About this file

This document contains questions and answers regarding a request for proposals for next generation all aluminum pallets. The solicitation seeks a contractor to manufacture and produce item 463L Air Cargo Pallets to MIL-DTL-27443 specifications over an 18-month basic period and nine one-year option periods. Production quantities range from 5 first article pallets in the basic period to a maximum of 15,000 pallets per year in later option periods. The coating for rivets is specified as MIL-PRF-32550. Questions addressed include clarification on lot size definition, consideration of alternative sampling plans to reduce costs, confirmation of specific water penetration testing required, and replacement of the specification with MIL-PRF-32550. Award will be made using tradeoff source selection procedures to determine the best value proposal.

RFP Release Q&A_4

View the file

Other files for this federal contract opportunity

Other files attached to Next Generation All Aluminum Pallets, newest first.
File Type Posted
FA853419R0001_______0004.pdf PDF
MIL-DTL-27443G.pdf PDF
Additional_Questions_from_Industry_2Oct19.docx DOCX document
CargoPalletAssembly201993426.STEP STEP file
CenterPanelExtrusion201993428.STEP STEP file
FA853419R0001_______0002.pdf PDF
Price_Model_Revised.xlsx XLSX spreadsheet
TieDownRingAssembly201993431.STEP STEP file
IntermediatePanelExtrusion201993427.STEP STEP file
RFP_release_-_Questions_from_Industry.docx DOCX document
FA853419R0001_______0001.pdf PDF
ppi_tool.accdb MDB file
Eng_Data_List.pdf PDF
Next_Gen_Cargo_Pallet_Replacement_MIL_DTL_27443G.pdf PDF
Side_Panel_Extrusion_(X201993429).STEP STEP file
Cargo_Pallet_Assembly_(X201993426).STEP STEP file
Center_Panel_Extrusion_(X201993428).STEP STEP file
Intermediate_Panel_Extrusion_(X201993427).STEP STEP file
Edge_Rail_Extrusion_(X201993430).STEP STEP file
CDRLS_A001_-_A010.pdf PDF
SOW_Next_Gen.pdf PDF
Drawing_Package.pdf PDF
Section_L_Final.pdf PDF
Price_Model,_final.xlsx XLSX spreadsheet
FA853419R0001.pdf PDF
ppi_tool.accdb MDB file
Section_M_Final.pdf PDF
Q&As_4.pdf PDF
Tie-Down_Ring_Assembly_(X201993431).STEP STEP file
Edge_Rail_Extrusion_(X201993430).STEP STEP file
Cargo_Pallet_Assembly_(X201993426).STEP STEP file
Intermediate_Panel_Extrusion_(X201993427).STEP STEP file
Pre-Solicitation_Conference_Questions_Final.pdf PDF
Revised_Drawings.pdf PDF
Agenda.docx DOCX document
Information_Sign_in_Sheet.pdf PDF
REVISED_Price_Model.xlsx XLSX spreadsheet
REVISED_SOW_NextGenPallet.pdf PDF
Revised_Section_L_Aluminum_Pallet.doc DOC document
QA_Mar_19_final.docx DOCX document
Draft_-_Next_Gen_Cargo_Pallet_Replacement_MIL_DTL_27443.docx DOCX document
SectionLAluminum.doc DOC document
FA853419R0001.pdf PDF
SOWNextGenPallet2018.pdf PDF
CargoPalletsCDRLS.pdf PDF
CWBSMatrix.docx DOCX document
PriceModel.xlsx XLSX spreadsheet
DraftForm1653.doc DOC document
PackagingFORM158.pdf PDF
Drawings.pdf PDF
Show all 50

Next Generation All Aluminum Pallets has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP Release Q&A_4

1. Could the definition of a lot be further clarified? For example “A lot shall consist of two weeks of production” or something more specific?

Response: The typical lot would most logically be identified as 140 pallets, since that quantity is designated as a full truck load. Potential bidders may opt to define a lot size differently.

Lot sampling is based on ANSI/ASQ definitions, which provide guidance for whatever lot size is defined by the manufacturer.

2. Would the Government consider changing sampling plan to reduce cost and waste? Will the government expect these samples to be scrapped or returned to the production stream, if they pass the tests above?

Response: See September Q&A Response below:

34. MIL-DTL-27433 (Draft of G version) requires the sampling plan per ANSI/ASQ Z1.4, general inspection level II, single sampling plan for normal inspection. For a lot between 91 and 150, the sample size would be 20 and would be subject to tests outlined in 4.5.3.4, 4.5.5.1, and 4.5.9.2. If these are performed on the actual pallets (which it appears they would be) what are done with the 20 pallets that went through this testing? Will the production rate need to be increased to account for the 20 pallets tested?

· Section 4.5.9.2 specifies “Samples shall be removed from actual pallets, off-cuts, or representative witness samples”. Completed production pallets are not mandatory for this testing

· Sample pallets used for tests 4.5.3.4 & 4.5.5.1 will be included in production quantities for all pallets that pass testing.

· Production rates should not be increased to account for the test samples.

3. This raises the same issue as question 2. Unless a sufficient quantity of representative cut offs, extractions or witnesses is available, this will require destruction of a large quantity of pallets at government expense.

Response: As stated in the “question”, this issue is the same as question 2. See the answer to Question 2. Manufacturing processes will allow for “representative samples” to be easily produced at a minimal cost to the producer.

4. Can the Government confirm which specific water penetration test is required?

Answer: See MIL-DTL-27443G posted on FBO October30, 2019 for the official, published version of the specification.

5. Was the Government’s intention to replace with MIL-PRF-32550?

Answer: Yes, MIL-PRF-32550 is the required coating for the rivets. See “Amended_Drawings_201993426” posted October 1, 2019 on fbo.gov. The specification is listed on the drawing 201993426 in note 8. The specification was removed from MIL-DTL-27443 section 2.2.1 to mitigate redundancy, since the document (MIL-DTL-27443) requires the pallet to be built to the TDP (drawing 201993426).