DRAFT_Attachment_6_GAP_CIE_Transition_SOO.pdf

PDF 131 KB Posted

Attached to
GLOBAL ADAPTIVE PLANNING COLLABORATIVE INFORMATION ENVIRONMENT (GAP CIE) SUSTAINMENT & ENHANCEMENTS
Solicitation number
FA8707-12-R-0014
Issued by

About this file

DRAFT Attachment 6 - GAP CIE Transition SOO

View the file

Other files

File Type Posted
Word_Copy_of_SF33.doc DOC document
Attachment_17_-_DO_001.doc DOC document
Post_RFP_Q A_(17_Jun_13).docx DOCX document
Attachment_13_-_Past_Performance_Client_Authorization_Ltr_(Final).doc DOC document
Attachment_17_-_DO_001.doc DOC document
Attachment_07_-_GAP_CIE_Cost_Model_(Final).xls XLS spreadsheet
Attachment_10_-_Past_Performance_Questionnaire_(Final).doc DOC document
Attachment_09_-_Past_Performance_Questionnaire_Cover_Letter_(Final).doc DOC document
Attachment_08_-_Past_Performance_Information_Sheet_(Final).doc DOC document
RFP_Ltr__-_GAP_CIE.pdf PDF
Attachment_16_-_GAP_CIE_Section_M_v3_(Final).pdf PDF
Attachment_01_-_GAP_CIE_Sustainment_SOW_v.2_(Final).pdf PDF
Attachment_05_-_GAP_CIE_Sustainment_WBS_(Final).pdf PDF
Attachment_03_-_GAP_CIE_DD254_(Final).pdf PDF
Attachment_04_-_GAP_CIE_Incentive_Fee_Plan_v2_(Final).pdf PDF
Attachment_14_-_DOL _EEOC_Clearance_Request_Information_Form.doc DOC document
Attachment_06_-_Transition_SOO_(Final).pdf PDF
Attachment_12_-_Past_Performance_Subcontractor_Consent_Ltr_(Final).doc DOC document
Attachment_02_-_GAP_CIE_Joint_Requirements-Development_Process_(Final).pdf PDF
Attachment_15_-_GAP-CIE_Section_L_v4_(Final).pdf PDF
Exhibit_A_-_GAP_CIE_CDRLs_(Final).pdf PDF
Attachment_11_-_Past_Performance_Tracking_Record_(Final).doc DOC document
Final_RFP_-_SF33.pdf PDF
GAP_CIE_Draft_RFP_Q A_(_31_May_13).docx DOCX document
GAP_CIE_DRAFT_RFP_Q A_(2_May_13).docx DOCX document
Attachment_15_-_DRAFT_GAP-CIE_Section_L_v1.pdf PDF
Attachment_06_-_Transition_SOO_v3.docx DOCX document
Attachment_12_-_Past_Performance_Subcontractor_Consent_Ltr_(Final).doc DOC document
Attachment_08_-_Past_Performance_Information_Sheet_(Final).doc DOC document
Attachment_10_-_Past_Performance_Questionnaire_(Final).doc DOC document
Attachment_13_-_Past_Performance_Client_Authorization_Ltr_(Final).doc DOC document
Attachment_11_-_Past_Performance_Tracking_Record_(Final).doc DOC document
Attachment_09_-_Past_Performance_Questionnaire_Cover_Letter_(Final).doc DOC document
DRAFT_Exhibit_A_-_GAP_CIE_CDRLs.pdf PDF
GAP_CIE_Draft_RFP_Question_ _Responses.docx DOCX document
DRAFT_Model_Contract.pdf PDF
DEMO_Day_-_Attendance_Sheet.pdf PDF
DEMO_Day_-_DR_Briefing.pdf PDF
DEMO_Day_-_Intro_Briefing.pdf PDF
DRAFT_Attachment_5_GAP_CIE_WBS.pdf PDF
DRAFT_Attachment_4_GAP_CIE_CPIF_Plan.pdf PDF
Attachment_7_-_GAP_CIE_Cost_Model.xls XLS spreadsheet
DRAFT_Attachment_15_GAP-CIE_Section_L.pdf PDF
DRAFT_Attachment_16_GAP_CIE_Section_M.pdf PDF
Notice_to_Offerors_-_Draft_Documents _Bidder's_Library _OCI.docx DOCX document
DRAFT_Attachment_1_GAP_CIE_Sustainment_SOW.pdf PDF
DRAFT_Attachment_2_GAP_CIE_Joint_Requirements__Development_Process.pdf PDF
DRAFT_Attachment_3__GAP_CIE_DD254.pdf PDF
GAP_CIE_Demonstration_-_Update_1.doc DOC document
GAP_CIE_Demonstration_Notification.doc DOC document
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GLOBAL ADAPTIVE PLANNING COLLABORATIVE INFORMATION

ENVIRONMENT (GAP CIE) SUSTAINMENT

TRANSITION STATEMENT OF OBJECTIVES (SOO)

Solicitation # FA8707-12-R-0014

Date: 21 Mar 2013

1.0. OVERVIEW

This SOO conveys the Government’s contract transition objectives as a guide to Offerors in developing their Transition Plan and subsequent proposal. The overall Government objective is to provide minimal disruption to the GAP CIE program during the contract transition.

2.0. BACKGROUND

The final software delivery under the current GAP CIE contract will be occurring when this follow-on contract is awarded. In order to maintain the software fielding tempo for GAP CIE users, Offerors must provide a smooth transition, while also beginning requirement clarification/planning for the initial software delivery under this new contract. Government

Furnished Property (GFP) will be provided for performance under this contract. It is upon the

Offeror to comprehensively bid all costs related to making the GFP available for their use, such as payment of all transportation, installation, or rehabilitation expenses.

3.0. TASKS

3.1. The Offeror shall develop a Transition Plan to meet the transition objectives outlined in

Section 4 Transition Responsibilities & Timeline Expectations. This transition plan shall be incorporated into the initial delivery order at contract award.

3.2. The Transition Plan shall include a description of the Offeror’s property management system, plan, and any customary commercial practices, voluntary consensus standards, or industry-leading practices and standards to be used by the Offeror in managing Government property.

3.3. The Offeror shall identify key personal and have qualified staff in place to execute the

Transition Plan as proposed to meet expectations as described in Section 4.

3.4. The Offeror shall be responsible to ‘stand up’ all GFP in a manner that will meet all timeline expectations in Section 4. Stand up includes all activities associated with having a fully capable

GAP CIE unclassified operational (current baseline); classified operational (current baseline); and developmental (future delivery/capability, classified and unclassified) working environments at the Contractor’s facility. The Government will supply GFP in accordance with the schedule included in Attachment 1 of this SOO.

3.5. The Offeror shall support all pre-award work IAW the GAP CIE Joint Requirements

Development Process for the first software drop delivery order under this new contract. The anticipated timeline for requesting, and submitting, a proposal is shown in Section 4.

3.6. The Contractor shall support weekly meetings with the Government Program Office to update their progress during transition.

4.0. TRANSITION RESPONSIBILITIES & TIMELINE EXPECTATIONS

4.1. NLT 7 days following contract award, the Contractor shall have their proposed key personnel, to included on-site support, in place.

4.2. NLT 7 days following contract award, initial GFP will be available for pickup at

Government facilities. Government will provide virtual image of Drop 19 (current operational baseline) including FOSS/COTS/GOTS. The Contractor shall coordinate a pick-up time with the

GAP CIE Program Management Office (PMO). The equipment will be available at the following location: 901 SAC Blvd, Suite BF19, Offutt AFB, NE 68113.

4.3. NLT 10 days following contract award, the Government will provide virtual images of GAP

CIE Drop 20 software currently going through Government testing. This will be an engineering drop; and the Government will provide a copy of the draft installation instructions for the software currently going through Government testing, and updated FOSS/COTS/GOTS for Drop

20.

4.4. NLT 20 days following contract award, the Government will issue an RFP w/draft technical requirements for the Drop 21 software delivery. The Contractor shall ensure appropriate personnel are available to support technical clarification sessions IAW the GAP CIE Joint

Requirements Development Process.

4.5. 21-50 days following contract award, Drop 21 technical requirement clarifications occur between Government and Contractor.

4.6. NLT 30 days following contract award, the second lot of GFP will be available for pickup at incumbent’s facilities. The Contractor shall coordinate a pick-up time with the GAP CIE PMO.

The equipment will be available at the following location: 4502 Maass Rd., Papillion, NE

68133.

4.7. NLT 45 days following contract award, the Contractor shall provide any draft documents that are due IAW CDRLs.

4.8. 51 – 70 days following contract award, Contractor generates and delivers Delivery Order proposal for Drop 21 software delivery.

4.9. NLT 60 days following contract award, the Government will provide the pre-production virtual image of the Drop 20 software, any available patches since the last delivery currently deployed.

4.10. NLT 60 days following contract award, the final lot of GFP will be available for transport from incumbent facilities. The Contractor shall coordinate a pick-up time with the GAP CIE

Program Management Office (PMO). The equipment will be available at the following location:

4502 Maass Rd., Papillion, NE 68133.

4.11. NLT 65 days following contract award, the Government will provide a copy of the final

Drop 20 installation instructions for the software currently deployed.

4.12. NLT 90 days after contract award, the delivery order for the Drop 21 software delivery will be awarded. The Contractor shall be capable of beginning full performance, to include staffing and GAP CIE operational and developmental working environments to complete the Drop 21 software delivery.

4.13. NLT 90 days following contract award, the Contractor shall provide any final documents that are due IAW CDRLs.

ATTACHMENT 1

Government Furnished Property (GFP)

NOTICE TO BIDDERS: THE GAP CIE GFP LIST IS CURRENTLY BE

FINALIZED. THE GOVERNMENT ANTICIPATES THE GFP LIST BEING

POSTED TO FBO DURING THE WEEK OF 25 MARCH 2013.

DAY 7 GFP

DAY 30 GFP

DAY 60 GFP