RFI 7 Response.docx
DOCX document 12 KB Posted
- Solicitation number
- FA8601-10-R-0010
About this file
Q A
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI 8 Response.docx | DOCX document | |
| FA8601-10-R-0010-0003.pdf | ||
| RFIs Responses for SABER Contract 7May10.docx | DOCX document | |
| FA8601-10-R-0010-0003.pdf | ||
| Wage Decision OH29 Mod 6 5-07-10.docx | DOCX document | |
| RFIs Responses for the SABER Contract.doc | DOC document | |
| Wage Decision OH29 Mod 5 4-30-10.docx | DOCX document | |
| Site Visit Attendees SABER.xlsx | XLSX spreadsheet | |
| FA8601-10-R-0010-0002.doc | DOC document | |
| SABER Bridge Solicitation RFI Responses.doc | DOC document | |
| General Decision Number OH29 Mod 4 4-16-10.docx | DOCX document | |
| B55-Steel Columns Sketch.pdf | ||
| FA8601-10-R-0010-0001.doc | DOC document | |
| Addendum.doc | DOC document | |
| Addendum 1.docx | DOCX document | |
| Addendum 2.docx | DOCX document | |
| FA8601-10-R-0010 SABER Solicitation.doc | DOC document | |
| Statement of Objectives | — | |
| VPPSafety Health Plan Requirement.docx | DOCX document | |
| Wage Decision OH29 Mod 2.docx | DOCX document | |
| SABER WPAFB_BFS_ _Specs_2009-11-27.pdf | ||
| Section 01 33 00.pdf | ||
| SABER_BRIDGE_SOW.doc | DOC document |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8601-10-R-0010
SABER
RFIs
Re: Statement of Work, Para. 3.1.5.1 – Do “Engineered Performance Standards, Preventative Maintenance Standards, and Service Call Standards” refer to specific publications? If so, please provide a source for these publications.
RESPONSE: The referenced standards are price books developed by RS Means.
Re: Statement of Objectives (Project No. 10-1888, VPP Repair Steel Posts Facility 30055) – Is the pricing to be based as strictly as possible on the Scope of Work (para. 3.0)? Can betterments be offered for consideration?
RESPONSE: Reference the SOW paragraph 3:
3. DELIVERY ORDER PRICING: Contractor delivery order pricing shall be accomplished as described below and based on the most economical standard construction practices. Value engineering and design review shall be used in project design and scope development. Unreasonable methods and or estimates to accomplish delivery order tasks will not be accepted.
Re: Statement of Work, Para. 3.1.5.2 - Several items of work required for this project are not included in the RS Means Price Book. This will require the use of Non Pre-priced Items. The referenced paragraph states “Labor costs shall be derived using the RS Means productivity crew cost rates”. If a matching item is not found, how are the labor costs derived from the price book.
RESPONSE: Reference the SOW paragraph 3.1.5. and 3.1.5.3.:
3.1.5. Non Pre-priced Items (NPP): Items of work not included in the UPB required for execution of a deliver order and within the scope and general intent of the contract, these items must be submitted, approved and or negotiated if necessary.
3.1.5.3. The contractor shall submit a worksheet for each NPP item which shows all of the costs and calculations used to develop the NPP item’s price.
Louie Poole Butt Construction Company lpoole@buttconstruction.com 937-426-1313 937-426-5323 fax