Final RFP Industry Questions Answers - 20120726.xlsx

XLSX spreadsheet 35 KB Posted

Attached to
Pre-Solicitation Conference (Industry Day)
Solicitation number
FA8823-12-R-0004
Issued by

About this file

GCS - Spreadsheet Final RFP Industry Questions Answers This is an ongoing spreadsheet of the questions and answers regarding the GCS Final RFP. The Government initially posted questions 1 through 66. This spreadsheet covers those questions/answers and continues to Question 94.

View the file

Other files

File Type Posted
FBO_Synopsis_GCS.docx DOCX document
SRS-MOST-555-1.pdf PDF
icd_gps_202c-1.pdf PDF
31S5-2FSQ217-2.pdf PDF
ss-pte-615_b.doc DOC document
SS_GIN_660.pdf PDF
31S5-2FSQ-217(T1)-6WC-1.pdf PDF
ICD-CS-605_Rev_B.doc DOC document
TAT2 description.docx DOCX document
MOW description.docx DOCX document
31S5-2FSQ217-01.pdf PDF
mg50539000013e5_new.doc DOC document
31S1-2FYN1-06.pdf PDF
31S5-2FSQ217-6WC-2.pdf PDF
31S1-2FYN1-6WC-1.pdf PDF
31S5-2FSQ217(T1)-2.pdf PDF
ss-sys-600_e.doc DOC document
31S1-2FYN1-2.pdf PDF
mg50539000013e2_e.doc DOC document
SS_GIN_660_25 Jan 11signed.pdf PDF
31S1-2FYN1-1.pdf PDF
mg50539000013e5_new_appendix_a.doc DOC document
mg50539000013e6_b.doc DOC document
31S5-2FSQ217-06.pdf PDF
31S5-2FSQ217(T1)-1.pdf PDF
31S5-2FSQ217(T1)-06.pdf PDF
31S5-2FSQ217-6WC-1.pdf PDF
Amended RFP coverletter and final changes.pdf PDF
GCS Amend 1 dtd 13 Aug 2012.pdf PDF
Final RFP Industry Questions Answers —
SS_GIN_660_25 Jan 11signed.pdf PDF
Final RFP Industry Questions Answers —
GCS Section L Volume Matrix Table - 20120731.docx DOCX document
CTO 08-005.pdf PDF
SS-CS-800F.docx DOCX document
GSMS-IM-01.pdf PDF
ATO IATO CHART.docx DOCX document
Final RFP Industry Questions Answers - 20120723.xlsx XLSX spreadsheet
Notice of Solicitation Ltr GCS.pdf PDF
GCS FA8823-12-R-0004.pdf PDF
Responses.docx DOCX document
2SOPS-OLM-DM-WI-202_Manual_Repro_Data_Sync.doc DOC document
2SOPS-OM-AEP-WI-202_Virus_Workstation-Scan_Media.doc DOC document
2SOPS-OM-AEP-WI-201_Oracle-Backup_Logs_for_DBA.doc DOC document
GCS Release.docx DOCX document
MIL-STD-461F.PDF PDF
SMC-S-021_15SEP2009.PDF PDF
MIL-HDBK-29612-4A 1 .pdf PDF
DoD 5220.22-M NISPOM.pdf PDF
20120201 PPP Letter to Industry.pdf PDF
Show 40 more

Latest 50 of 118 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Item #Section/SourceParagraphPageQuestion:Government Response:
1Attachment 2 and Bidders LibraryAllThe PWS on page 2 specifically states that “The scope of this contract does not include LADO”; however, on the first tab of file "GFE_BMOSC_GSF_TSTS_06202012 for BL.xlsx" (copied for use as Attachment 2) there are listed 187 LADO items, 4 LADOBU items and 114 LADOTR items. Please confirm that it is now the Government's intent that these 305 LADO items are to be maintained as part of the OCS work scope.No. All references to LADO equipment are incorrect. Those pieces of equipment will be maintained and sustained on a different contract. The GFE list in the RFP will be amended to remove all LADO items.
2Bidders LibraryNAFile "IIF Contract Attachment 6A.doc" concerns the space segment. As such, is it safe to assume the Ground Control Segment Sustainment contractor will not be required to use/maintain anything related to this document or other Bidder's Library documents that concern the space segment tools and infrastructure?Correct. The Bidder's Library is a repository for informational purposes provided to assist the potential offeror in the view of the work required to accomplish the contract. If the potential offeror does not believe a particular file or piece of information is of value in their preparation, then they may feel free to disregard.
3Attachment 38Table 2 of Attachment 3 lists monthly T1 line leases from Colorado Springs to both Huntington Beach, CA and Gaithersburg, MD. These appear to be lines between incumbent contractor facilities and incumbent contractor and subcontractor facilities. Please confirm that it is the Government’s intent and requirement that the successful contractor, if other than the incumbent, maintain these same T1 lines. If so, is the Government specifying the use of Sprint or are alternative carriers permissible?No. The lines from Colorado Springs, CO to Gaithersburg, MD will not be maintained under this contract. The Government will update Attachment 3 to delete the references to the Gaithersburg connections. The Government will publish an amended Attachment 3. The Government expects the line from Colorado Springs, CO to Huntington Beach, CA to be maintained by the successful contractor. The Government will not specify which carrier the contractor employs for this circuit.
4Section B2-12With respect to CLINs 0002, 1002, 2002, 3002, 4002, and 5002 the statement is made “The estimated annual value of this CLIN (including all ODCs) is $3M ($3,000,000.00)”. Please confirm that it is now the Government’s intent that all bidders use this as a Government stipulated price for the aforementioned CLINs and that such figure is to be entered by all bidders for those CLINs in section B.Correct.
5Section MParagraph 2.1.4.19Please confirm that the cost type CLINs 0002, 1002, 2002, 3002, 4002, and 5002 are not included as part of the Total Evaluated Price.Correct.
6Section MParagraph 2.1.4.29How does the Government intend to use the price reasonableness evaluation performed pursuant to this paragraph when paragraph 2.1.4.1 of Section M states that the total evaluated price is the price proposed by the offeror?Price reasonableness is addressed as stated in Section M, Paragraph 2.1.4.2.1.
7Section B11Please explain the purpose of CLIN 5005 as there is very little descriptive data. Is this intended to be a placeholder for options beyond option year 5 (also see Section I, FAR 52.217-9(c) which appears to limit the contract to 6 years total)? Lastly, are bidders to propose any pricing for this CLIN or are we directed to leave it blank?Section L, paragraph 3.3.5 clearly states the potential offeror is to fill out Section B and Table 2, GCS Proposed Pricing, for all options, to include CLIN 5005. The descriptive data for CLIN 5005 references FAR 52.217-08 which provides for up to six months extension.
8CDRL A013NAPlease provide all current ATO and IATO dates applicable to GCS.Agreed. The Government will provide current ATO and IATO dates applicable to GCS and post to FBO; however, as stated during previous question and answer sessions those dates may change multiple times prior to contract award.
9ATT 3

Section L ATT 3

Paragraph 2.11.2.3 5,12

These pages in Attachment A require an estimated cost for specific CDRL items; however, all data and reports CLINs in Section B are designated “NSP”. Does the Government still require cost data on Attachment 3 if the purpose of Attachment 3, as stated, is to identify the rights that the US Government will acquire?Yes. All costs for CDRLs should be part of CLIN XXX1 series.
10Section LGeneralNAWill the Government allow contractors to engage Ogden ALC to participate in their proposal development (beyond provision of their labor rates and review/execution of SPA, PA, and IA)?That is up to the Ogden ALC. Ogden ALC should be treated no differently than any other subcontractor for this effort.
11Section LParagraph 3.1.49What does the Government consider to be the difference between the small business participation plan and the small business subcontracting plan? Aren’t these supposed to be one and the same?In response to a solicitation requiring the submission of a subcontracting plan (above $650K), all offerors (with the exception of small businesses and those large businesses who are participants in the DoD Comprehensive Subcontracting Plan (CSP) Test Program) must submit either a master plan with goals for the instant procurement or an individual plan for the instant procurement. Small businesses are exempt while those in the CSP submit a copy of that document which is negotiated annually with the DCMA. The CSP consolidates all the performance data across the participant's entire suite of DoD contracts. Whereas the individual and master plans provide requirement-specific data on how well the prime is meeting his/her small business participation obligations, the CSP does not. To obtain this type information, the DoD has implemented use of the "participation" plan. There are no prohibitions from requesting this information from small businesses and those in the CSP. The information provided is basically the same. In fact, the numbers in the subcontracting plan, should be mirrored in the participation plan. Whereas only large business is required to provide a subcontracting plan (whether it be of the Individual, Master or CSP variety), when implemented, ALL offerors (regardless of size) must submit a participation plan.
12Section MParagraph 2.1.4.19In the response to DRFP Question 193, the Government stated the following “The Government intends to evaluate the offeror's plan to transition those requirements as outlined in PWS 3.8; however, any transition costs associated with the potential move of those assets is not evaluated as part of the Total Contract Value.” Review of the final RFP in Section M, Paragraph 2.1.4.1 indicates that there is no provision to remove transition costs proposed as part of the Section B, CLIN 0001 price and, therefore, such transition costs would end up being included as part of the Total Evaluated Price. Will the Government revise Section M to accommodate their intent to exclude transition cost from price evaluation as clearly stated in the response to DRFP Question 193?All tasks in PWS 3.8 are for transition purposes only. The work associated with sustaining, maintaining and operating those assets are clearly defined in other task within the PWS. The potential offeror should not inlcude the price associated with transition tasks in PWS 3.8 in their total evaluated price; however, for clarity the Government is expecting labor hours and an estimate price associated with PWS 3.8 as part of their phase-in plan and will not be evaluated. The Government will update Section L, paragraph 3.1.1 to read: "The Offeror shall provide a single integrated phase-in plan with schedule milestones that will be placed on contract as binding upon award. The plan shall address all phase-in requirements in the PWS as described below. The plan shall include labor hours and an estimated price for each transition task which may be put on contract after award." The Government will also update the descriptive data in section B to exclude PWS 3.8 from the total evaluated price and amend the RFP.
13Section LTable 1 (Volume Matrix)4Should the attachments listed after Volume IV, Price Volume be included at the end of Volume II, Technical?Yes. The Government is adding clarification in the VM table to show which attachments are for the Technical Volume.
14Section LParagraph 3.1.2.17This requirement directs the offeror to provide job requisitions. Please confirm that offerors may provide a single set of unique job requisitions in support of the entire list of PWS tasks (with each unique requisition provided only once). The alternative would result in the provision of many duplicate job requisitions for technical positions. Furthermore, what information does the Government require be provided within each individual requisition (e.g. position number, position title, required experience and education, etc.)?Correct. The Government will accept job requisitions for each unique position only once if the potential offeror can meet the evaluation criteria outlined in Section M, paragraph 2.1.2.2. The Government will not dictate what information the potential offeror provides to prove they meet that criteria. The potential offeror can be as detailed as necessary to meet the requirements.
15Section LParagraphs 3.1.3.6 through 3.1.3.108-9Attachment 3, when completed, will be 16 pages long. Is this to be included as part of the Technical Volume or as a 7th technical process approach attachment. In either case, will the page count be adjusted to accommodate addition of Attachment 3?Thank you for pointing this out. First, this will be added to Section L, Table 1 - Volume Matrix, as an additional Technical Process Approach and the page limit will be updated to include these 16 pages. The Government will post an updated Section L to FBO.
16PWSParagraph 3.4.621This states in part “Contractor will ensure problems accounted with ClearQuest are documented and corrected as needed”. Is this standard referring to all GCS PRs that are accounted for within the CQ database or to all problems encountered with the ClearQuest tool itself”?Thank you for pointing this out. The Government will update the standard within PWS 3.4.6 to read: "Contractor will ensure problems encountered within ClearQuest are documented and corrected as needed" because this task was specific to maintaining the ClearQuest tool vice GCS system PRs.
17Section LParagraph 2.83Format for proposal Parts II and III: Line spacing is not prescribed. Does the government want open text double-spaced? Can text in charts, tables and diagrams be single spaced with font size smaller than 12 point?The Government will update Section L, paragraph 2.8.3 to provide clarification for the potential offeror. This update will include line-spacing expectations and font size regarding charts, tables and diagrams. The potential offeror must ensure legibility at all times.
18PWSParagraph 2.8.75Language only requires ACA with Raytheon corporation. Is ACA required with Boeing and Lockheed SV contracts to obtain current CML and OOH information for GPS IIF and GPS III vehicle or will that data be delivered as GFP?No. The Raytheon ACA is the only required ACA. Any other ACA(s) in which the potential offeror chooses to enter is at the discretion of the potential offeror.
19Section LPast PerformanceVerbal Question via Telephone Call: Mr. Cournoyer was the PCO on a former contract. Should we send the questionnaire to him?Yes. He will forward the questionnaire to a responsible party to provide the response.
20Section LTable 1 (VM) 3.1.3.2 3.1.3.3 and answer to Question #19May we assume that you wish to have all plans as appendices to the technical volume: ? CTE Relocation, GA Test Asset Transition, GSIMS Transition, Personnel facilities, ClearQuest/ClearQuest transition, Configuration Mgt, Software Development, and EDLM/UDLM, Small Bus Contracting, SPA for GCS SW maintenance, PA for GCS SW maintenance, and Public-Private Implementation agreementYes. The Government is adding clarification in the VM table to show which attachments are for the Technical Volume.
21Section L3.2.4Is it correct to assume that the government desires the past performance letters of consent to be attached to the Past Performance Volume III rather than the Technical Volume II?Yes. The Government will update the VM table to inlcude this as an attachment.
22Section L3.1.3.6-3.1.3.10Can we assume that Attachment 3 is not considered part of the 50 page total for the technical volume?This will be added to Section L, Table 1 - Volume Matrix, as an additional Technical Process Approach attachment and the page limit will be updated to include these 16 pages plus an additional 4 pages for contractor use. The Government will post an updated Section L to FBO as an amendment.
23Section L2.8.5.3 & Table 1Guidance from Section L Table 1 indicates a total page count for Volume III, Past Performance not to exceed 30 pages (10 x 3), but there is no provision for an introduction, a list of contracts, and rationale for relevancy, only individual PIF pages. Can the Offeror use content within the 30 pages of Vol III for an introduction and summary information on past performance citations?Yes. The potential offeror can use the 30 pages as they see fit. 30 pages is a not to exceed number.
24Section L3.1.2.2Is the intent of the direction in 3.1.2.2 for us to state our process and plan for issuing contingency offers to GCS candidates and adhere to the intent of 52.222.46?Yes.
25Section L3.1.4 Subfactor 4For the purposes of this submission, may we assume that the 20% small business based upon TCV is equivalent to the FFP CLIN x001?Yes.
26Section L1.2; 3.1.3.6Regarding Attachment 3, Data rights, is it correct to assume that this attachment is part of the Executive Summary/Contracts Volume I?No, it is an element of the technical volume. The Government has updated the VM table for clarity.
27Section L3.1.1Can the Gov clarify to what level "specific steps" is deemed acceptable? As an example, one cannot provide detailed steps such as disconnect W# from J# on equipment A# without engineering drawings.The acceptable level of "specific steps" may be defined as that which is measurable proof that the offeror can provide distinctive and unmistakable evidence to execute the plan.
28Section L3.1May we assume that the technical risks requested is only applicable to Subfactors 1 through 3?Yes.
29Section M2.1.2.1.3PWS 3.8.3 calls out that GSIMS will be moved in 5 or 15 calendar days rather than section M 30 or 60 days. Which is correct?Section M 2.1.2.1.3 calls for a GSIMS transition plan within 30 or 60 days. PWS 3.8.3 calls for the actual transition period of GSIMS in 5 or 15 days.
30Section M2.1.2.3Can the Gov elaborate on the definition of what is considered acceptable "clear understanding" related to all plans?"Clear understanding" may be defined as proof that the offeror can provide distinctive and unmistakable evidence to support the contract plans. It is up to the potential offeror to convince the Government in any means necessary they can meet this requirement.
31PWS2Can the Gov elaborate on what is meant by "All ambiguities in this PWS shall be construed against the contractor"?The Government will remove this sentence as it is ambiguous and will publish an update PWS to FBO.
32PWS3.3.1Is it correct to assume that the reference to use TMO is for AMC flights only and any commercial flights may use the companies standard travel processes?Yes.
33PWS3.4May we assume that all currently used licenses are grandfathered and approved regarding the text in paragraph 3.4?Yes.
34Section L3.1.1Given that the RFP defines no potential or known ongoing activities that will run into 2013, our assumption is that the transition of any ongoing modifications and software release activities, if any, is not addressed within the requested phase-in plans. Is this a valid assumption?Yes.
35PWS3.11.10Can the Government identify the product of preference? If so, please identify?The current product being used is RETINA. An acceptable alternative may be chosed off of the SCAP product listing provide by DISA. However, the DOD may replace RETINA with NESSUS in the future.
36Section M2.1.2The rating guidelines for “Acceptable” and “Unacceptable” do not define the “acceptable” risk level. Please define acceptable risk. For example, is an acceptable risk level where the risk of unsuccessful performance is low or is it where the risk of unsuccessful performance is no worse than moderate (low/moderate as defined in DoD Source Selection Procedures Table 3)?We will not define acceptable risk. It is defined as written in Section M.
37Attachment 3The costs for data rights are allocated to cost reimbursable CLINs and is not considered as part of the total evaluated price (FFP CLINs: At the total price proposed). Unlike COTS and sparing costs, data rights and their costs are potentially unique for each offeror. Therefore, we recommend the government include the data rights cost as part of the total evaluated price as the true indicator of offeror specific prices.The costs for data rights are not part of the total evaluated price. The Government wants the information in Attachment 3 to validate our cost reimbursement estimate of $3M.
38Section BWill additional CLINS be added to the model contract post award to handle transition (PWS 3.8) and modifications (PWS 3.9 & 3.5.4) costs?Yes, when applicable.
39Section BCLIN0001To have Section B consistent with response to Question 193 and as included in the option year x001 CLINS, we suggest the following be included in the CLIN0001 description: This period CLIN excludes PWS paragraph 3.8.The Government will update the descriptive data in section B to exclude PWS 3.8 from the total evaluated price and amend the RFP.
40Attachment 4PP QuestionnaireThe attachment doesn’t have a place to identify the Company or Contract ID. Can we add two lines page 1 of the questionnaire to include this information request?Yes.
41Attachment 4Cover LetterCan the email address for Mr. Rodney Houser be clarified as ending with a 1 (one) or an L?The character in question is the number 1, not an alpha "l."
42PWS3.419As per PWS 3.4"The contractor shall ensure that there is no functionality in the reusable software component that would inhibit operation unless explicitly specified and approved by the Government. This provision includes, but is not limited to, the periodic need to enter in a license code or the presence of a physical key or similar device to enforce licensing conditions." Do all existing software products currently used on the program meet this requirement? 2. What process is in place to get Government approval should the need arise?Yes. The process is for the contractor and Government software representatives to resolve any issues that arise. If the need arises for purchase, update or replacement of licenses this would be handled under the cost reimbursable part of the contract.
43PWS2.8.19Section 2.8.7 of the PWS only lists Raytheon for ACA. The draft RFP had a longer list of ACA's called out. Is Raytheon the only one required? Does ACA need to be executed prior to contract award on upon contract award? What about agreements with other contractors to cover Boeing GPS IIF & IIA, and Lockheed Martin GPS IIR-M? Will those agreements be pursued in the future?The Raytheon ACA is the only required ACA. Any other ACA(s) in which the potential offeror chooses to enter is at the discretion of the potential offeror. The ACA with Raytheon SHALL be in place no later than contract award.
44PWS3.11.938As per the DRAFT RFP Q&A, 3.11.9 had two releases per year independent of the software releases in 3.4.5 is this still true?Yes.
45PWS3.7.228The standard for section 3.7.2 of the PWS indicates that the TAT2, MOW and Almanac PC in MOD 17A hardware and software must be consistent and compatible with providing a high fidelity replica of the existing operational system 100% of the time. Does the existing system meet these requirements?
Yes.
46Section L3.1.2.1Section L 3.1.2.1 states "Provide the job requisitions for the technical and management staff..." As per the Draft RFP Q&A, are the job requisitions required for subfactor 2 still an attachment to the Technical Volume and not part of the 50 page technical volume?Yes. The Government has updated the VM table to reflect these as attachments to the technical volume.
47Section L3.1.2.2Section L 3.1.2.2 States "Provide clear evidence (hiring procedures, retention statistics, contingency offers to potential employees, etc.) that demonstrates the Offeror has the ability to obtain the proposed staff to accomplish the skills required to perform all the tasks in the PWS." Does the Government wish the copies of the hiring procedures, retention statistics; contingency offers to potential employees, etc. attached as a new appendix to the Tech volume not covered by the page counts already defined?Yes. The Government is adding clarification in the VM table to include additional attachments for critical staffing for the Technical Volume.
48Section L Section M3.1.3.10 2.1.2.3.69Section L 3.1.3.10 States "To ensure that the parties will maintain proper configuration control of all licenses throughout the performance of the resulting contract, the contractor shall create an “Appendix A‖ to GCS Attachment 3 with a separate tab for each vendor listed in Table 2." Is this an attachment to the Technical Volume or Model contract and doe this apply to the other tables required under Attachment 3?The potential offeror should treat this as an attachment to the Technical Volume and follow the updated VM table for page counts.
49Section L3.1.3.16SMC-S-012 Section 6.5 , Tailoring Guidance indicates that the standards and DIDs should be tailored to the specific requirements of a particular program, program phase, or contractual structure. It also states that care should be taken to eliminate tasks that add unnecessary costs and data that do not add value to the process or product. Will the government be providing tailoring guidance for SMC-S-012? Will the government accept suggested tailoring, will that be allowed?
No, the Government has already provided tailoring guidance in the PWS. However, the Government will welcome any suggested tailoring from potential offerors up until 10 August 2012. The Government reserves the right to approve/disapprove any suggestions.
50Section L3.2.310Section l 3.2.3 states "If a teaming arrangement is contemplated, the Offeror shall provide complete information as to the arrangement, including any relevant and recent past performance information on previous teaming arrangements with same partner. If this is a first time joint effort, each party to the arrangement must provide a list of past relevant contracts." Where Is this attachment to be placed ?This attachment shall be placed as part of the Past Performance Volume. The Government will update the VM table to include this attachment.
51GeneralAs per the Q&A from the draft RFP, Can graphics, Tables, Job Descriptions, etc. still be as small as 8 point font?The Government will update Section L, paragraph 2.8.3 to provide clarification for the potential offeror. This update will include line-spacing expectations and font size regarding charts, tables and diagrams. The potential offeror must ensure legibility at all times.
52Section B2-10Section B has a reference to Clause H104. Did the Government intend to reference Clause H 102, Travel, Material, Licenses, Service Contracts, Warranties, and Subscription Services?Thanks for pointing this out. The Government also recognized this discrepancy and will update the descriptive data for H002.
53Attachment 313Attachment 3, page 13, paragraph d. (2) refers to CDRL A019. Did the Government intend to reference CDRL A016, Software Release Packages rather than CDRL A019, Small Business Participate Report?Thanks for pointing this out. The Government will update Attachment 3 will replace CDRL A019 with CDRL A016.
54H-8SMC-S-012SMC-S-012 Section 6, Schedules and activity network, of the SDP Template found in Appendix H of SMC-S-012 calls for a schedule identifying the activities in each build along with other activities. Would the government accept a reference to the sample schedule call out in section L & M as fulfilling this requirement?Yes.
55PWS4.141PWS Section 4.1 System Safety states "… A draft version of Task 102 in accordance to DID-SAFT-81626 presented in contractor format shall be included with the proposal for review…" Is this attached to the Tech volume and a new attachment?Yes. The Government has updated the VM table to reflect these as attachments to the technical volume.
56Section M2.1.2.1Will the government clarify that the Phase-In activity begins at Authority to Proceed/Contract Start Date, not award date?Yes.
57Section I29The H115 special OCI Clause was deleted from the Final RFP, but the AFFARS 5352.209-9000 ALT VI OCI provision "precludes" the Contractor "for the life of the 'system' from award of a DoD contract to supply the 'system' or any of its components." On its face, this SETA-like clause appears appropriate perhaps for the Government Technical Group, but not the Contractor or Subcontractors performing Operation & Maintenance work in the Control Segment, according to the PWS. The AFFARS OCI clause is also inconsistent with the DFARS 252.209-7009 (Dec. 2010) policy disfavoring avoidance. Further, 5352.209-9000(a)(1) defines the "system" as "the system that is the subject of this contract." Please define the term "system." Please also confirm that the Government does not define the term "system" to encompass the entire GPS enterprise, and that the Contractor would not be precluded from future GPS enterprise competitions in the Space, Control, or User Segments, upon an approved mitigation plan if required.The Government will remove this AFFARS clause and amend the RFP.
58Section L4Section L, Table 1 Vol Matrix calls out the Small Business Plans and the PPP agreements to be submitted. Please clarify where this plan should be located.Those shall be attachments to the technical volume. The Government will update the VM table to reflect this change.
59Section B11Can the government please clarify the intent of CLIN 5005 "Option to Extend Services" and define the POP and value that should be placed in the Total Item Amount column?Section L, paragraph 3.3.5 clearly states the potential offeror is to fill out Section B and Table 2, GCS Proposed Pricing, for all options, to include CLIN 5005. The descriptive data for CLIN 5005 references FAR 52.217-08 which provides for up to six months extension.
60Section B2The government has provided an estimated annual value of $3M for the cost reimbursable basic ODC CLIN 002 and all follow on option ODC CLINs 1002 through 5002. If the contractor detail pricing produces a different amount, should that value or the Government estimate be utilized in the proposal response?It is the Government’s intent that all bidders use $3M as a Government stipulated price for the aforementioned CLINs and that such figure is to be entered by all bidders for those CLINs in section B.
61Section M8Paragraph 2.1.4, Price Factor, indicates that the Government evaluation on price will only be against FFP CLINs. There could be a substantial variation of material/ODC estimates between bidders based on their understanding of the RFP requirements, program execution approach and each bidder's ability to obtain the lowest pricing for this program. Please provide the Government's rationale for not including the price estimate of material/ODCs as part of the basis of this LPTA award.The Government decided to remove the ODC CLIN from the Total Evaluated Price because the Government must pay all reimbursables that the potential offeror incurs. The $3M is a Government estimate to be used by all potential offerors.
62Section LAs per the Q&A from the draft RFP, Can graphics, Tables, Job Descriptions, etc. still be as small as 8 point font?The Government will update Section L, paragraph 2.8.3 to provide clarification for the potential offeror. This update will include line-spacing expectations and font size regarding charts, tables and diagrams. The potential offeror must ensure legibility at all times.
63Section B“The government has provided an estimated annual value of $3M for the cost reimbursable basic ODC CLIN 002 and all follow on option ODC CLINs 1002 through 5005. If the contractor detail pricing produces a different amount, should that value or the Government estimate be utilized in the proposal response?”It is the Government’s intent that all bidders use $3M as a Government stipulated price for the aforementioned CLINs and that such figure is to be entered by all bidders for those CLINs in section B.
64Bidders LibraryWhile attempting to obtain License, Warranty, and Maintenance costs from the list provided by the Government in the Bidder’s Library, it was brought to our attention that additional data is required for some vendors to adequately cost said Licenses etc. Additionally, other vendors recognized that this was for GPS and indicated that the quantities aren’t accurate according to their current records. To expedite a compliant proposal response to the Final RFP, would the Gov consider allowing the $3M annual material allotment to be a plug number whereby all offeror’s bid the same $3M material cost?It is the Government’s intent that all bidders use $3M as a Government stipulated price for the aforementioned CLINs and that such figure is to be entered by all bidders for those CLINs in section B.
65Attachment 3Table 2Would the Gov consider that Table 2 of the Attachment 3, Data Rights be filled out within 30 days of contract award given one cannot currently obtain vendor quotes without all necessary data?No. The Government would like for the potential offeror to fill out Table 2 as required. If the winning contractor has to update that information post contract award the Government and winning contractor will address the issue at that time.
66Section ICWith respect to AFFARS 5352.209-9000, Organizational Conflict of Interest (OCT 2010) - ALT VI (OCT 2010), from the Hill website, the text reads "Interim Change: see OCI Policy Memo 10-C-15." Is this the document we are to reference for OCI considerations rather than the Oct 2010 clause?Yes. 5352.209-9000 will be removed from the amended RFP.
67CDRL A007 PWSParagraph 3.11.938CDRL A007, Block 16 says vulnerability patch releases are to be performed “at least every 6 months” and “antivirus signature releases at least every month”. PWS 3.11.9 says to “Deliver fully tested vulnerability patch and virus signature releases approximately twice annually”. Please clarify the frequency requirement for antivirus signature releases?CDRL A007 is only the quarterly report summarizing the vulnerability patches and antiviruis signature updates availalble and a schedule of those deliverable. The Government expects to only release those products approximately twice annually.
68CDRL A010 PWSParagraph 3.11.1039CDRL A010, Block 10 says Vulnerability Scan Reports are to be delivered semi-annually. PWS 3.11.10 Performance Standard says vulnerability scans are to be performed monthly. Please clarify the frequency requirement for vulnerability scans and associated reports?The PWS standard is correct for the scans to be performed monthly. The CDRL is correct in requesting the reports semi-annually.
69PWSParagraph 3.7.428Please confirm that the requirement to “Operate CTE 0600-1700 (MT) and TSTS 0600-1700 (MT)…” is only applicable Monday through Friday.Correct. The Government will update the PWS 3.7.4 standard to include Monday through Friday as the applicable work days. The 600 hour surge capability is for hours outside of the normal duty hours listed.
70Bidders libraryICD-GPS-804This document references a requirements document SS-CS-800 which is not found in the bidder’s library (note SS-CS-600 is in the bidder’s library). Will the Government please add the document to the bidder’s library?The Government will add the SS-CS-800 to the Bidder's Library.
71Bidders libraryGPS-SW-OP-00 (Depot Software Maintenance)This document references Operational Procedure, GSMS-IM-01 (Information Assurance Vulnerability Management Process). Will the Government please add the document to the bidder’s library?The Government will add OP GSMS-IM-01 to the Bidder's Library.
72Bidders libraryGPS-SW-CM-01 ( Depot Software Maintenance CM Plan)5-6Please confirm that the “COTS and Media Management Tool” referenced in Table 2-3 will be made available to the successful bidder as GFE. Also, please confirm that any databases for the tool that contain current COTS/Media/License data will also be made available as GFE.That is correct.
73Section MParagraph 2.1.3.2.2, Table 37PWS paragraph 2.4.2 and Section L, paragraph 3.1.4 require the subcontracting of at least 20% of the contract value to small business. Section L, paragraph 3.2.2 requires that we include the past performance references of teaming partners and significant subcontractors that we consider most relevant in demonstrating our ability to perform the proposed effort. Given the aforementioned requirements, a fair number of our key team members are small businesses that have highly relevant Air Force and SMC past performance references. Unfortunately, the relevancy requirements in Section M call for a reference to have an annual value of $15M to be considered “relevant”. Most small businesses under a $25M size standard would not be small businesses if they had past performance references of this size. As such, would the Government consider waiving the $15M annual revenue relevancy requirement for citations from small business teaming partners? Furthermore, such small business entities are not required to further subcontract to small businesses per the FAR. As such, would the Government consider waiving the small business participation relevancy requirement for citations from small business teaming partners?The $15M cost/price threshold only applies to the potential prime offeror.
74Attachment 3Paragraph (2)(vi)6-7Paragraph (2)(vi) states that, should the Government use, release or disclose the commercial item technical data, computer software, or computer software documentation in a manner that violates the terms of the licenses listed in Table 2, the Government shall not be required to de-install and stop using the items or return them to the Contractor, and the Contractor’s remedy shall be limited to monetary damages. Please clarify that it is the Government’s intent that should the Government cause any violation of license agreements, that the Government will accept a Request for Equitable adjustment and fund the Contractor for said monetary damages.Only if the Contractor's Request for Equitable Adjustment (REA) demonstrates the existence of liability, causation and damages will the Government grant the Contractor an equitable adjustment.
75Section LTable 1 and Paragraph 3.1.44The Small Business Participation Plan is included in both the Technical Volume which has a 50 page limit and as a separate document with “No Limit”. Which is correct? Also, please note that the paragraph 3.1.4.1 noted as the referenced section L requirement for the Small Business Participation Plan version listed as a separate document does not exist.Thanks for pointing this out. The Government understands where potential offerors can be confused by this. The Government's intent was for the potential offeror to summarize their Small Business approach in the Technical Volume, which would be part of the 50 page limit, and attach a Small Business Participation Plan & a Small Business Subcontracting Plan, which would have an unlimited page count. Additionally, the Government will update Section L to capture accurate paragraph numbers. NOTE: The Government will also update Section L to clarify the same construct for Public-Private Partnering.
76Attachment 3 Section LTable 1, Column 4 and Table 3, Column 3 Paragraphs 2.11.2.3, 3.1.3.7, and 3.1.3.85, 12 5,8The figures for table 3, column 3 are defined as “direct cost” whereas the figures for table 1, column 4 are just defined as “estimated cost” without any qualification (e.g. direct, fully loaded, etc). Please clarify the direction for table 1, column 4. Should it be the same as table 3, column 3 (i.e. direct cost)?Yes. Both column 3 of Table 3 and column 4 of Table 1 are entitled "Estimated Cost" -- not "direct cost". The question appears to be referring to Section L-3.1.3.7, which states that "estimated cost" in Table 3 = "only direct costs" vice Section L-2.11.2.3 which does not define the term "estimated cost" in the context of Table 1. To clarify this ambiguity, the RFP will be amended to state as follows: "L.2.11.2.3. Insert a proposed estimated cost into each cell in Column 4 of that table for those items of data or computer software associated with that item's corresponding cell in Columns 1-2 including only direct costs. (As used in this subsection, the term "direct costs" is defined as the cost/price to be charged the Offeror by a prospective subcontractor excluding any overhead or G&A the Offeror anticipates expending to acquire that noncommercial item technical data, computer software or computer software documentation from that prospective subcontractor.) Because CDRL A016..."
77PWS Section LParagraph 3.12.3 Paragraph 3.3.440 11-12There is a conflict between the Government directed start and end dates for staffing in PWS paragraph 3.12.3 and Section L 3.3.4 as they relate to the requirements of PWS Paragraphs 3.12.1 to 3.12.3 and 3.12.6. Does the government require that the bidders staff the requirements from June CY13 to Jun CY 16 (per Section L, paragraph 3.3.4 direction) or does the government want the bidders to staff the requirements from GCS contract start (January CY13) for approximately 36 months (per PWS 3.12.3 direction)?The Government recognizes the conflict between the PWS and Section L. The dates in Section L are the most current based on the latest schedule from OCX. The Section L language says to assume those start dates as OCX Transition dates are out of our control.
78PWS Section LParagraphs 3.12.4 and 3.12.5 Paragraph 3.3.440-41 11Please confirm that the OCX Transition period is August 2015 to January 2016 as stated in Section L, paragraph 3.3.4. Furthermore, is the on-call support required only during that OCX Transition period or also required during the entire 36 month period beginning June 2013 and in the remaining option periods beyond CY 2016?At this time the OCX transition period is August 2015 through January 2016. All on-call support is documented in specific tasks of the PWS 3.12
79Section LParagraph 3.3.411-12The last sentence in Section L3.3.4 directs the bidders to "For the remaining option years price the OCX transition tasks identical to the way the Offeror priced CY16." On PWS paragraphs 3.12.1 to 3.12.3 and 3.12.6, we believe the intent of the government is for bidders to provide a steady state level of support to the OCX transition from 1 July 2016 - 31 Dec 2018 at the exact same level proposed for the period 1 January 2016 through 30 June 2016. On PWS paragraphs 3.12.4 and 3.12.5, we believe the intent of the government is for bidders to provide a steady state level of support to the OCX transition from 1 February 2016 - 31 Dec 2018 at the exact same level proposed for the period 1 August 2015 to January 2016. Please confirm our understanding or provide clarification of the direction.The Government expects the contractor to price option years after CY16 exactly as requested.
80PWSParagraphs 3.8.1, 3.8.3, 3.8.5, and 3.8.829-31Do any of the servers/systems to be transitioned have replicated servers/systems (i.e. for backup/disaster recovery) at a location external to the current incumbent contractor’s facility on Wooten road?Yes.
81PWSParagraphs 3.8.1, 3.8.3, 3.8,5 and 3.8.829-31For any of the servers/systems to be transitioned that do not have replicated servers/systems (i.e. for backup/disaster recovery) are they currently being backed up to tape locally?Yes. Backup/disaster recovery media are stored at an off-site, bonded storage facility.
82PWSParagraphs 3.8.1, 3.8.3, 3.8,5 and 3.8.829-31Where servers/systems to be transitioned have replicated servers/systems (i.e. for backup/disaster recovery), do they have full replication in place where all software is loaded or is it partial replication where only specific software items are replicated? If applicable, what tools are being used for replication of these servers/systems?For 3.8.1, there are multiple strings of each lab that provide full redundancy. For 3.8.3, there is no full or partial replication. The process used is to do full daily data backups which are stored in two separate off-site locations. The system has a full backup suite of hardware which can be used in the event of a hardware failure. For 3.8.5, this is not applicable because the task is for taking responsibility for GFE. For 3.8.8, there are full replications located in two separate off-site locations that would allow for full data/software/tool restoration in the event of a site failure. All disaster recovery procedures and tools are described in GPS-SW-CM-01, Depot SW Maintenance Configuration Management Plan which is located in the Bidder's Library.
83PWSParagraphs 3.8.1, 3.8.3, 3.8,5 and 3.8.829-31For servers/systems that have replicated capability, what is the acceptable outage time for any of these servers/systems to fail over/fail back?The PWS 3.8 series tasks are not day-to-day sustainment, maintenance or operations activities. These tasks are only for transition. The sustainment, maintenance and operations tasks are outlined in other PWS tasks for each specific tool/capability.
84PWSParagraphs 3.8.1, 3.8.3, 3.8,5 and 3.8.829-31Is it acceptable for replicated servers/systems to be located outside El Paso County, CO as risk mitigation in the event of a widespread natural or man-made disaster?No.
85PWSParagraphs 3.8.1, 3.8.3, 3.8,5 and 3.8.829-31Do detailed DR plans exist for any of the servers/systems to be transitioned? Do these plans include all of their applications and software?Yes to both.
86PWSParagraph 3.8.229Given there is only one Ground Antenna test asset, please confirm that outage time is acceptable when it is being moved during transition?Yes. Even the though the GA is considered as part of the CTE, the Government specifically included the PWS 3.8.2 GA transition task seperately to allow for outage time during the move.
87Given the templates for the SDP and CMP total more than 100 pages by themselves, is it fair to assume that the total page count of 100 pages for the Technical Process Approach appendices are for each plan rather than 100 pages for all four plans combined?No, it is not a good assumption. The Government would ask all potential offerors to provide enough evidence that the plans requested provide clear and convincing evidence of their capabilities to meet the requirement. 100 pages is adequate for all four plans.
88PWS, CDRLParagraph 3.11.10, CDRL 10Regarding PWS 3.11.10 “Perform network vulnerability scans” and CDRL A010, the Bidder’s Library DVD did not include CTO 08-005 or an example of an annual validation check. Will the Government provide a copy of those items and any other related references pertinent to the execution of CTO 08-005?Government will add CTO 08-005 to the Bidder's Library.
89PWSParagraph 3.10.1Regarding PWS 3.10.1, will the Government be conducting 12 POA&M reviews annually (approximately 3 per quarter), or 12 POA&M reviews each quarter (approximately 48 annually)?The Government plans to conduct approximately 12 POA&M reviews quarterly for a total of approximately 48 annually.
90PWSParagraph 3.11.3According to one of the standards in PWS 3.11.3, this task is to be completed IAW an approved IACMP (PWS 3.11.2). Does the Government desire to have task 3.11.3 begin when the IACMP is approved by the Government or to have both 3.11.2 and 3.11.3 run in parallel, knowing that the initial SSPs submitted may not be IAW the final approved IACMP?The Government expects the contractor to work both the SSP and IACMP in parallel as the SSP is a collection of the data, whereas the IACMP is the plan to manage the data in the SSP.
91PWSParagraph 3.12.1In paragraph 3.12.1, is the “one-time contractor assessment” intended to occur individually for each hardware or software change made in AEP. Would this require an assessment of the “impact to OCX” for each SCR (software) and modification (hardware) made against AEP for the duration of the contract until transition to OCX?No. The Government is not expecting the contractor to perform an assessment for each hw/sw delivery. It's a one time impact assessment of schedule impacts, risks from implementing the AEP Transition Server with AEP version 7.
92Section LParagraph 3.1.3.10Section L, 3.1.3.10 States "...the contractor shall create an ―Appendix A to GCS Attachment 3 with a separate tab for each vendor listed in Table 2. Insert into that data or computer software the Offeror will purchase from that vendor and subsequently deliver to the Government." The final RFQ response to question # 22 adds 20 pages to for the addition of Attachment 3 to the Technical volume but does not seem to add page count for the Section L 3.1.3.10 requirment. Table 2 lists 19 Vendors (tabs) with 78 individual software products with unknown pages for the each product. Is Appenpix A exempt from the 20 page limit or would this data to be required after ATP?Appendix A is exempt from the 20 page limit and the VM Table 1 in Section L will be updated accordingly.
93Section LParagraph 3.1.3.11IAW section L, 3.1.3.10 ".. Insert into that data or computer software the Offeror will purchase from that vendor and subsequently deliver to the Government." Is this a one time delivery or covered under a CDRL? If under a CDRL what number?One-time delivery.
94PWSParagraph 2.8.7This shows Raytheon in El Segundo, CA for the ACA. If this ACA is with Raytheon for GPS OCX, then we believe the correct address and point of contact under Raytheon Prime Contract No. FA8807-10-C-0001, is Raytheon Company, Ms. Darlene Blea (720) 858-5172, Email: dsblea@raytheon.com, 16800 E. CentreTech Parkway, Aurora, CO 80011.Noted. The PWS will be updated to reflected the new POC and contact information.

Sheet2

Sheet3