplished within the contract period of performance and funding for this contract. Questions with regard to ERPTools software and training can be addressed to the ERPIMS Help Desk.

(CDRL B006)

https://safe.apps.mil/ https://www.afcec.af.mil/What-We-Do/Environment/Restoration/ERPIMS/Registration-Process/ https://www.afcec.af.mil/What-We-Do/Environment/Restoration/ERPIMS/Registration-Process/

Figures, diagrams, maps, and drawings shall be delivered as pdf, image, CADD or GIS files as negotiated with the BEC. Files shall be compatible with the current AFCEC Microsoft™ Office

Suite and GIS software versions. All figures shall be delivered in original application files GIS format. GIS submissions shall include layers. (CDRL A002a, A002b)

Analytical tools, techniques, and software developed specifically to perform the work specified in this SOW shall be the property of the United States Air Force, and shall be delivered at the end of the contract in an electronic form negotiated with the COR.

2.7 Record Keeping

The Contractor shall create and maintain records sufficient to recreate each sampling, analytical, testing and monitoring event, and shall make these records available to the Government upon request. The records shall take the form of written, bound, numbered logbooks and/or equivalent electronic files. If electronic files are used, they must be protected such that they cannot be altered after they are created. The Contractor shall maintain records of, and derived from, all activities outlined in the appropriate portion of the Quality Program Plan (QPP) supporting the generation of these sampling and analysis records. The Contractor shall also retain written calculations using information obtained from sampling, analysis monitoring, and testing activities, to include all raw data. All information shall be provided to the Government upon request and included as part of the appropriate deliverables associated with this SOW.

2.8 Key Personnel and Qualifications

The Contractor shall identify key positions and assign qualified personnel to fill those positions.

Personnel assigned to those positions shall be credentialed members of architectural, planning, science, and engineering professions. Generally, a credentialed professional (a) is licensed (e.g., registered professional engineer) to practice in the state where the work is being performed and/or (b) commands the necessary expertise, in terms of knowledge and experience, to undertake the specified task.

3.0 PLANS AND REPORTS

The Contractor shall prepare and deliver the technical plans and reports specified in this section

(hereinafter referred to as project plans and project reports). All plans and reports shall be considered IAG primary documents unless otherwise specified below or negotiated with the by the Air Force and regulatory agencies. IAG primary and secondary documents shall be managed as specified in Section 2.7 of this SOW and the CDRL.

All versions of technical reports (working copy, draft final, and final) delivered by the Contractor shall be complete; substantively correct and consistent with applicable laws, regulations, DoD and Air Force policies; in proper format; and free of grammatical and typographical errors.

Working copies are considered “drafts” only in the sense that they have not been reviewed and approved by the Air Force. Draft documents are the initial version of documents that have undergone Air Force review and are submitted to the appropriate regulatory agencies for review.

Draft Final documents incorporate regulatory comments on the draft and are submitted to the regulatory agencies so the agencies can confirm their comments have been adequately addressed.

Final documents incorporate regulatory comments on the draft final and are intended to be the last version of the document to be issued. The final is the version that will be placed in the AR to become a permanent part of the publicly-available record for the site.

3.1 Quality Program Plan

The QPP shall comprise the Remedial Action Work Plan (RAWP), Health and Safety Plan

(HSP), McClellan Basewide QAPP (to be included by reference), project-specific QAPP

Addendum, Sampling and Analysis Plans (SAPs), Construction Work Plan (CWP), and

Construction Quality Plan (CQP) for this contract. The QPP shall not be a separate deliverable.

It will simply consist of the final versions of each of the documents listed above.

3.2 Remedial Action Work Plan and Remedial Design

The Contractor shall prepare and deliver a RAWP describing all activities needed to complete remediation of the OMCC as specified in the FoSS ROD. The contractor shall decide, in consultation with the Air Force, whether there will be a single RAWP for the entire project or separate RAWPS for each work unit. The activities will be described in sufficient detail for the

Air Force and regulatory agencies to verify the work will be sufficient to meet the cleanup goals specified in the ROD, the Air Force to perform inspections and surveillance, and Contractor and subcontractor personnel to perform the work. The RAWP must describe the technical approach that will be used to obtain unrestricted radiological release of each OMCC Work Unit (Figure 1, Attachment 1), the technical approach that will be used to preserve and/or restore the structure, appearance, and function of B690, and the technical approach that will be used to preserve and/or restore other infrastructure disturbed during the OMCC remediation. The RAWP also must include the designs of the excavations and any structures required to complete the remedy such as roads, fences, soils holding areas, and staging areas. To the extent the remediation requires demolition of any pavement or structures, the RAWP shall include the demolition plan for those items. The RAWP is an IAG primary document. (CDRL A003a)

3.3 Quality Assurance Project Plans

The Contractor shall prepare a project-specific addendum to the McClellan AFB Basewide

QAPP using the forms specified in the Basewide QAPP. The Contractor shall comply with the

Basewide QAPP except as specified in the final, approved QAPP Addendum. The QAPP

Addendum is an IAG primary document. The Contractor shall, in consultation with the

Air Force, determine whether the QAPP addendum will be issued as a stand-alone document or as part of the RAWP. (CDRL A003b)

3.4 Sampling and Analysis Plans

The Contractor shall prepare SAPs for pre-excavation sampling (Section 4.2 of this SOW), radiological final status surveys (Section 4.6 of this SOW), and backfill sampling (Section 4.7 of this SOW). There shall be a separate pre-excavation SAP for each work unit and a separate final status survey SAP for each work unit. The contractor shall decide, in consultation with the

Air Force, whether there will be a single backfill SAP for all backfill soil or separate backfill

SAPs for each work unit. The Contractor shall prepare the SAPs in accordance with the UFP-

QAPP, McClellan AFB Basewide QAPP, and project specific QAPP Addendum. The

McClellan AFB Basewide QAPP worksheets shall be used, and a crosswalk (Worksheet 2) shall be used to document that all required elements of the UFP-QAPP are present in the SAP. The pre-excavation and final status survey SAPs are IAG primary documents. The backfill SAPs are

IAG secondary documents, and the associated primary document is the RACR. The Contractor shall, in consultation with the Air Force, determine whether the SAPs will be issued as stand-alone plans or as part of the RAWP. (CDRL A004)

3.5 Construction Work Plan

The Contractor shall prepare a CWP describing all activities needed to restore infrastructure affected by the OMCC remediation. This includes but is not limited to B690, B708, B751, B752, B753, and pavement, structures, and utilities adjacent to or under B690, Kilzer Ave., MAT K, or the current Magpie Creek. There shall be a separate CWP for each work unit. The

CWP is an IAG primary document. (CDRL A005a)

3.6 Construction Quality Plan

The Contractor shall prepare a CQP to define the organization, procedures, and quality control program necessary to ensure the proper execution of the efforts specified in the CWP. The CQP must address the following items at a minimum: (CDRL A005b)

• The processes, procedures, and forms the Contractor shall use to verify equipment, materials, and construction activities meet the requirements of the final 60% design (see

Section 3.15 of this SOW) and comply with all relevant DoD, Air Force, federal, state, and local statutes, codes, requirements, and guidance.

• The inspections and documentation the Contractor shall use to verify equipment, materials, and infrastructure construction are in accordance with the specifications and work standards in the final 60% design.

• The corrective actions process the Contractor shall use to address deficiencies found during the inspections, including the selection and documentation of corrective actions, time frame for corrective actions, and re-inspection to confirm the implementation and effectiveness of corrective actions.

• Construction Quality Assurance (QA) personnel, responsibilities, and reporting chain.

The contractor shall decide, in consultation with the Air Force, whether there will be a single

CQP for the entire project or separate plans for each work unit.

3.7 Health and Safety Plan

The Contractor shall prepare an HSP as required by Title 29 of the Code of Federal Regulations

Part 1910.120 (29 CFR 1910.120), Title 10 of the Code of Federal Regulations Part 20

(10 CFR 20), and AFMAN 40-201. The HSP shall apply to all field activities required to perform the OMCC remediation and infrastructure restoration. The Contractor shall use USEPA guidelines, AFMAN 40-201, and 10 CFR 20 for designating the appropriate levels of protection needed at the site. The Contractor shall maintain written certification that the approved HSP has been reviewed with all personnel that work at the project site prior to their mobilization. The

Contractor shall decide, in consultation with the Air Force, whether a single HSP will be issued for the entire project or separate HSPs are needed for the remediation and construction phases of the work and whether the HSP(s) will be issued as stand-alone documents or as parts of the

RAWP and/or CWP. HSPs are IAG primary documents. (CDRL A006)

3.8 Other Plans

The Contractor shall prepare any other plans necessary to describe the work required at the site, protect human health and the environment and comply with federal, state, and local requirements during the performance of this SOW. Such plans might include but are not limited to plans for site security and access control, transportation, dust mitigation, surface water management, storm water pollution prevention, wildlife conservation, and confined space entry. The Contractor shall determine the need for any such plans in consultation with Air Force and the regulatory agencies. These plans shall be primary documents unless otherwise negotiated with the

Air Force and regulatory agencies. The Contractor shall determine in consultation with

Air Force whether each plan will be issued as a stand-alone document or as part of the RAWP and/or CWP. (CDRL A0005c)

3.9 Engineering Study Report for B690

The Contractor shall prepare a technical report documenting the results of the engineering study for B690 (see Section 4.3 of this SOW). This will be an Air Force-internal document and will not require review by the regulatory agencies. The report shall be prepared in draft and final versions. The Air Force shall have 30 days to review the draft report, and the Contractor shall issue the final version, incorporating the Air Force’s comments on the draft within 30 days of receiving the Air Force comments. At the Air Force’s discretion this report may be shared with

MBP and Sacramento County. (CDRL A007a)

3.10 Biological Resources Field Investigation Report

The Contractor shall prepare a technical report for each work unit documenting the results of the biological resources field investigation for that work unit (see Section 4.1 of this SOW). These are IAG secondary documents. The associated primary document is the RACR. (A007b)

3.11 Pre-Excavation Sampling Reports

The Contractor shall prepare a pre-excavation sampling report for each work unit (Figure 1, Attachment 1). Pre-excavation sampling is discussed in Section 4.2 of this SOW. The reports shall present the following information:

• Locations, boundaries, and MARSSIM classification of each survey unit

• Locations and depths of all samples

• Sampling and analysis methods used

• Laboratory results for each sample

• Quality assurance/quality control (QA/QC) measures used during the sampling and analysis

• Data validation

• Conclusions and recommendations

• Disposal of any waste generated during the sampling, i.e., Investigation Derived Waste

(IDW)

• Decontamination of tools and equipment used during sampling and transport to the lab

• Any restoration done to return the site to its pre-sampling condition

• All necessary backup information needed to decide whether the SAP was followed, human health and the environment were protected during the sampling, and the data are usable for decision making, including but not limited to field logs; boring logs; laboratory reports; visitor access logs; incident, accident, and spill reports; and reports of actions taken to control fugitive dust and surface water run-on and run-off

The conclusions and recommendations must explicitly address whether the work unit or any part of the work unit requires excavation and whether all or part of the work unit is suitable for unrestricted radiological release without excavation. The Contractor shall decide in consultation with the Air Force whether the scoping survey reports for each work unit shall be issued as stand-alone documents or combined into a single document. For a work unit where the sampling shows no excavation is needed, the scoping survey report can be converted to a FSSR if the

Air Force and regulatory agencies agree. (CDRL A007c)

3.12 Final Status Survey Reports

The Contractor shall prepare a FSSR for each work unit (Figure 1, Attachment 1). Each work unit requires a FSSR regardless of whether any excavation is performed in that work unit. Final status surveys are discussed in Section 4.6 of this SOW. The FSSRs shall present the following information:

• Locations, boundaries, and MARSSIM classification of each survey unit

• Surface scan results, instruments used for the surface scans, and instrument calibration and QA/QC

• Locations and depths of all samples

• Sampling and analysis methods used

• Laboratory results for each sample

• QA/QC measures used during the sampling and analysis

• Data validation

• Conclusions and recommendations

• All necessary backup information needed to decide whether the SAP was followed, and the data are usable for decision making including but not limited to field logs, boring logs, and laboratory reports.

The conclusions and recommendations must explicitly state that the ROD cleanup levels have been met, a reasonable effort was made to remove all radioactive contamination, and the work unit is suitable for unrestricted radiological release. The remediation at OMCC will be phased to manage the impact of the remediation on MBP and its tenants, so final status surveys for the different work units will be done at different times. Therefore, the FSSRs for each phase of work shall be issued at different times. The Contractor shall decide in consultation with the

Air Force whether the FSSRs for each work unit done during a specific phase of the remediation shall be issued as stand-alone documents or combined into a single document. (CDRL A007d)

3.13 Backfill Suitability Reports

The Contractor shall prepare one or more technical reports documenting the sampling results for backfill soil (see Section 4.7 of this SOW). The contractor shall decide, in consultation with the

Air Force, whether there will be a single backfill suitability report for all backfill soil used in the project or separate reports for each work unit. These are IAG secondary documents. The associated primary document is the RACR. (CDRL A007e)

3.14 Final Inspection Reports

The Contractor shall prepare a final inspection report for each work unit once the work unit has been restored to its pre-excavation condition. The draft version will be called the Pre-Final

Inspection Report. It shall be issued prior to the final inspection and used as the basis for the final inspection. The final version will be called the Final Inspection Report. It shall be prepared after the final inspection has been completed and all final inspection punch list items have been completed. This report will document the final condition of the work unit. These are

IAG secondary documents. The associated primary document is the RACR. (CDRL A007f)

3.15 Remedial Action Completion Report

The Contractor shall prepare a RACR for the entire OMCC remediation effort. The RACR shall present the following information:

• Remediation conducted at each work unit. If the scoping survey showed no excavation was needed at a work unit and the Air Force and regulatory agencies concur, then the remediation description will summarize the results of the scoping survey and state that no active remediation was required to meet the cleanup levels in that work unit.

• Quantity of soil removed.

• Where the excavated soil was disposed.

• Depth and width of the excavations and any lay-backs or terracing that was required.

• A summary of the data, conclusions, and recommendations from the FSSR demonstrating that the ROD cleanup level has been met.

• The source of backfill material and sampling results showing the backfill meets the ROD cleanup levels for Ra-226 and chemical contaminants of concern.

• Disposal of any IDW generated during the final status survey.

• Decontamination of tools and equipment used during the remediation and final status survey.

• Any restoration, including construction, done to return the site to its pre-remediation condition.

• An explicit determination that the remedy selected in the ROD has been performed and the cleanup level in the ROD has been met.

• All necessary backup information needed to decide whether the RAWP was followed, human health and the environment were protected during the remediation, and the data collected during the final status survey are usable for decision making, including but not limited to field logs, boring logs, laboratory reports, visitor access logs, incident, accident, and spill reports, and reports of actions taken to control fugitive dust and surface water run-on and run-off.

The RACR will be largely repetitive of information presented in the FSSRs. However, the

RACR and FSSRs cannot be combined into a single document because they follow different guidance concerning how to determine and document whether remediation is complete. (CDRL

A007g)

3.16 Construction Drawings and Specifications

The Contractor shall prepare construction drawings and specifications (collectively referred to as the design) for all infrastructure requiring construction work to restore to its pre-remediation condition. The Contractor shall prepare a 60% design prior to construction and an as-built design after construction is complete. The as-built shall reflect the final configuration of the infrastructure as actually constructed and finished. The design shall include the following to the extent they are disturbed during remediation and need to be repaired/restored:

• B690

• Paving around B690

• Paving between B690 and Kilzer Ave.

• Roadway and west margin of Kilzer Ave.

• Utilities, landscaping, and fencing west of Kilzer Ave.

• B708

• Paving inside MAT K

• B751 and B752

• Paving between MAT K and Magpie Creek

• The liner of Magpie Creek

The 60% and as-built designs are not subject to the IAG. They are “other” documents and shall be prepared in working copy, draft, and final versions. The Air Force shall have 30 days to review the working copies, and the regulatory agencies shall have 30 days to review the drafts.

The Contractor shall issue the drafts, incorporating the Air Force’s comments within 30 days of receiving their comments, and issue the finals, incorporating comments from the regulators, within 30 days of receiving their comments. (CDRL A008a, A008b)

4.0 REMEDIAL ACTION

The Contractor shall implement the remedy selected in the FoSS ROD for Ra-226 contaminated soil in the OMCC—excavation to unrestricted use levels with disposal in the CU. The unrestricted use cleanup level for Ra-226 is 2.0 pCi/g. The Contractor shall completely or partially demolish infrastructure such as buildings, utilities, and roads as necessary to implement the remedy, excavate soil that exceeds the Ra-226 cleanup level, transport the contaminated soil for disposal, perform final status surveys, backfill the excavation, and restore infrastructure to its pre-remediation condition. The Contractor shall restore to its original condition all infrastructure affected by the work performed pursuant to this SOW.

4.1 Biological Resources Field Investigation

The Contractor shall perform a biological resources field investigation in each work unit prior to mobilization and site preparation. The purpose of the investigation is to determine whether any species protected by federal or state statutes or regulations are present at the site and, if so, to define mitigation actions commensurate with federal and state requirements. There are no wetlands or sensitive habitat within the OMCC or its surroundings.

4.2 Pre-Excavation Sampling

The Contractor shall perform pre-excavation sampling in each work unit. The pre-excavation sampling shall consist of a radiation scoping survey and chemical sampling to (1) identify which areas are contaminated above the Ra-226 cleanup level and which areas are not, (2) verify the depth at which Ra-226 contamination begins, (3) determine if any of the soil being sent for disposal will exceed CU waste acceptance criteria (WAC) for Ra-226 or chemicals, and (4) estimate the radiological source term being sent for disposal. Soil samples shall be taken from trenches or continuous core borings to make sure samples are collected from the gray layer. The number of samples to be taken shall be based on MARSSIM recommendations for a Class 1 final status survey. Soil samples shall be analyzed for Ra-226 by gamma spectroscopy in an analytical laboratory accredited by the DoD Environmental Laboratory Accreditation Program

(ELAP). Chemical soil samples shall be analyzed for OMCC chemical contaminants of concern in an ELAP accredited laboratory. The radiological and chemical pre-excavation sampling results will be used to prepare waste profiles for disposal. Areas where the sample results show

Ra-226 exceeds the cleanup level shall be excavated. (CDRL A007h)

4.3 Engineering Study for B690

The Contractor shall perform an engineering study to determine how best to excavate in and around B690. For the purposes of this SOW, the term excavate is used to mean removal of the contaminated soil from the site. It is not meant to require or imply the use of any specific methodology. The Contractor shall be responsible for selecting an appropriate methodology and obtaining approval for it from the Air Force and regulatory agencies. The Contractor shall perform a radiation scoping survey to determine which parts of the OMCC beneath B690 are contaminated either before or as part of the engineering study (see Section 4.2 of this SOW).

The engineering study must document a technical approach to remove contaminated soil beneath

B690, perform a MARSSIM final status survey of beneath the building, and preserve or restore the functionality, structural integrity, and appearance of B690. At a minimum, the study must address the following:

• How the Contractor will decide what parts of the OMCC inside B690 to excavate, and if any areas of the OMCC under B690 are not to be excavated how it can be demonstrated that the remediation beneath B690 meets the requirements of the FoSS ROD

• How the structural integrity of B690 will be maintained during the excavation, final status survey, and backfill

• Whether the soil beneath the eight structural supports…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .