SMORS_Pre-Proposal_Conference_-_Sample_Fee_Calculation_v002.pdf

PDF 91 KB Posted

Attached to
SUSTAINMENT AND MODIFICATION OF OPTICAL AND RADAR SENSORS (SMORS)
Solicitation number
FA8707-12-R-0010
Issued by

About this file

Sample Fee Calculation

View the file

Other files

File Type Posted
Synopses_of_Contract_Award.docx DOCX document
20170125_Submission_of_Classified_Data.pdf PDF
20170125_DD_Form_254_Contract_Security_Classification_Specification.pdf PDF
CONFORMED_FA8723-17-R-0001_20170120.doc DOC document
20170120_Conformed_SF33_&_NDA_POCs.pdf PDF
CONFORMED_FA8723-17-R-0001_20170119.PDF PDF
20170119_Conformed_SF33_and_SB.pdf PDF
20170118_Cross_Reference_Matrix_Use.pdf PDF
BL_updates_12Jan17.docx DOCX document
Amendment_0003_sig_page.pdf PDF
SMORS_Amendment_0003_13Jan2017_Updated_Files.zip ZIP file
FA8723-17-R-0001-0003.pdf PDF
20170113_SMORS_AMEND_0003.pdf PDF
SMORS_2016Dec_RFP_Industry_CRM_v01_12Jan2017.pdf PDF
SMORS_2016Dec_RFP_Industry_CRM_v00.pdf PDF
20161229_SMORS_Pre-Proposal_Conference_Q&A.pdf PDF
15Dec16_preproposal_attend.pdf PDF
BL_Update_29Dec16.pdf PDF
SMORS_Pre-Proposal_Conference_Slides_v00rev004.pptx PPTX presentation
FA8723-17-R-0001-0002.pdf PDF
SMORS_Amendment_0002_Updated_Files.zip ZIP file
FA8723-17-R-0001_0001.pdf PDF
00_11_SMORS_IDIQ_ATCH09_Sec_L_v08rev000_AMD01.pdf PDF
20161214_NDA_POC.pdf PDF
SMORS_Pre-Proposal_Conference_Slides_v00rev003.pptx PPTX presentation
SMORS_Pre-Proposal_Conference_-_Sample_Fee_Calculation.pdf PDF
20161214PRE-PROPOSAL_CONFERENCE_AND_INCENTIVE_FEE_HANDOUT.pdf PDF
F0014_ExhA_RFP.zip ZIP file
F0014_ExhC_RFP.zip ZIP file
F0013_ExhA_RFP.zip ZIP file
F0014_ExhB_RFP.zip ZIP file
F0013_ExhB_RFP.zip ZIP file
F0012_ExhB_RFP.zip ZIP file
F0011_ExhA_RFP.zip ZIP file
F0012_ExhA_RFP.zip ZIP file
F0011_ExhB_RFP.zip ZIP file
F0009_ExhA_RFP.zip ZIP file
F0010_ExhA_RFP.zip ZIP file
F0010_ExhB_RFP.zip ZIP file
F0009_ExhC_RFP.zip ZIP file
F0009_ExhB_RFP.zip ZIP file
F0008_ExhA_RFP.zip ZIP file
F0006_ExhA_RFP.zip ZIP file
F0006_ExhB_RFP.zip ZIP file
F0007_ExhB_RFP.zip ZIP file
F0007_ExhA_RFP.zip ZIP file
F0004_ExhA_RFP.zip ZIP file
F0003_ExhA_RFP.zip ZIP file
F0003_ExhB_RFP.zip ZIP file
F0003_ExhC_RFP.zip ZIP file
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUSTAINMENT & MODIFICATION OF RADAR SENSORS (SMORS)

PRE-PROPOSAL CONFERENCE HANDOUT

SAMPLE FEE CALCULATION

The following scenario provides an example of the how the Government will apply criteria to calculate the cost, performance and schedule incentive fees earned by the contractor. This example is based on the Ballistic Missile Early Warning System (BMEWS) and PAVE Phased Array Warning System (PAWS) (BPP) Radio Frequency Monitor Technology Refresh (RFM TR) Delivery Order (DO) [FA8723-17-F-0009 (F0009)]. This example will show the calculations of the various elements to show the overall resulting incentive fee for the Base Period of RFM TR (CLINs 1001, 9001 and 9002). The incentive fees are based on the contractor’s Target Cost. The values used throughout the scenario are for illustration purposes only and do not reflect any estimates, budgets or other data associated with this DO.

Sample Data

CLIN 1001

Target Cost (TC): $5,000,000 (proposed amount)

Target Fee (cost) (1.40%): $70,000 $5,000,000 x 1.40%

Maximum Fee (cost) (2.00%): $100,000 $5,000,000 x 2.00%

Minimum Fee (cost) (0.60%): $30,000 $5,000,000 x 0.60%

Underrun share ratio: 75/25

Overrun share ratio: 80/20

CLIN 9001

Performance Incentive Fee Pool (6.00%): $300,000 $5,000,000 x 6.00%

CLIN 9002

Schedule Incentive Fee Pool (2.00%): $100,000 $5,000,000 x 2.00%

F0009 Performance Incentive Fee Criteria

Product Quality – 67% of the Performance Incentive Fee Pool

The contractor will earn the allocated portion of the Product Quality performance incentive based on the number of Category II – Urgent DRs identified during each DT or OT event that are within the contractor’s control. The average number of Category II – Urgent DRs will be calculated by dividing the total number of Category II – Urgent DRs within the contractor’s control assigned during DT and OT for each site divided by the total number of DTs and OTs during the evaluation period. Performance incentive will be based on the average number of DRs according to:

67% of Available PIF (Max) = average of less than 1 Category II – Urgent DRs in DT & OT

57% of Available PIF = average of less than 2 Category II – Urgent DRs in DT & OT

47% of Available PIF = average of less than 3 Category II – Urgent DRs in DT & OT

37% of Available PIF = average of less than 4 Category II – Urgent DRs in DT & OT

28% of Available PIF = average of less than 5 Category II – Urgent DRs in DT & OT

20% of Available PIF (Min) = average of 5 or more Category II – Urgent DRs in DT & OT

Quality Engineering Reviews – 33% of the Performance Incentive Fee Pool

The contractor will earn the allocated portion of the Quality Engineering Review performance incentive based on the contractor’s average number of open action items and document comments at the completion of all SETR milestone meetings associated with CLIN 1001. The average number of action items and document comments will be calculated by dividing the total number of action items and document comments within the contractor’s control assigned at each SETR milestone meeting that are open at the completion of the meeting by the total number of SETR milestone meetings during the evaluation period. Performance incentive will be based on the average number of action items or document comments according to:

33% of Available PIF (Max) = average of less than 1 Critical action items or Critical document comments, or an average of less than 1 Major action items or Major document comments

28% of Available PIF = average of less than 1 Critical action items or Critical document comments, or an average of less than 2 Major action items or Major document comments

23% of Available PIF = average of less than 1 Critical action items or Critical document comments, or an average of less than 3 Major action items or Major document comments

17% of Available PIF = average of less than 1 Critical action items or Critical document comments, or an average of less than 6 Major action items or Major document comments

10% of Available PIF (Min) = average of 1 or more Critical action items or Critical document comments, or an average of 6 or more Major action items or Major document comments

F0009 Schedule Incentive Fee Criteria

Schedule is measured at the successful completion of DT, within the contractor’s control. The contractor will earn the allocated portion of the schedule incentive according to the measures below:

100% of Available SIF (Max) = Completes DT ≥ 15 business days ahead of schedule

70% of Available SIF = Zero (0) days behind ≥ completes DT < 15 business days ahead of schedule

30% of Available SIF (Min) = Completes DT > zero (0) business day behind schedule

Sample #1 - Contract Results and Incentive Fee Calculations

At the end of the evaluation period, the Government determined the average number of Category II – Urgent DRs to be less than 1 for the Product Quality PIF. In addition, the Government determined that for the Quality Engineering Review PIF the average number of Major action items was 1.8. Also, DT was completed seven (7) business days ahead of the contractually agreed to schedule. The Total Allowable Cost was $4,801,502.

Sample Cost Incentive Fee Calculation for CLIN 0001

≡1.4%
≡25/20%

Cost Incentive Fee Earned: $119,625 $70,000 + [25% x ($5,000,000 – $4,801,502)]

Sample Performance Incentive Fee Calculation for CLIN 9001

Performance Incentive Fee Earned: $285,000 ($201,000 + $84,000)

Product Quality $300,000 x 67% = $201,000

Quality Engr. Review $300,000 x 28% = $84,000

Sample Schedule Incentive Fee Calculation for CLIN 9002

Schedule Incentive Fee Earned: $70,000 $100,000 x 70%

Sample #1 Total Incentive Fee Calculation (Cost, Performance & Schedule))

Total Incentive Fee Earned: $474,625 $119,625 + $285,000 + $70,000

Total Fee Percentage of Cost: 9.88% $474,625 / $4,801,502

Sample #2 - Contract Results and Incentive Fee Calculations – Impact of Cost Control Overrun

At the end of the evaluation period, the Government determined the average number of Category II – Urgent DRs to be less than 1 for the Product Quality PIF. In addition, the Government determined that for the Quality Engineering Review PIF the average number of Major action items was 1.8. Also, DT was completed seven (7) business days ahead of the contractually agreed to schedule. The Total Allowable Cost was $5,647,963, which is greater than the threshold 8% overrun, and therefore, the Performance Incentive Fee Pool would be reduced by 10%. The Performance Incentive Fee percent earned for Product Quality and Quality Engineering Review remains the same.

Cost Incentive Fee Earned: $30,000 (Min Fee)

$70,000 + [20% x ($5,000,000 – $5,647,963)] = -$59,593

Sample Performance Incentive Fee Calculation for CLIN 9001

Performance Incentive Fee Earned: $256,500 ($180,900 + $75,600)

Product Quality ($300,000 x 90%) x 67% = $180,900

Quality Engr. Review ($300,000 x 90%) x 28% = $75,600

Sample Schedule Incentive Fee Calculation for CLIN 9002

Schedule Incentive Fee Earned: $70,000 $100,000 x 70%

Sample #2 Total Incentive Fee Calculation (Cost, Performance & Schedule))

Total Incentive Fee Earned: $356,500 $30,000 + $256,500 + $70,000

Total Fee Percentage of Cost: 6.31% $356,500 / $5,647,963