This solicitation is for an Indefinite-Delivery Indefinite-Quantity construction contract to provide maintenance, repair, alteration and new construction work at Robins Air Force Base. The contract has a one year base period with four one-year options and has a maximum value of $95 million to be awarded across multiple contracts. Task order values will typically range from $250,000 to $3 million. Work may include new building construction, renovation, repair of structures and facilities, utilities work, hazardous material abatement, and design-build services. The solicitation is restricted to service-disabled veteran-owned small businesses. The contractor must be registered in the System for Award Management and be a U.S.-owned entity. Bonds valued up to the full task order amount will be required on orders over $35,000. The solicitation includes revisions to the statement of work and evaluation procedures.

Demonstration Project Attachment 2 Addendum 1 dated April 15 2019

View the file

Other files for this federal contract opportunity

Other files attached to CEMACC II, newest first.
File Type Posted
Post_Award_Synopsis.docx DOCX document
Construction_Abstracts.pdf PDF
A11_Layout1.pdf PDF
A14_Layout1.pdf PDF
M09-Layout1.pdf PDF
A13_Layout1.pdf PDF
M07-Layout1.pdf PDF
S11_Layout1.pdf PDF
A02-Layout1.pdf PDF
A04-Layout1.pdf PDF
RFI__3_Final.docx DOCX document
Solicitation_Amendment_FA850119BA0010001_SF_30.pdf PDF
Photo_5.JPG JPG image
Photo_7.JPG JPG image
Photo_3.JPG JPG image
Photo_8.JPG JPG image
Photo_1.JPG JPG image
IMG_7174.JPG JPG image
Photo_4.JPG JPG image
Pre-Proposal_Conference_Briefing-FINAL__4_Aug_19.ppt PPT presentation
Site_Visit_Attendee_List_-_Final.pdf PDF
RFI__2.docx DOCX document
2019-07-31_UHHZ130375_-_Combined_Specifications_(Updated).pdf PDF
2019-07-31_UHHZ130375_Corrected_Final_Drawings_(Updated).pdf PDF
Notice_to_Bidders__4.docx DOCX document
UHHZ130375_-_Revision_No_2_(Addendum_20190718).pdf PDF
RFI__1.docx DOCX document
Notice_to_Bidders__3_Site_Visit.docx DOCX document
Notice_to_Bidders__2.pdf PDF
Appendix_C_1080274.pdf PDF
Solicitation_-_FA850119BA001.pdf PDF
Notice_to_Bidders__1.pdf PDF
Atch__7_-_BLANK_SAMPLE_AF_Form_3065.xlsx XLSX spreadsheet
Atch__5_-_Blank_Sample_AF_Form_3052.xls XLS spreadsheet
Atch__9_-_Master_Utility_Outage.pdf PDF
Atch__6_-_BLANK_SAMPLE_AF_Form_3064.xlsx XLSX spreadsheet
Atch__8_-_AF_Form_3000.pdf PDF
Demonstration_Project_Attachment_4_Bid_Schedule.docx DOCX document
Demonstration_Project_Attachment_1_Specifications.pdf PDF
CEMACC_SOW_dated_15_April_2019.pdf PDF
Atch__4_-_Robins_AFB_Asbestos_Management_Plan_-_January_2015.pdf PDF
Atch__15_-_AF_Form_2586_Flightline_Driving_Request.pdf PDF
Davis_Bacon_Wage_Determination.pdf PDF
Atch__3_-_Robins_AFB_Division_1_Specs.pdf PDF
Atch__2_-_PROCEDURAL_GUIDE_FOR_DESIGNERS_INCLUDING_AE_FIRMS_29_May_15.pdf PDF
Atch__13_-_AFMAN_31-116_Motor_Vehicle_Traffic_Supervision.pdf PDF
Atch__11_-_Form_911,_xx__Design,_Discipline_Review.docx DOCX document
Demonstration_Project_Attachment_3_Corrected_Final_Drawings.pdf PDF
Atch__14_-_AFMAN_32-1084_Civil_Engineering_Facility_Requirements.pdf PDF
Sample_Bid_Bond_dated_June_24,_2019.pdf PDF
Show all 50

CEMACC II has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revision No. 3 Cover Page

15 April 2019

REVISION NO. 1

TO

PROJECT UHHZ 130375

Cnst/Inst Maint Platform RAC 2, Acft Cor Con, B/38

Revision No. 1 consists of the following line items:

Item No. 1: SOW Revisions:

1. Plate S100, An existing ladder exists at the alcove (east) end of the of the duct sock chase and extends the full height of the chase. Ladder needs to be modified or replaced to meet OSHA requirements for configuration and fall protection devices. This also includes a ladder cage for sections 24 ft. or more above the bottom level. Affix an inspection tag to the ladder when work is completed. Ladder requirements shall also meet specifications for new ladders as per drawings and specifications.

2. Plate S100, Provide aluminum floor access hatch at each platform level as required to protect opening per OSHA requirements. Hatch shall pre-manufactured hinged unit with checkered plate top, rated to minimum 300 psf., have hold opens and have gas struts to assist opening/closing. Hatch shall be operable from both sides and shall not be lockable. Hatch shall allow for 30”x30” opening (adjust framing as required). Basis of design – Acudor or equal.

3. Plate E100, Provide Class 1, Div. 1 exit sign at each level and in mechanical room. Signs shall be LED with battery backup. Basis of design – Larson Electronics or equal.

4. Plate E100, At new ladders, change safety chains across openings to gates similar to Detail 3/S503. Also protect adjacent electrical conduit, boxes, etc. from being accidentally grasped with minimum 20 ga. continuous metal guards the full height of the ladder sections, both sides.

Guards shall have hemmed vertical edges to prevent injury if brushed against and shall extend at least 12 inches beyond the sides of the ladders.

5. At Detail 3/A503, add bottom rail to gate to act as a toe guard when gate is closed.

6. All railings shall have minimum 4” high toe guards.

7. Plate S100, change platform at west end on all 3 levels to extend to existing wall with necessary grating, beams and columns (delete note “Edge of new platform match existing steel angle all 3 new levels”). Purpose is to prevent multistory falls should one occur with a ladder next to railing.

8. Plate E100, All new electrical within the plenum shall be rated Class 1, Division 1 per NEC.

Revision No. 3 Cover Page

9. Protect all penetrations through the existing fire rated wall as required to maintain 1 Hr fire rating of wall. All penetrations shall require UL ratings and shall be so designated during shop drawing submittal. Utilize UL approved sleeved methods wherever possible.