Question and Answer 3.docx

DOCX document 22 KB Posted

Attached to
Ground Power Modernization
Solicitation number
FA8532-22-R-0001
Issued by

About this file

This document contains questions and answers related to a forthcoming solicitation for ground power equipment. The solicitation will be for indefinite-delivery, indefinite-quantity multiple award contracts for a 72kW ground power unit, 144kW ground power unit, and 144kW universal load bank. One contract will be awarded on a full and open basis for all three items under Group A. The 72kW ground power unit will be awarded as a small business set aside under Group B. The base period of performance will be three years with seven one-year ordering periods. A total of 2928 units of the 72kW ground power unit, 250 units of the 144kW ground power unit, and 300 units of the 144kW universal load bank will be acquired. The solicitation is expected to be released on October 15, 2021 with an anticipated award date of September 26, 2022.

View the file

Other files

File Type Posted
GPM_JA_(400_Hz_Power_Cable_Assembly)_Redacted.pdf PDF
M-900 - Evaluation Basis for Award - Updated.pdf PDF
FA8532-22-R-0001_0004.pdf PDF
Question and Answer 8.docx DOCX document
Question and Answer 7.docx DOCX document
Question and Answer 6.docx DOCX document
FA8532-22-R-0001_0003.pdf PDF
RFP Attachment 3 - List of Fill-In Clauses to be Completed - Revised 2.pdf PDF
Extraction from RFP Attachment 10_Columns A thru D only.xlsx XLSX spreadsheet
Pre-Proposal Conference Brief Re-upoload.pptx PPTX presentation
Pre-Proposal Conference Follow-Up.docx DOCX document
QA from Pre-Proposal Conference.docx DOCX document
Pre-Proposal Conference Brief.pptx PPTX presentation
Question and Answer 5.docx DOCX document
RFP Attachment 5 - Relevancy Table - Revised.pdf PDF
Pre-Proposal Conference Brief.pptx PPTX presentation
Question and Answer 4.docx DOCX document
FA8532-22-R-0001_0002.pdf PDF
RFP Attachment 5 - Relevancy Table - Revised.pdf PDF
RFP Attachment 3 - List of Fill-In Clauses to be Completed - Revised.pdf PDF
FA8532-22-R-0001_0001.pdf PDF
RFP Attachment 10 - Price Spreadsheet - Revised.xlsx XLSX spreadsheet
Question and Answer 2.docx DOCX document
Question and Answer 1.docx DOCX document
C017.pdf PDF
D004.pdf PDF
C004.pdf PDF
D004_TM86-01R.pdf PDF
C010.pdf PDF
C012.pdf PDF
F001.pdf PDF
RFP Attachment 9 - GPU Engine Derating Calculation Worksheet.pdf PDF
E001.pdf PDF
C007.pdf PDF
D002_TM86-01R.pdf PDF
D006.pdf PDF
E008.pdf PDF
RFP Attachment 3 - List of Fill-In Clauses to be Completed.pdf PDF
C002.pdf PDF
RFP Attachment 6 - Subcontractor and Teaming Member Consent Form.pdf PDF
RFP Attachment 1 - Past Performance Information (PPI) for Offerors.pdf PDF
C003.pdf PDF
C008.pdf PDF
E002.pdf PDF
M-900 Evaluation Basis for Award.pdf PDF
FA8532-22-R-0001.pdf PDF
RFP Attachment 4 Instructions.docx DOCX document
E003.pdf PDF
A002.pdf PDF
Statement of Work (SOW)_1 Sep 21.pdf PDF
Show 40 more

Latest 50 of 90 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Questions and Answers #3 22 Oct 2021

Q1:We were looking thru the pricing spreadsheet (Attachment 10 – Price Spreadsheet). In the subsequent year risk factors (Group A Risk Factor tab), the Gov’t mentioned “Engine and Generators” as a cost element in Universal Load Bank. As you know, there is no “Engine nor Generator” in ULB, they are only applicable to GPUs. This seems to be an error and needs to be corrected.
A1:You are correct in that the inclusion of the generator and the engine in the ULB price factor tabwas an error. RFP Attachment 10 was updated, and incorporating via RFP amendment -0001.
Q2:We have a question regarding the number of efforts we can provide in the Past Performancesection. We have various IDIQ contracts with multiple delivery orders. Do we consider eachcontract with its respective series of delivery orders (aggregate quantities, total dollar value andtotal period of performance) as one (1) effort OR will each Delivery Order be considered as one(1) effort?
A2:Each contract with its respective series of orders will count as one effort. If an ordering typecontract only has one order that demonstrates relevancy, then that one order would count as asingle effort.
Q3:Regarding the list of fill-in clauses listed in Attachment 3:
FAR 52.223-33: I could not find this clause in the RFP. However, I found 52.223-22 in page 288of 303. Is FAR 52.223-22 the one we need to complete?
FAR 52.222-18 and DFARS 252.225-7020: Can you clarify that if we complete/answer therespective FAR 52.204-8 and DFAR 252.204-7007 no further action is required for these (FAR52.222-18 and DFARS 252.225-7020)? I want to make sure we do not leave any of these clausesunanswered.
A3:RFP Attachment 3 indeed should have referenced FAR 52.223-22 instead of FAR 52.223-33. Acorrected RFP Attachment 3 will be forthcoming.
Regarding the FAR 52.222-18 and DFARS 252.225-7020 clauses, completing the respective FAR 52.204-8 and DFAR 252.204-7007 clauses will cover these requirements as long as the representations and certifications posted in SAM for your company reflect the completion of these clauses. If your SAM information does not reflect these clauses, then the proposal submission will need toaddress these.
Q4:I had a couple of questions regarding the Oral Discussions after each Gate submission.

(a) The number of participants is 5, can you change or rotate participants’ after each Gate?

(b) Can critical subcontractors be part of the oral discussion?

(c) Do they have to be included as part of the 5 participants or can they be added in addition to the 5?

A4:

(a) Offerors are not required to have the same 5 participants during the oral discussions. Each gate should have the specific participants needed that can best respond to any evaluation notices provided.

(b) Yes, offerors can choose to include critical subcontractor participants within the oral discussions.

(c) At this time, any critical subcontractor participants would be included as a part of the 5 person limit. However, please note that this could be changed if the Government receives sufficient rationale for a change request.

File details come from the government source that posted it. Updated .