Guidance_SSC_Question_and_Answer_3_31_MAR_2014.pdf

PDF 200 KB Posted

Attached to
Guidance Subsystem Support Contract Federal contract opportunity
Solicitation number
FA8214-14-R-0004
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to Guidance Subsystem Support Contract, newest first.
File Type Posted
Sec_J_Attch_1_GRID_8_Apr_14.docx DOCX document
Guidance_SSC_Amendment_4_CRM.pdf PDF
Section_J_Attch_9_Combined_Guidance_GFE_Listing_8_APR_14.xlsx XLSX spreadsheet
FA821414R0004_______0004.pdf PDF
Guidance_SSC_Question_and_Answer_4_8_APR_2014.pdf PDF
Guidance_SSC_Amendment_3_CRM_Final.pdf PDF
Sec_J_Attch_1_GRID_31_Mar_14.docx DOCX document
Section_J_Attch_9_Combined_Guidance_GFE_Listing_25_Mar_14.xlsx XLSX spreadsheet
Sec_J_Attch_7_Guidance_SSC_Award-Fee_Plan__31_Mar_14.docx DOCX document
Guidance_SSC_Section_L_31_Mar_14_updated.docx DOCX document
Sec_L_Attch_6_Guidance_Organizational_Manning_Matrix__19_Mar_14.xlsx XLSX spreadsheet
Guidance_SSC_Section_M_10_Mar_14_updated.docx DOCX document
Guidance_SSC_Amendment_2_CRM_Final.pdf PDF
Sec_L_Attch_6_Guidance_Organizational_Manning_Matrix__10_Feb_14.xlsx XLSX spreadsheet
Guidance_Sec_L_Attch_1_Cross_Reference_Matrix_13_Mar_2014.xlsx XLSX spreadsheet
Sec_J_Attch_3a_Guidance_SSC_CDRL_Instructions_and_Master_Listing_5_Mar_14.pdf PDF
Sec_J_Attch_7_Guidance_SSC_Award-Fee_Plan__5_Mar_14.docx DOCX document
Section_J_Attch_9_Combined_Guidance_GFE_Listing_5_Mar_14.xlsx XLSX spreadsheet
Guidance_SSC_Q A_2_Final.pdf PDF
Sec_J_Attch_3a_Guidance_SSC_CDRL_Instructions_and_Master_Listing_3_Mar_14.pdf PDF
Guidance_SSC_Section_L_24_Feb_14.docx DOCX document
FA821414R0004_______0001.pdf PDF
Sec_J_Attch_3b_IWRP_CDRL_Instructions_and_Master_Listing_27_Feb_14.pdf PDF
Guidance_SSC_Amendment_1_Q_and_A.pdf PDF
Sec_J_Attch_2_Guidance_SSC_PWS_24_Feb_14.docx DOCX document
Sec_J_Attch_9_Combined_Guidance_SSC_and_IWRP_GFE_List_20_Feb_14.xlsx XLSX spreadsheet
Sec_J_Attch_8_IWRP_Incentive_Fee_Plan__24_Feb_14.docx DOCX document
Guidance_Questions_and_Answers_1.pdf PDF
Sec_J_Attch_4_Guidance_SSC_Labor_Rate_Matrix_5_Feb_14.xlsx XLSX spreadsheet
Guidance_SSC_Section_L_6_Feb_14.docx DOCX document
Sec_J_Attch_3a_Guidance_SSC_CDRL_Instructions_ _Master_Listing_5_Feb_14.pdf PDF
Guidance_SSC_Section_M_11_Feb_14.docx DOCX document
Sec_J_Attch_10_Guidance_SSC_DD_254_7_Feb_14.pdf PDF
Sec_L_Attch_2_Guidance_Past_Performance_Information_Sheet_31_Jan_14.docx DOCX document
Sec_J_Attch_5_Guidance_SSC_Mapping_Worksheet_5_Feb_14.xlsx XLSX spreadsheet
FA821414R0004.pdf PDF
Sec_L_Attch_5_Guidance_Roles_Responsibilities_Worksheet_31_Jan_14.docx DOCX document
Sec_J_Attch_9_Combined_Guidance_SSC_ _IWRP_GFE_List_11_Feb_14.xlsx XLSX spreadsheet
Sec_J_Attch_2_Guidance_SSC_PWS_11_Feb_14.docx DOCX document
Sec_L_Attch_7_Guidance_CLIN_Pricing_Matrix_3_Jan_14.xlsx XLSX spreadsheet
Sec_J_Attch_3b_IWRP_CDRL_Instructions_and_Master_Listing_5_Feb_14.pdf PDF
Sec_L_Attch_10_Past_Performance_Questionnaire_3_Feb_14.doc DOC document
Sec_L_Attch_8_EZ_Source_Instructions_03_Feb_14.docx DOCX document
Sec_L_Attch_1_Cross_Reference_Matrix_29_Jan_2014.xlsx XLSX spreadsheet
Sec_L_Attch_4_Guidance_Commercial_Client_Authorization_31_Jan_14.docx DOCX document
Sec_L_Attch_3_Guidance_Consent_Form_31_Jan_14.docx DOCX document
Sec_L_Attch_6_Guidance_Organizational_Manning_Matrix__10_Feb_14.xlsx XLSX spreadsheet
PPI_Tool.mdb MDB file
Guidance_Sec_J_Attch_7_Guidance_Labor_Category_Descriptions_13_Jan_14.pdf PDF
Guidance_GFP_Questions.pdf PDF
Show all 50

Guidance Subsystem Support Contract has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offeror Questions

Solicitation No.: FA8214-14-R-0004

Doc. Page Para. Background/Issue Suggested Resolution Government Response Section I N/A 52.216-16 Paragraph (c), Data submission, specifies data to be submitted "Within * days after the end of the month", but the asterisk is not subsequently defined.

Request the Government clarify the definition of the asterisk in paragraph (c).

Updated 52.216-16. Changes will be reflected in

Amendment 3.

Section J Attachment

1, GRID

Section L

10 CDRL A126

7.1.7.1, c. 2) (a)

CDRL A126, Commercial Off-The-Shelf (COTS) Manuals and Associated Supplemental

Data, is listed in GRID Table 1, Rights in Noncommercial Technical Data, Computer

Software and Computer Software Documentation. CDRL A126 concerns commercial data. As such, we believe it is more appropriate for this CDRL to be listed in GRID

Table 2.1, Commercial Technical Data and Commercial Software Products.

Request the Government remove CDRL A126 from GRID Table

1.

Updated Section J Attachment 1. Changes will be reflected in Amendment 3.

Section J Attachment

40 1.6.5.2.3.5 Section 1.6.5.2.3.5 of the PWS refers to the Guidance SSC scope as follows: "The contractor shall provide inputs on weapon system performance and accuracy to the

Government for each flight test. Analysis tools and methodologies are required to properly evaluate the performance of each test." It is unclear if this requirement is at the weapon system level or for the Guidance contribution to the weapon system.

There are a number of other instances in Section 1.6.5.2 were the PWS refers to

"weapon system support" as well. As written, it is unclear where the delineation between the ISC and the Guidance SSC is for this scope.

Request the Government clarify if the FTUE technical assistance scope in PWS 1.6.5.2.3 is bounded to the Guidance

Subsystem only or is intended to be a broader weapon system level scope as written in the PWS. In the cases where the scope is intended to be for guidance only, recommend the

Government insert the phrase "the guidance contribution to the weapon system..."

Guidance SSC contractor input on weapon system performance and accuracy for flight tests is limited to guidance subsystem inputs which contribute to the weapon system.

Section J Attachment

39 1.6.5.2.3 There is overlap between the PWS scope defined for FTUE Flight Test Analysis and

Anomaly Support and the scope defined for Assessment in Section 1.6.3.2. Without some clarity, the costs may not be captured correctly against the CLINs and the offerors may not partition the scope consistently for evaluation purposes.

Request the Government clarify the scope to be included in

CLIN X001 and X051 for Analysis and Anomaly Resolution.

PWS requirements defined in FTUE Flight Test Analysis

(1.6.5.2.3) and Anomaly Support (1.6.5.2.4) sections are activities that will occur specifically following FDE events. PWS requirements defined in Guidance

Subsystem Assessment (1.6.3.2) are assessment activities that will always continue to occur even if FDE events are halted/delayed/cancelled.

Section J Attach 9 (20

Feb 14)

N/A "MOD 7 Specific" tab

There are no locations specified in the MOD 7 tab of the 20 Feb 14 GFE list. Request the Government add a "Location" column to the MOD

7 tab to specify the location of each item listed on that tab.

Update Section J attachment 9. Changes will be reflected in Amendment 3. Mod 7 GFE list updated with locations and posted to bidders library.

Sec_J_Attach_

2_Guidance_

SSC_PWS_2

4_Feb_14

99 2.1 – Phase 1:

Technology &

Risk Reduction

Phase (TMRR)

Document Request: Section 2.1 mentions IWRP Acquisition Decision

Memorandum (ADM). Please provide.

Need document to better understand contractor requirement, per paragraph 2.1, of

“assisting the Government in developing and submitting the required Milestone B documentation as defined in the IWRP

Acquisition Decision Memorandum (ADM).

Draft ADM Memo and Documentation Analysis was posted to Bidders Library.

Doc. Page Para. Background/Issue Suggested Resolution Government Response Guidance_

SSC_Se ction_L_24_F eb_14

11 4.2.3.4 Section L (4.2.3.4) and Section M

(2.1.1.4) are written to imply that the offerors will be evaluated on the approach to the CWBS, Schedule, and

CSOW. Our interpretation is that the government wants the actual CWBS, Schedule, and CSOW for the

Awardable Task versus the approach.

Clarification is needed on Awardable Task

CWBS, Schedule and CSOW delivery requirements. Are the actual documents to be delivered or our approach in developing the documents?

Section L&M dictates to the offerors that they will be evaluated on their CSOW, CWBS, Schedule, and

Proposed conceptual design. As detailed in sections

L&M the contractors must deliver the actual CSOW, CWBS, and Schedule that will become contractual documents upon delivery after contract award for evaluation versus a technical approach of how these documents will be developed. The CSOW, CWBS, and

Schedule are to be delivered in Technical Volume II sections 8-1, 8-2, and 8-3 respectively (Sections 8-1 and

8-3 do not count towards page limit). Section 8-4 will be used by the offerors to present their proposed conceptual design.

Sec_J_Attach_

2_Guidance_

SSC_PWS_2

4_Feb_14

76 Appendix F:

Applicable

Documents

Document Request: ICBMSD OI

63-26 “Technical Design Review” was not found in Bidder’s Library;

please provide.

Need referenced document to better understand solicitation requirements

ICBMSD OI 63-26 “Technical Design Review" and its attachments have been added to the bidders library.

Sec_J_Attach_

8_IWRP_Inc entive_Fee_P lan__24_Feb

_14

INSTRUMENT

ATION

WAFER

REPLACEME

NT PROGRAM

INCENTIVE

FEE PLAN

Will the Air Force consider amending the RFP to allow contractors to propose an alternate fee structure for the IWRP incentive plan? This would, of course be subject to a bilateral agreement between the parties.

Collaboration and agreement on the thresholds, objectives and bandwidths of the incentives will assure that appropriate levels of incentives are established to optimize contractor performance.

No

Guidance_

SSC_Se ction_L_10_

Mar_14_upda ted

13 4.2.3.5.2 Team

Structure (PWS

1.6.4.2)

d. Organizational

Manning

Matrix (Section

L Attachment 6, Guidance

Organizational

Manning Matrix)

Is the page count for Organizational

Manning Matrix included or excluded in the Technical Volume page count?

Need clarification on page count to size

Technical Volume proposal sections

Update Section L. Changes will be reflected in

Amendment 3. Section L Attachment 6 will not be included in the page count.

Sec_L_Attach

_6_Guidance

_Organizatio nal_Manning

_Matrix__10

_Feb_14

Do the roll-up levels of the WBS need to be populated, or should the matrix be populated at the level that the BOEs were estimated? For example, do rows need to be added to

WBSs 1.0, 1.1, 1.1.1 to summarize each of the Labor Categories used in all of the level 4 WBS elements

(1.1.1.X)?

Clarification whether summary levels are required. Note: Affects page count

The Matrix should be populated at the 4th WBS level as indicated on the Matrix. The 3rd, 2nd and 1st level does not need Labor categories populated unless there is an addition at that level of work. Only total FTE needs to be populated.

Doc. Page Para. Background/Issue Suggested Resolution Government Response Sec_L_Attach

_6_Guidance

_Organizatio nal_Manning

_Matrix__10

_Feb_14

“Notes and

Instructions”

Instructions 2 and 4

Deconfliction between Instructions 2 and 4 needed: Instruction 2 states

“Add labor category title, quantity of personnel fulfilling skill and annual hours each member will contribute to efforts of the specified WBS element”.

Instruction 4 states “FY Quantity” data should be reported as man-year based. i.e. FDE equivalent”

In this context, what is the nomenclature for “FED”? Does the man-year based quantity as stated in instruction

#4 replace the quantity of personnel and annual hours portion of Instruction #2?

Need clarification on what type of data required for populating the FY quantity column.

Update Section L Attachment 6. Changes will be reflected in Amendment 3. FDE was a typo. FTE means

Full Time Equivalent and the Matrix should only be populated to reflect FTE, not hours.

Section J Attachment

Example Award Fee Plan Update Section J attachment 7. Changes will be reflected in Amendment 3.

Draft SCD for Miniature Analog Translator (MAT) Draft SCD for MAT posted in bidders library.

Section L 2.2.1.1 Section L --- added parts c and d. Update Section L. Changes will be reflected in

Amendment 3.

CDRL A061

CDRL A062

CDRL A063

CDRL A070

CDRL A075

CDRL A076

CDRL A082

CDRL A083

CDRL A086

CDRL A087

CDRL A088

CDRL Delivery Timelines Updated to reflect Current OI guidance.

Update Section J Attachment 3a. Changes will be reflected in Amendment 3.