U.S Air Force

FA8601-12-R-0032

QUESTION: Page 5 of 39 of the solicitation states that the required delivery for CLIN 0001 is 2 months ADC, however item 3.1 of the SOW identifies four required submissions for CLIN 0001, and requires Contractor to allow at least 30 calendar days for review/approval by the Government between each submission. Can you please clarify this apparent conflict?

RESPONSE: The Statement of Work takes precedent.