RFI 8 Response.docx

DOCX document 10 KB Posted

Attached to
Simplified Acquisition Base Engineering Requirements
Solicitation number
FA8601-10-R-0010
Issued by

About this file

Q A

View the file

Other files

File Type Posted
RFI 7 Response.docx DOCX document
FA8601-10-R-0010-0003.pdf PDF
RFIs Responses for SABER Contract 7May10.docx DOCX document
Wage Decision OH29 Mod 6 5-07-10.docx DOCX document
FA8601-10-R-0010-0003.pdf PDF
RFIs Responses for the SABER Contract.doc DOC document
FA8601-10-R-0010-0002.doc DOC document
Wage Decision OH29 Mod 5 4-30-10.docx DOCX document
Site Visit Attendees SABER.xlsx XLSX spreadsheet
SABER Bridge Solicitation RFI Responses.doc DOC document
General Decision Number OH29 Mod 4 4-16-10.docx DOCX document
B55-Steel Columns Sketch.pdf PDF
FA8601-10-R-0010-0001.doc DOC document
Addendum.doc DOC document
Addendum 1.docx DOCX document
Addendum 2.docx DOCX document
FA8601-10-R-0010 SABER Solicitation.doc DOC document
SABER_BRIDGE_SOW.doc DOC document
Statement of Objectives —
VPPSafety Health Plan Requirement.docx DOCX document
Wage Decision OH29 Mod 2.docx DOCX document
SABER WPAFB_BFS_ _Specs_2009-11-27.pdf PDF
Section 01 33 00.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SABER – Request For Information It was my understanding that RS Means is bare cost and that you have to add the city cost index based on what quarter it is. In e4 clicks this would have to be added to the totaling component.

If I’m understanding you correctly the city cost index should be included in our seed project take off. Is that a correct assumption?

RESPONSE: The assumption stated above is correct.