Statement of Objectives

63 KB Posted

Attached to
Simplified Acquisition Base Engineering Requirements
Solicitation number
FA8601-10-R-0010
Issued by

About this file

Statement of Objectives (Seed Project 101888)

Text of this file

STATEMENT OF OBJECTIVES

FOR

VPP - Repair Steel Columns Facility 30055

WRIGHT-PATTERSON AIR FORCE BASE, OHIO

Project No. 10-1888 12 January 2010 1.0 GENERAL: The contractor shall provide all supervision, labor, materials, equipment, and transportation to accomplish this project in accordance with this Statement of Work, project drawings, and the requirements contained in the original documents.

1.1.

All work shall be done in a professional and craftsman-like manner.

1.2.

Field verify all dimensions.

1.3.

All materials shall be installed per manufacturer's recommendations unless specified otherwise. All materials shall be utilized within the manufacturers limitations and intended purposes.

1.4.

The Contractor shall protect against construction debris, including dust, from entering non-project areas.

1.5.

In the event of damages of any nature caused by this work due to improper protection, precaution or safety measures, such damages shall be repaired or such property shall be replaced by the Contractor at no cost to the Government. In the event the Contractor does not satisfactorily repair or replace such damage caused by the work of this contract, the Government will make the necessary corrections and the contractor shall reimburse the Government for inconveniences, labor, and materials involved.

1.6.

It shall be the responsibility of the Contractor with assistance from base personnel to locate all existing utility lines in the field before starting excavation of any kind. The Contractor shall obtain a signed AF Form 103, Base Civil Engineering Work Clearance Request prior to excavating. Contractor shall notify Government SABER Representative 72 hours in advance to schedule an on-site clearance.

1.7.

In order to prevent damage, all digging around utilities shall be done by hand.

1.8.

All required utility outages shall be approved through Government SABER Representative, with no less than 7 days advanced notice.

1.9 No Government Furnished Property (GFP) will be included in this project.

2.0. PERFORMANCE PERIOD: 60 calendar days total.

- 45 days (mobilization/submittals/close-out

- 15 days (construction) 2.1

LIQUIDATED DAMAGES: N/A

3.0 GENERAL SCOPE OF WORK:

3.1.

HAZARDOUS MATERIAL: Contractor shall be aware existing coatings may contain lead based paint.

3.2.

DEMOLITION: Contractor shall remove extensive rust and paint from lowest 8’ on all (14) structural columns. On (7) selected columns, contractor shall remove lowest 2’ of column rusted beyond repair.

3.3.

STRUCTURAL: Contractor shall replace removed steel with new structural column/plates and secure to existing structural columns.

3.4 MECHANICAL: not applicable 3.5 ELECTRICAL: Contractor shall temporarily relocate surface mounted conduit to allow for rust removal, priming, and painting of structural columns.

3.6 FINISHES: Contractor shall prime and paint all (14) columns with rust inhibiting paint on the lowest 8’ of columns.

4.0 CODES, REGULATIONS, AND PERMITS: All work shall be in accordance with the applicable codes and manufacturer's standards.

4.1.

Air Force Occupational Safety and Health Administration Standards (AFOSH).

4.2.

Applicable USAF / AFMC / Wright-Patterson Regulations.

4.3.

OSHA 1910 Standards.

4.4.

National Safety Council Data Sheets.

4.5.

The Ohio Environmental Protection Agency (EPA).

4.6.

Regional Air Pollution Control Regulation (RAPCA).

4.7.

National Electric Code (NEC).

4.8 Ohio Plumbing Code.

5.0 DRAWINGS, SPECIFICATIONS, AND SUBMITTALS:

5.1 Drawings shall be submitted by the contractor, which will indicate to the Government that the Contractor has a full and complete understanding of the construction requirements and that adequate engineering has been done to meet the project requirements. As a minimum drawings submitted shall include;

5.1.1.

Proposed scaled civil, architectural, mechanical, and electrical drawings showing design and details.

5.1.2.

As-built record drawings upon project completion.

5.1.3.

All work shall be in compliance with SABER Contract Specifications.

5.1.4.

Contractor shall submit for approval technical data for all equipment.

5.1.5.

Contractor shall submit for approval color boards, texture/pattern samples, and style /design literature or product brochures for all finish materials.

6.0. SPECIAL CONDITIONS AND/OR INSTRUCTIONS:

6.1.

The Contractor shall remove all debris and refuse from jobsite on a daily basis.

6.2.

The Contractor shall barricade and post the work area to restrict non-project related personnel traffic.

6.3.

The contractor shall conduct his work in such a manner that it would not inhibit or cease operations being conducted in and around the project area without the written approval from the contracting officer.

6.4.

Prior to welding or the use of any flame apparatus, a clearance shall be obtained from the Fire Inspector. Notification to the Fire Inspector for a clearance requires the request be made at a minimum of 24 hours in advance of the desired "hot" work. N/A 6.5.

Contractor shall be in compliance with all applicable safety and security requirements.

6.6. Changes to this contract shall be allowed only by the Contracting Officer.

12 January 2010

Other files

File Type Posted
RFI 8 Response.docx DOCX document
RFI 7 Response.docx DOCX document
FA8601-10-R-0010-0003.pdf PDF
RFIs Responses for SABER Contract 7May10.docx DOCX document
FA8601-10-R-0010-0003.pdf PDF
Wage Decision OH29 Mod 6 5-07-10.docx DOCX document
RFIs Responses for the SABER Contract.doc DOC document
Wage Decision OH29 Mod 5 4-30-10.docx DOCX document
Site Visit Attendees SABER.xlsx XLSX spreadsheet
FA8601-10-R-0010-0002.doc DOC document
SABER Bridge Solicitation RFI Responses.doc DOC document
General Decision Number OH29 Mod 4 4-16-10.docx DOCX document
B55-Steel Columns Sketch.pdf PDF
FA8601-10-R-0010-0001.doc DOC document
Addendum.doc DOC document
Addendum 1.docx DOCX document
Addendum 2.docx DOCX document
FA8601-10-R-0010 SABER Solicitation.doc DOC document
VPPSafety Health Plan Requirement.docx DOCX document
Wage Decision OH29 Mod 2.docx DOCX document
SABER WPAFB_BFS_ _Specs_2009-11-27.pdf PDF
Section 01 33 00.pdf PDF
SABER_BRIDGE_SOW.doc DOC document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .