About this file

Atch 7 - questionnaire

View the file

Other files for this federal contract opportunity

Other files attached to Mechanical/Electrical IDIQ Construction Contract, newest first.
File Type Posted
CLARIFICATION - FA8501-11-R-0002 28 APR 2011.docx DOCX document
Atch 7 FA8501-11-R-0002.doc DOC document
Question Answers 2 FA8501-11-R-0002.doc DOC document
Q A 1 - FA8501-11-R-0002.docx DOCX document
History Info - Current Mech Elec IDIQ.pdf PDF
Sign in sheet - Pre-proposal meeting FA8501-11-R-0002.pdf PDF
Mech Elec IDIQ - Pre-proposal conference.ppt PPT presentation
Atch 3 - Facts Sheet 11-R-0002.doc DOC document
Atch 9 FA8501-11-R-0002.pdf PDF
Specs.zip ZIP file
FA8501-11-R-0002.rtf RTF text file
Atch 2 FA8501-11-R-0002 Appendix C.pdf PDF
Atch 3 - Facts Sheet 11-R-0002.doc.pdf PDF
Atch 8 Consent Form 11-R-0002.doc DOC document
Atch 6 Transmittal Letter 11-R-0002.doc DOC document
Atch 5 Tracking record 11-R-0002.doc DOC document
Atch 10 11-R-0002.pdf PDF
Atch 4 Client auth Letter 11-R-0002.doc DOC document
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRESENT/PAST PERFORMANCE QUESTIONNAIRE

FA8501-11-R-0002

Atch #7

PLEASE PROVIDE THE FOLLOWING INFORMATION ABOUT YOURSELF:

Name/Signature and Role Relative to Contract (e.g. Contract Administrator, Inspector, Project Engineer, Quality Assurance Evaluator, Other-explain):

Agency or Business:

Telephone:

Fax Number:

RETURN YOUR COMLETED QUSTIONAIRE VIA FAX NUMBER AT (478-327-3061). TO ENSURE PROPER HANDLING OF THE INFORMATION, PLEASE CALL MRS. ANGIE WHITLEY (478-926-7989) BEFORE TRANSMITTAL.

NOTICE: WHEN COMPLETED, THIS QUESTIONNAIRE WILL BE CONSIDERED SENSITIVE AND SHALL NOT BE RELEASED TO THE OFFEROR.

PART 1. PROGRAM INFORMATION:

Contractor/Business:

Program Description: (Description of Project Scope of Work)

Contractor’s Role in the Program: ____Prime ____Subcontractor ____Vender/Supplier

Did this contractor perform any of the following on this effort: ____ Fire Alarm Work ___ HVAC Work ____Steam Distribution ____Medium Voltage ____ Direct Digital Controls

If the effort involved any of the above work: Did the contractor engineering/design the work, install/perform the work or do both? ____________________________________________________________________________

Contract Number:

Number of Years?: Basic: _____ Option:_____

Contract Type(s): List all applicable contract types, i.e. Firm-Fixed-Price, Time & Materials, Cost, Etc.

Total Contract Amount: $ Status: ( ) Active ( ) Completed

Date of Award:

If completed, date of completion:

If Award Fee Contract, what percentage of the fee has been awarded in each of the last 3 years?

Note: In Part II, should your response be other than “satisfactory,” please provide supporting documentation in “Additional Remarks” on page 3 of 3.

PART II. PERFORMANCE ASSESSMENTS:

Please check the appropriate rating for each of the following questions:

N/A=Not Applicable – Self-explanatory. U=Unsatisfactory – Performance did not meet most contractual requirements. M=Marginal – Performance did not meet some contractual requirements. There were problems, some of a serious nature, for which corrective action was only marginally effective. S=Satisfactory – Performance met contractual requirements. There were some minor problems and corrective actions taken by the contractor were satisfactory. V=Very Good – Performance met all contractual requirements and exceeded some to the customer’s benefit. E=Exceptional – Performance met all contractual requirements and exceeded many to the customer’s benefit. Problems, if any, were negligible and were resolved in a timely, highly effective manner.

Rate the following areas:
N/A
U
M
S
V
E
1
Quality/acceptability of completed work:
2
Contractor performed the contract requirements within the agreed prices:
3
Provided effective quality control and/or inspection procedures:
4
Corrected deficiencies in timely manner:
5
Contractor’s ability to assign and retain competent/responsible/effective on-site manager:
6
Effective management of material and personnel to accomplish contract requirements:
7
Contractor’s effectiveness in coordinating and managing multiple subcontractors:
8
Contractor's ability to retain competent subcontractors throughout the project:
9
Demonstrated timely recognition and effective resolution of administrative, technical, vendor, and subcontractor problems affecting the project:
10
Demonstrated positive responsiveness to contract changes/modifications:
11
Working relationship with Government personnel after award:
12
Completion of work according to project schedule:
13
Provided reports/submittals in a timely manner:
14
Provided accurate, timely, and complete line item cost proposals for changes/modifications:
15
Paid subcontractors/suppliers in a timely manner:
16
Contractor's responsiveness to items covered by warranty:
17
Contractor’s overall performance:

16. During the project, did the contractor change any of the original subcontractors? ( ) Yes ( ) No If Yes, please explain.

17. Were you satisfied with the contractor’s coordination and management of multiple worksites operating simultaneously? Please explain. ( ) Yes ( ) No ( ) N/A

18. Has action been initiated to cancel or terminate the contract for default? ( ) Yes ( ) No If Yes, please explain.

19. Has there been any dispute/claim relative to the contract? ( ) Yes ( ) No If Yes, Please explain.

20. Describe the contractor’s or company’s strong characteristics.

21. Describe the contractor’s or company’s weak characteristics.

21. If given a choice, would you award to this contractor again? ( ) Yes ( ) No

22. Additional Remarks: