Sec_J_Attch_7_Guidance_SSC_Award-Fee_Plan__5_Mar_14.docx
DOCX document 62 KB Posted
- Attached to
- Guidance Subsystem Support Contract Federal contract opportunity
- Solicitation number
- FA8214-14-R-0004
About this file
Section J Attachment 7 Guidance SSC Award-Fee Plan
View the file
Other files for this federal contract opportunity
Show all 50
Guidance Subsystem Support Contract has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AWARD-FEE PLAN
FOR
GUIDANCE SUBSYSTEM
SUPPORT CONTRACT
4 February 2014
Approved:
DARYL J. HAUCK, Brig Gen, USAF
AFLCMC/SS
Fee Determining Official
Table of Contents
Section
Page
INTRODUCTION
ORGANIZATION
RESPONSIBILITIES
AWARD-FEE PROCESSES
AWARD-FEE PLAN CHANGE PROCEDURE
PERFORMANCE DEFICIENCIES IN PREVIOUS AWARD-FEE PERIODS
CONTRACT TERMINATION
Annex
AWARD-FEE ORGANIZATION
AWARD-FEE ALLOCATION BY EVALUATION PERIODS
AWARD-FEE PERFORMANCE EVALUATION AREA WEIGHTS AND RATINGS RELATIONSHIP
AWARD-FEE EVALUATION CRITERIA
SAMPLE AWARD-FEE PERFORMANCE POINTS COMPUTATION
I
I
1. INTRODUCTION
This award-fee plan is the basis for the evaluation of the contractor's performance on the Guidance Subsystem Support Contract (Guidance SSC) and for presenting an assessment of that performance to the Fee Determining Official (FDO). It describes specific criteria and procedures used to assess the contractor’s performance and to determine the amount of award-fee earned. As described below, the contractor may provide a self-assessment of contractor performance. Actual award-fee determinations and the methodology for determining award-fee are unilateral decisions made solely at the discretion of the Government; however, the determination is subject to the “Disputes Clause” of the contract.
The award-fee earned will be provided to the contractor through contract modifications. The award-fee earned and payable will be determined by the FDO based upon review of the contractor's performance against the criteria set forth in this plan. The FDO may unilaterally change this plan prior to the beginning of a new evaluation period. The contractor will be notified of changes to the plan by the Procuring Contracting Officer (PCO), in writing, before the start of the affected evaluation period. Changes to this plan that are applicable to a current evaluation period will be incorporated by mutual consent of both parties.
2. ORGANIZATION
The award-fee organization consists of: the Fee Determining Official (FDO), an Award-Fee Review Board (AFRB) (which consists of a chairperson and members, the contracting officer, and a recorder), other functional area participants, advisor members, and the performance monitors. The FDO, AFRB members, and performance monitors are listed in Annex 1.
3. RESPONSIBILITIES
| a. Fee Determining Official. The FDO approves the award-fee plan and any significant changes thereto. The FDO reviews the recommendation(s) of the AFRB, considers all pertinent data, and determines the earned award-fee amount for each evaluation period. | |
| b. Award-Fee Review Board. AFRB members review performance monitors’ evaluation of the contractor's performance, consider all information from pertinent sources, prepare interim performance reports, and arrive at an earned award-fee recommendation to be presented to the FDO. The AFRB may also recommend changes to this plan. | |
| c. Chairman, Award-Fee Review Board. AFRB Chairman is responsible for the overall functioning of the AFRB in the performance of its members. | |
| (1) Schedule all meetings of the AFRB and notify its members of the meetings. | |
| (2) Conduct the briefing to the FDO with regard to the recommendations of the AFRB. | |
| d. AFRB Recorder. The AFRB recorder is responsible for coordinating the administrative actions required by the performance monitors, the AFRB, and the FDO including: | |
| (1) Receive, process, and distribute evaluation reports from all required sources; | |
| (2) Schedule and assist with internal evaluation milestones such as briefings; and | |
| (3) Accomplish other actions required to ensure the smooth operation of the award-fee process. | |
| e. Procuring Contracting Officer (PCO). The PCO is the liaison between contractor and Government personnel. The PCO is the only individual authorized to monetarily obligate the Government. | |
| f. Performance Monitors. Performance monitors maintain written records of the contractor’s performance in their assigned evaluation area(s) so that a fair and accurate evaluation is obtained. Performance monitors prepare interim and end-of-period evaluation reports as directed by the AFRB. Performance monitors are prohibited from being AFRB members. |
4. AWARD-FEE PROCESSES
| a. Available Award-Fee Amount. The available award-fee for each evaluation period is shown in Annex 2. The award-fee earned will be paid based on the contractor’s performance during each evaluation period. |
| b. Task Activities to be Evaluated. Award-fee evaluation is limited to those completed task activities found on the Guidance Subsystem Task Log. |
| c. Evaluation Criteria. Evaluation criteria are located in Annex 4. Changes to the evaluation criteria will be made in accordance with Paragraph 5, Award-Fee Plan Change Procedure. Any changes to area weight or the evaluation criteria will be made by revising Annex 3 and/or 4. For the cost performance evaluation criteria for each evaluation period, a bilateral agreement will be reached on the budgeted work to be performed 14 calendar days after the start of that evaluation period. |
| d. Interim Evaluation Process. The AFRB Recorder notifies each AFRB member and performance monitor not less than 10 calendar days before the Quarterly PMR/Task Log Review. Performance monitors submit their evaluation reports to the AFRB not more than 5 calendar days after this notification. The AFRB determines the interim evaluation results and the Government notifies the contractor of the strengths and weaknesses for the current evaluation period during the Quarterly PMR/Task Log Review. The PCO may issue letters at any other time when it is deemed necessary to highlight areas of Government concern. |
| e. End-of-Period Evaluations. The AFRB Recorder notifies each AFRB member and performance monitor not less than 14 calendar days before the end of the evaluation period. Performance monitors submit their evaluation reports to the AFRB not later than 14 calendar days after the end of the evaluation period. The AFRB prepares its evaluation report and recommendation of earned award-fee. The AFRB chairperson briefs the evaluation report and recommendation to the FDO. At this time, the AFRB may also recommend any significant changes to the award-fee plan for FDO approval. The FDO determines the overall grade and earned award-fee amount for the evaluation period within 45 calendar days after each evaluation period. The FDO letter informs the contractor of the earned rating/award-fee amount which will be forwarded to the contractor by the contracting officer. The PCO issues a contract modification, authorizing the payment of the award-fee earned not later than 14 calendar days after the FDO’s decision is made. |
| f. Contractor’s Self-Assessment. When the contractor chooses to submit a self-evaluation, it must be submitted to the PCO within 10 calendar days after the end of the evaluation period. This written assessment of the contractor’s performance throughout the evaluation period may also contain any information that may be reasonably expected to assist the AFRB in evaluating the contractor’s performance. The contractor’s self-assessment may not exceed 10 pages including the title page. The contractor, if they desire, may brief the AFRB; briefing may not exceed 30 minutes, not including questions. |
5. AWARD-FEE PLAN CHANGE PROCEDURE
All significant changes are approved by the FDO. The PCO, in coordination with the AFRB Chairperson, approves other changes. Examples of significant changes include: changing evaluation criteria; adjusting weights (detailed in Annex 3) to redirect contractor’s emphasis to areas needing improvement; and revising the distribution of the award-fee dollars. The contractor may recommend changes to the PCO no later than 30 days prior to the beginning of the new evaluation period. The PCO shall notify the contractor in writing of any approved change(s) no later than 10 business days before the start of the upcoming evaluation period. Unilateral changes may be made to the award-fee plan if the contractor is provided written notification by the contracting officer no later than 10 business days before the start of the upcoming evaluation period. Changes affecting the current evaluation period must be by mutual agreement of both parties.
6. PERFORMANCE DEFICIENCIES IN PREVIOUS AWARD-FEE PERIODS
If, during the current award-fee period, performance or cost deficiencies from a prior award-fee period are discovered that show degradation which should have been detected in a prior award-fee period, the Government reserves the right to unilaterally decrease the size of the award-fee pool for the current award-fee period by an amount determined appropriate by the FDO.
7. CONTRACT TERMINATION
a. Termination for Convenience: In the event that the contract is terminated for the convenience of the Government, the amount of award-fee to which the contractor is entitled shall be determined as follows:
| (1) Award-Fee earned or earnable by the contractor for award-fee evaluation periods completed prior to the effective date of the termination will not be affected by the termination. Upon termination award fee amount will be calculated based upon a pro-rated ratio of completed days in award fee period. |
| (2) Award-Fee deemed earned and to be paid for performance during the period in which the termination becomes effective will be determined by the FDO in accordance with the approved award-fee criteria and will not be subject to negotiation as part of the equitable adjustment in accordance with the termination clause of the contract. For purposes of fee determination, contractor performance evaluation will end as of the date of termination. |
(3) The remaining award-fee dollars for all periods subsequent to the period in which the termination becomes effective will not be considered earned or earnable; therefore, will not be paid.
b. Termination for Default: If the Government terminates this contract for default (i.e., contractor's performance is less than satisfactory), the contractor shall not earn any fee for the period in which the default occurred. Consequently, no additional award-fee shall be paid during the termination settlement of the contract. Award-Fee earned or earnable by the contractor for award-fee evaluation periods completed prior to the effective date of the termination will not be affected by the termination.
5 ANNEXES
1. Award-Fee Organization
2. Award-Fee Allocation by Evaluation Periods
3. Award-Fee Performance Evaluation Area Weights and Ratings Relationship
4. Award-Fee Evaluation Criteria
5. Sample Award-Fee Performance Points Computation
ANNEX 1
Award-Fee Organization
Members
Fee Determining Official:
AF Program Executive Office/Strategic Systems
AFPEO/SS
Award-Fee Review Board Chairperson:
System Program Manager (SPM) or Deputy
AFNWC/NI
Award-Fee Review Board Members:
Flight Systems Division Chief or Deputy Flight Systems Chief Engineer Program Control Chief or Deputy Contracting Division Chief or Deputy Guidance Branch Chief Guidance Engineering Branch Chief Contracting Officer (Non-Voting Member) Recorder (Program Manager) (Non-Voting Member)
AFNWC/NIB
AFNWC/NIE
AFNWC/NIL
AFNWC/PZB
AFNWC/NIBA
AFNWC/NIBD
AFNWC/PZBF
AFNWC/NIBA
Advisors
| Staff Judge Advocate (or designee) | |
| 75 ABW/JAQ |
Performance Monitors
| Guidance Program Manager |
| AFNWC/NIBA |
| Guidance Engineer |
| AFNWC/NIBD |
| Vandenberg Program Manager |
| AFNWC/NIBA |
Vandenberg Engineer IWRP Program Manager IWRP Engineer
AFNWC/NIBD
AFNWC/NIBA
AFNWC/NIBD
ANNEX 2
Award-Fee Allocation by Evaluation Periods
The award-fee earned by the contractor will be determined at the completion of evaluation periods IAW Section II Services Summary of the PWS and shall begin on contract start date. The dollars shown corresponding to each period is the maximum available award-fee amount that can be earned during that particular period.
| Evaluation Period |
| From |
| To |
| Available Award-Fee * |
| I |
| 1 April 2015 |
| 30 Sep 2015 |
| II |
| 1 Oct 2015 |
| 31 Mar 2016 |
| III |
| 1 April 2016 |
| 30 Sep 2016 |
| IV |
| 1 Oct 2016 |
| 31 Mar 2017 |
| V |
| 1 April 2017 |
| 30 Sep 2017 |
| VI |
| 1 Oct 2017 |
| 31 Mar 2018 |
| VII |
| 1 April 2018 |
| 30 Sep 2018 |
| VIII |
| 1 Oct 2018 |
| 31 Mar 2019 |
| IX |
| 1 April 2019 |
| 30 Sep 2019 |
| X |
| 1 Oct 2019 |
| 31 Mar 2020 |
| XI |
| 1 April 2020 |
| 30 Sep 2020 |
| XII |
| 1 Oct 2020 |
| 31 Mar 2021 |
| XIII |
| 1 April 2021 |
| 30 Sep 2021 |
| XIV |
| 1 Oct 2021 |
| 31 Mar 2022 |
| XV |
| 1 April 2022 |
| 30 Sep 2022 |
| XVI |
| 1 Oct 2022 |
| 31 Mar 2023 |
Total
* Will be filled out after negotiations and included in the final award-fee plan.
ANNEX 3
Award-Fee Performance Evaluation Area Weights and Ratings Relationship
During the first award-fee period, the Government will evaluate contractor performance using the criteria identified in Annex 4, Award-Fee Evaluation Criteria. Performance Evaluation Areas and their respective weights are listed in the table below.
| AREA |
| PERFORMANCE EVALUATION AREA (PEA) |
| WEIGHT |
| 1 |
| Performance |
| 10% |
| 2 |
| Cost |
| 0% |
| 3 |
| Transition |
| 90% |
During the remaining award-fee periods, the Government will evaluate contractor performance using the criteria identified in Annex 4, Award-Fee Evaluation Criteria against task areas identified in the Guidance Subsystem PWS. Performance Evaluation Areas and their respective weights are listed in the table below.
| AREA |
| PERFORMANCE EVALUATION AREA (PEA) |
| WEIGHT |
| 1 |
| Performance |
| 80% |
| 2 |
| Cost |
| 20% |
| 3 |
| Transition |
| 0% |
The following table depicts the relationship between the overall performance ratings, the point spread of the ratings, and the percentage of the award-fee payable.
| Overall Rating |
| Total Points |
| Percent of Award-Fee Earned |
| Excellent |
| 91 - 100 |
| 91% - 100% |
| Very Good |
| 76 - 90 |
| 76% - 90% |
| Good |
| 51 - 75 |
| 51% - 75% |
| Satisfactory |
| 1 - 50 |
| Not Greater Than 50% |
| Unsatisfactory |
| 0 |
| 0% |
During the evaluation, the AFRB will award points for the contractor’s performance as measured against the criteria established in this plan. The points awarded in each evaluation area will be multiplied by the respective area weight. The weighted area points will then be summed to provide the total points earned. This number of total points earned will equal the percentage of the award-fee to be paid.
ANNEX 4
Award-Fee Evaluation Criteria
The Government will evaluate contractor performance using the criteria identified in the following four Performance Evaluation Area (PEA) tables.
Table 1 - PEA 1 - PERFORMANCE
| Sub PEA |
| EXCELLENT |
(91% – 100%) An award in this range indicates:
VERY GOOD
(76% – 90%) An award in this range indicates:
GOOD
(51% – 75%) An award in this range indicates:
SATISFACTORY
(No Greater Than 50%) An award in this range indicates
UNSATISFACTORY
(0%) An award in this range indicates:
1.1 Respons-iveness
1.1 Respons-iveness Cont.
Contractor provides all deliverables significantly ahead of Estimated Closure Date (ECD).
Maintains accurate status of tasks, recommends reprioritization, minimizes transitions between tasks, and recommends a more efficient use of resources.
Proactively reports potential schedule impacts to Guidance Subsystem Sustainment and develops feasible/successful mitigation plan.
Accommodates all requests for changes involving high priority tasks in a timely manner.
Accommodates most requests for changes on medium and low priority tasks.
Contractor provides all deliverables slightly ahead of Estimated Closure Date (ECD).
Maintains accurate status of tasks, recommends reprioritization, and minimizes transitions between tasks.
Regularly reports potential schedule impacts to Guidance Subsystem Sustainment and develops feasible/effective mitigation plan.
Accommodates most requests for changes on high priority tasks in a timely manner.
Accommodates some requests for changes on medium and low priority tasks.
Contractor provides most deliverables ahead of Estimated Closure Date (ECD).
Maintains accurate status of tasks and recommends reprioritization.
Reports potential schedule impacts to Guidance Subsystem Sustainment and develops mitigation plan on request.
Accommodates some requests for changes on high priority tasks in a timely manner.
Accommodates a few requests for changes on medium and low priority tasks.
Coordinates required changes (e.g., current status, ECD, prioritization) of Task Log items with the Government.
Contractor provides all deliverables by Estimated Closure Date (ECD).
Maintains accurate status of tasks.
Accommodates some requests for changes on high priority tasks.
Fails to meet the criteria for SATISFACTORY performance.
1.2 Deliver-able Quality Contractor execution of Task exceeds all technical requirements to resolve the issue without rework for work accomplished in the current or previous award-fee periods.
| Contractor execution of Task meets all and exceeds most technical requirements to resolve the issue without rework for work accomplished in the current or previous award-fee periods. |
| Contractor execution of Task meets all technical requirements to resolve the issue for work accomplished in the current or previous award-fee periods. |
*Minimal rework (<5%) of total task output required to satisfy technical task requirements.
Contractor execution of Task meets all technical requirements to resolve the issue for work accomplished in the current or previous award-fee periods.
*Some rework (<10%) of total task output required to satisfy technical task requirements.
Fails to meet the criteria for SATISFACTORY performance.
1.3 Innovation Contractor develops innovative solutions and new systems to improve management oversight, timeliness, and quality of the Guidance SSC technical and business processes.
Implements process improvement change demonstrated in one or more areas of responsiveness, quality, cost effectiveness, or any other scope.
Contractor develops innovative solutions and new systems to improve management oversight, timeliness, and quality of the Guidance SSC technical and business processes.
Provides mature process improvement plans to implement process improvements demonstrable in one or more areas of responsiveness, quality, cost effectiveness, or any other scope.
Contractor proposes innovative solutions and new systems to improve management oversight, timeliness, and quality of the Guidance SSC technical and business processes.
Provides draft process improvement plans for process improvements demonstrable in one or more areas of responsiveness, quality, cost effectiveness, or any other scope.
| Contractor participates in process improvement meetings with Guidance SSC team. |
| Fails to meet the criteria for SATISFACTORY performance. |
Table 2 PEA 2 – COST
| Sub PEA |
| EXCELLENT |
(91%- 100%) An award in this range indicates:
VERY GOOD
(76% – 90%) An award in this range indicates:
GOOD
(51% – 76%) An award in this range indicates:
SATISFACTORY
(No Greater Than 50%) An award in this range indicates:
UNSATISFACTORY
(0%) An award in this range indicates:
| 2.1 |
| **Increases task log completion by 10% or greater beyond tasks established at the beginning of the award-fee period within current budget while maintaining responsiveness and quality. |
| **Increases task log completion between 5% and 9.99% beyond tasks established at the beginning of the award-fee period within current budget while maintaining responsiveness and quality. |
| **Increases task log completion between 0% and 4.99% beyond tasks established at the beginning of the award-fee period within current budget while maintaining responsiveness and quality. |
| **Task log completion between 90% and 99.99% of tasks established at the beginning of the award-fee period within current budget while maintaining responsiveness and quality. |
| **Task log completion below 90% of tasks established at the beginning of the award -fee period within current budget. |
Fails to maintain current budget.
*Percentages of rework may be based on proportion of deliverable requiring corrections or proportion of schedule necessary to accomplish corrections.
**The Task Log will be the unit of measurement the Government utilizes to analyze cost efficiencies implemented by the Guidance SSC contractor. The Government recognizes that tasks can reach a level of criticality where a few tasks have the potential to out-prioritize and consume the entire budget. Consideration will be given to the Guidance SSC contractor in scenarios where cost efficiencies cannot be gained due to the level of complexity and urgency.
Table 3 PEA 3 – TRANSITION
| Sub PEA |
| EXCELLENT |
(91% – 100%) An award in this range indicates:
VERY GOOD
(76% – 90%) An award in this range indicates:
GOOD
(51% – 75%) An award in this range indicates:
SATISFACTORY
(No Greater Than 50%) An award in this range indicates:
UNSATISFACTORY
(0%) An award in this range indicates:
3.1
Transition
3.1 Transition Cont.
Proactively, effectively, and continuously meets with Government and ISC and PBC contractors immediately after Post Award Conference to assist in preparing the draft transition plan to ensure submission prior to 20 calendar days following Post Award Conference.
Complete the final transition plan and ensure submission prior to the first 55 calendar days after the Post Award Conference.
Accomplishes successful transition of all General Sustainment and CLS CLIN requirements and is effectively performing the requirements of the Guidance SSC PWS earlier than 6 months after contract award.
Proactively, effectively, and continuously meets with Government and ISC and PBC contractors immediately after Post Award Conference to assist in preparing the draft transition plan to ensure submission prior to 20 calendar days following Post Award Conference.
Complete the final transition plan and ensure submission prior to the first 55 calendar days after the Post Award Conference.
Accomplishes successful transition of all General Sustainment and CLS CLIN requirements and is effectively performing the requirements of the Guidance SSC PWS earlier than 6 months after contract award.
Effectively and continuously meets with Government and ISC and PBC contractors immediately after Post Award Conference to assist in preparing the draft transition plan to ensure submission no later than 30 calendar days following Post Award Conference.
Complete the final transition plan and ensure submission no later than 60 calendar days after the Post Award Conference.
Accomplishes successful transition of all General Sustainment and CLS CLIN requirements and is effectively performing the requirements of the Guidance SSC PWS no later than 6 months after contract award.
Continuously meets with Government and ISC and PBC contractors immediately after Post Award Conference to assist in preparing the draft transition plan to ensure submission no later than 30 calendar days following Post Award Conference.
Complete the final transition plan and ensure submission no later than 60 calendar days after the Post Award Conference.
Accomplishes successful transition of all General Sustainment and CLS CLIN requirements and is effectively performing the requirements of the Guidance SSC PWS no later than 6 months after contract award.
Fails to meet the criteria for SATISFACTORY performance
ANNEX 5
Sample Award-Fee Performance Points Computation
| PERFORMANCE EVALUATION AREA (PEA) |
| POINTS EARNED (0-100) |
| AREA WEIGHT |
| WEIGHTED % POINTS |
| PEA 1 – Performance |
| 92 |
| 70% |
| 64.4 |
| PEA 2 – Cost |
| 92 |
| 20% |
| 18.4 |
| PEA 3 – Transition |
| N/A |
| 0% |
| N/A |
| PEA 4 – Special Interest Item |
| 100 |
| 10% |
| 10 |
| Total Points Earned |
| 92.8 |
File details come from the government source that posted it. Updated .