Section_J_Attachment_3_PSSC_CDRL_Package.pdf

PDF 2 MB Posted

Attached to
Propulsion Subsystem Support Contract Federal contract opportunity
Solicitation number
FA8214-14-R-0003
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Section J Attachment 3 PSSC CDRL Package

View the file

Other files for this federal contract opportunity

Other files attached to Propulsion Subsystem Support Contract, newest first.
File Type Posted
PSSC_Questions_and_Answers_3.xlsx XLSX spreadsheet
Section_L_PSSC_Instructions_Conditions_and_Notices_to_Offerors.pdf PDF
FA821414R0003_______0003.pdf PDF
Section_J_Attachment_1_PSSC_Performance_Work_Statement.pdf PDF
PSSC_Questions_and_Answers_2.xlsx XLSX spreadsheet
Section_J_Attachment_1_PSSC_Performance_Work_Statement.pdf PDF
Section_J_Attachment_4_PSSC_Labor_Rate_Matrix.xlsx XLSX spreadsheet
Section_J_Attachment_3_CDRL_Package_PSSC.pdf PDF
Section_J_Attachment_5_PSSC_Labor_Categories.pdf PDF
PSSC_Questions_and_Answers_1.xlsx XLSX spreadsheet
Section_L_PSSC_Instructions_Conditions_and_Notices_to_Offerors.pdf PDF
Section_J_Attachment_6_PSSC_Mapping_Worksheet.xlsx XLSX spreadsheet
FA821414R0003_______0001.pdf PDF
Section_J_Attachment_5_PSSC_Labor_Categories.pdf PDF
Section_J_Attachment_6_PSSC_Mapping_Worksheet.xlsx XLSX spreadsheet
Section_L_Attachment_7_PSSC_Cross_Reference_Matrix.xlsx XLSX spreadsheet
Section_L_Attachment_1_PSSC_PPI_Tool.pdf PDF
Section_L_Attachment_4_PSSC_Consent_Form.pdf PDF
Section_L_Attachment_9_PSSC_EZSource_Instructions.pdf PDF
Section_L_Attachment_8_PSSC_Encryption_Instructions.pdf PDF
PPITool.accdb —
Section_J_Attachment_8_PSSC_GFP_Listing.pdf PDF
Section_L_Attachment_3_PSSC_Questionnaire.pdf PDF
Section_J_Attachment_9_PSSC_DD254.pdf PDF
Section_J_Attachment_2_PSSC_Government_Rights_in_Data_(GRID).docx DOCX document
FA821414R0003.pdf PDF
Section_L_Attachment_12_Sample_BOE_Summary.xlsx XLSX spreadsheet
Section_L_Attachment_5_PSSC_Commercial_Client_Auth.pdf PDF
Section_L_Attachment_11_PSSC_Transition_Matrix.xlsx XLSX spreadsheet
Section_J_Attachment_4_PSSC_Labor_Rate_Matrix.xlsx XLSX spreadsheet
Section_J_Attachment_7_PSSC_QASP.pdf PDF
PSSC_Bidders_Library_Instructions.docx DOCX document
Section_L_Attachment_6_PSSC_Roles_and_Responsibilities.xlsx XLSX spreadsheet
Section_M_PSSC_Evaluation_Factors_for_Award.pdf PDF
Section_L_Attachment_10_PSSC_CLIN_Pricing_Matrix.xlsx XLSX spreadsheet
Section_J_Attachment_3_PSSC_CDRL_Package.pdf PDF
Section_J_Attachment_1_PSSC_Performance_Work_Statement.pdf PDF
Section_J_Attachment_2_PSSC_Government_Rights_in_Data_(GRID)_20140718.docx DOCX document
Section_L_Attachment_11_PSSC_Transition_Matrix_20140717.xlsx XLSX spreadsheet
Section_L_Attachment_12_Sample_BOE_Summary.xlsx XLSX spreadsheet
Section_J_Attachment_1_PSSC_Performance_Work_Statement_20140714.docx DOCX document
Section_J_Attachment_4_PSSC_Labor_Rate_Matrix_20140717.xlsx XLSX spreadsheet
Section_J_Attachment_3_PSSC_CDRL_Instructions_and_Master_Listing_16_Jul_14.pdf PDF
Section_M_PSSC_20140714.docx DOCX document
Draft_RFP_Release_Comment_and_Replies_20140717.xlsx XLSX spreadsheet
ICBM_PSSC_GFP_Listing_20140718_Location.docx DOCX document
FA821414R0003.pdf PDF
Section_J_Attachment_5_PSSC_Labor_Categories_20140717.docx DOCX document
Section_L_Attachment_10_PSSC_CLIN_Pricing_Matrix_20140717.xlsx XLSX spreadsheet
Section_L_PSSC_20140717.docx DOCX document
Show all 50

Propulsion Subsystem Support Contract has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STANDARD FORM 1447 (2/2012)

Prescribed by GSA FAR (48 CFR) 53.215-1(d)

Contract Data Requirements List (CDRL) Program: Propulsion System Support contract (PSSC)

Date: 22 September 2014

Version:

1. Introduction

This document was developed in accordance with DOD MIL-STD 310000A and represents the general requirements for the Technical Data Package (TDP) for this program. The purpose of this Attachment, Technical Data Package, is to define the data deliverables due for this program, including the instructions for their development, and delivery. All specific delivery instructions are specified on the CDRL forms or its digital (word, excel, pdf) equivalent.

2. General Guidelines

The CDRL form, Department of Defense (DD) Form 1423, specifies the data required to be delivered to the Government, as well as the frequency and approval requirements. The Data Item Descriptions (DID), listed on the CDRL form, were selected from the Acquisition Streamlining and Standardization

Information System (ASSIST) and provide additional direction for data preparation.

3. Communications

Any correspondence related to requests for data delivery deviations and/or amendments, additions or deletions to the CDRL form shall be addressed to the Procuring Contracting Officer (PCO) with a courtesy copy to the Data Management Officer (DMO) (Air Force Nuclear Weapons Center (AFNWC)/NIES) and the cognizant program manager (PM). Copies of all forms & templates noted in this file are available as requested from your program manager, the DMO or your PCO.

4. Codes used in the DD Form 1423

The directions for submittal and approval of data is indicated in Blocks 7, 8, 9, 10, 11, 12, 13, 14, 15 or 16 of the DD Form 1423. Usually, the direction is in the form of a code (explained below). The following abbreviations/codes are common usage within AFNWC.

4.1 Block 7, DD Form 250 Requirements

Block 7 of the CDRL form indicates whether Procurement Quality Assurance (PQA) inspections and acceptance of deliverable data by DD Form 250 is required. “Draft” copies submitted for advance approval and “Preliminary Draft” copies submitted are exempt from the DD Form 250 requirements.

Information copies of DD Form 250 to accompany each letter of transmittal for this category of data.

Code Inspection Acceptance

SS Source (DD Form 250 or equivalent document)

Source (DD Form 250 or equivalent document)

DD Destination (DD Form 250 or equivalent document)

Destination (DD Form 250 or equivalent document)

SD Source (DD Form 250 or equivalent document)

Destination (DD Form 250 or equivalent document)

DS Destination (DD Form 250 or equivalent document)

Source (DD Form 250 or equivalent document)

Code Inspection

LT Letter of Transmittal only

NO No inspection or acceptance required

XX Inspection and acceptance requirements specified elsewhere in contract

S Indicates the contractor’s facility

D Indicates the primary destination point

4.2 Block 8, Approval Code

When document approval is required (code “A”), the approval authority (ORG) for that 1423 is designated with an (A). Approval coordination shall be done using the Contract Document Action Form (CDA).

When document approval is not required (code “N/A”), no approval of the CDRL is required (note that documents that do not require approval shall also be marked as “NO” or “LT” in block 7.

Code Description

A Approval Required

N/A Approval Not Required

4.3 Block 10, Frequency of Submittals

DAILY Daily

WEKLY Weekly

BI-WE Each 2 weeks

MTHLY Monthly

BI-MO Each 2 months

QRTLY Quarterly

ANNLY Annually

SEMIA Each 6 months

OTIME One time

ONE/R One time and revisions

R/ASR Revisions as required

ASGEN As generated

ASREQ As required*

DFDEL Deferred delivery

DFORD Deferred ordering

DFREQ Deferred requisitioning

ONE/P One time preliminary draft

XTIME Multiple separate submittals (i.e., 2Time, 3Time)

* When ASREQ is used in Blocks 10, 11, 12 or 13 an explanation of the requirements must be entered in

Block 16.

4.4 Block 12 and 13, Dates of Initial and Subsequent Submissions

ATP Authority To Proceed

ASGEN As generated

ASREQ As required*

CDR Critical Design Review

CA Contract Award

CO Change Order

CD Calendar Day(s)

CP/REQ Change page/as required

CP/O Change page/(only)

DCARC Defense Cost and Research Center

DFDEL Deferred delivery

FQT Formal Qualification Test

FCA Functional Configuration Audit

PCA Physical Configuration Audit

TRR Test Readiness Review

SA Supplemental Agreement

WD Working Day(s)

* When ASREQ is used in Blocks 10, 11, 12 or 13 an explanation of the requirements must be entered in

Block 16.

5. Supplemental Data Preparation Instructions

5.1 Data Item Description (DID) Tailoring

The DID is a specification for the preparation of data. DID tailoring is reflected in Block 16 of the CDRL form. “T” entered after the DID number in Block 4, means that the DID has been tailored. Block 4 tailoring is made to either relax preparation instructions or to tailor the DID to be in consonance with the source document tailoring contained in the Statement of Work (SOW), Performance Work Statement

(PWS) or Statement of Objectives (SOO).

5.2 Distribution Statement Marking

The designation in Block 9 of the CDRL form indicates that one of the following seven (7) authorized distribution statements from Department of Defense (DoD) Directive 5230.24 and Air Force Instruction

(AFI) 61.204 shall be annotated on that technical data. Distribution statements will be selected to denote the audience the data is intended for: A distribution statement marking is distinct from and in addition to a security classification marking assigned in accordance with (IAW) DoD 5200.1-R. Should Block 9 of the

CDRL form and the DID be in conflict, Block 9 of the CDRL form shall take precedence. The following distribution statements are authorized for use in marking technical documents:

Distribution Statement A:

Approved for public release; distribution is unlimited.

Distribution Statement B:

Distribution authorized to U.S. Government

Agencies only (fill in reason) (date of determination). Other requests for this document shall be referred to AFNWC/NI, 6054 Dogwood

Ave Bldg 1255, Hill AFB UT 84056-5816.

Distribution Statement C:

Agencies and their contractors (fill in reason) (date of determination). Other requests for this document shall be referred to AFNWC/NI, 6054 Dogwood

Ave Bldg 1255, Hill AFB UT 84056-5816.

Distribution Statement D:

Distribution authorized to the DoD and U.S. DoD contractors only for Administrative or Operational

Use determined as of (date of determination). Other requests shall be referred to AFNWC/NI, 6054

Dogwood Ave Bldg 1255, Hill AFB UT

84056-5816.

Distribution Statement E:

Distribution authorized to Department of Defense

(DoD) Components only (fill in reason) (date determination). Other requests shall be referred to

AFNWC/NI, 6054 Dogwood Ave Bldg 1255, Hill

AFB UT 84056-5816.

Distribution Statement F:

Further dissemination only as directed by

AFNWC/NI, 6054 Dogwood Ave Bldg 1255, Hill

AFB UT 84056-5816 (date of determination) or higher Department of Defense (DoD) authority.

Distribution Statement X:

Agencies and private individuals or enterprises eligible to obtain export-controlled technical data in accordance with (IAW) regulations implementing

10 U.S.C. 140 (date of determination). Controlling office is (insert).

5.3 Other Notices

All technical documents marked with Distribution Statements B, C, D, E, F, or X will also be marked with the following notices:

WARNING:

This document/software contains technical data/software whose export is restricted by the Arms Export

Control Act (Title 22, U.S.C., Sec 2751 et seq.) or the Export Administration Act of 1979, as amended, (Title 50, U.S.C., App 2401 et seq). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DOD Directive 5230.25.

Destruction Notice:

For classified documents, follow the procedures in DOD 5220.22M, National Industrial Security Program

Operating Manual, Chapter 5, Section 7, or DOD 5200.1R, Information Security Program Regulation, Chapter 6, Section 7. For unclassified, limited documents, destroy by any method that will prevent disclosure of contents or reconstruction of the document.

5.4 Pricing CDRL Items Separately

If blocks 17 and 18 of the DD form 1423 documents are marked as "N/A" and "NSP" respectively, then the Government does not want to separately group or price CDRL items. If blocks 17 and 18 are left blank, the Government intends to seek separate pricing for the development costs of each CDRL. This pricing is for development costs of the data items and is considered separate from data rights costs.

6. Supplemental Data Delivery Instructions

6.1 Due Dates

Due dates for delivery of data are to be construed as receipt at destination.

6.2 Late Delivery

Delivery of data is considered late if it does not arrive at its destination by 1530 hours (3:30 PM) Mountain

Time on the date specified in Blocks 12, 13 or 16 of the CDRL.

6.3 Submittal Procedures

6.3.1 CDRL Submittal Procedure

For the purposes of data submittal, unclassified CDRLs are submitted to the government via encrypted email to the recipient outlined in Block 14.

Each data submittal shall be accompanied by a Contract Document Action (CDA) form (please request current version from ORG1). If for any reason a CDA form is not available, a cover letter shall contain the following information:

1. Contract number

2. CDRL sequence number (i.e., A001)

3. Exact title and subtitle (if applicable) of the document being transmitted

4. Line item or CLIN number

5. Modification Number or Order Number

4. Document date, number, and revision information (if applicable)

5. Data delivery method and date of delivery

6. Whether the document is a draft, or final submittal

7. For approval data: State “For Approval”

8. If the document is a re-submittal, reference the Government letter Contractual Document Action (CDA) requesting re-submittal or disapproval of previous submittal

9. For periodic reports: The report period that the document covers

10. Distribution: Information disclosing the total contractual distribution being made per Block 14, or

Block 16 of the CDRL Form

6.3.2 Classified CDRL Submittal Procedure

Classified CDRLs and classified documentation are submitted in accordance with this instruction and are never to be emailed. Classified CDRLs or portions of a CDRL, as applicable, shall be forwarded IAW

Appendix B of the DD254. For Classified Disks send two (2) copies.

Outer Envelope:

Address

ATTN: Security Office/Document Control

Inner Envelope:

Address

ATTN: Name of person for whom the document should be delivered

7. Supplemental Data Review and Approval Process

7.1 Approval CDRLs

The letter “A” in Block 8 of the DD Form 1423 indicates that the Government must approve the data item.

In addition, Block 16 of the form may contain additional directions.

Written Written approval indicates agreement or concurrence with the contractor furnished

Approval data only and shall not be construed as changing any of the terms or conditions of the subject contract. The approval authority shall be ORG 1 as outlined in section 9 of this document. Approval shall take the form of either a letter signed by the PCO/DMO or concurrence using the Contractual Document Action (CDA) form, signed and dated by the representative stated in ORG 1. Data items submitted for approvals are NOT automatically approved without government approval.

Approved with

Comment or

Disapproved

The Contractor shall revise data items Approved with Comments or Disapproved in accordance with the specific written comments transmitted with the CDA or

PCO/DMO letter and resubmit not later than 30 calendar days (unless otherwise directed) from receipt of the Approval with Comments or Disapproval, unless otherwise directed. The resubmitted data will require a new approval cycle as indicated in Block 8 of the DD Form 1423.

Draft Versions of the CDRL

If a DD Form 1423 directs the Contractor to submit a “draft” version of an approval

CDRL in advance of the final version, the draft will be considered an information only submission. However, the PCO/DMO still retains the right to disapprove a draft data item that does not comply with the contract requirements. Unless otherwise directed by the PCO, the Contractor shall incorporate the Government’s comments in the final submission and shall not resubmit the draft version of the data item.

7.2 Contractual Document Action (CDA)

After the Government receives a data item submission, a Temporary Data Identification Number (TDID), a unique identifier to that submission, will be assigned by the DMO. The Government’s review of that data item will result in a coordinated CDA form, or PCO letter, indicating the data items approval or disapproval. Should the Government have comments on the data item; the CDA will include either comments on the CDA form itself or a Comment Resolution Matrix (CRM). Comments will be provided to the submitter in accordance with the format and timeline noted in block 16. Comments will be assigned one of the following codes:

COMMENT CODE CODE DESCRIPTION

C Critical Comments of a very serious nature that will preclude final approval and publication of the document. You are willing to elevate the comment or issue to senior organization leadership (e.g., general officer) and recommend they non-concur. These are the "show-stoppers". Convincing rationale for critical comments must be provided. The individual making the comment and the document writer will reconcile the comment.

S Substantive Comments of a less serious nature that have noticeable impact on the documents quality or content. The document appears to be incorrect, misleading, confusing, or inconsistent with other sections.

A Administrative Comments that address minor items such as typographical, format and/or grammatical errors.

7.3 Information Only CDRLs

When an “A” is not indicated in Block 8 of the DD Form 1423, the PCO/DMO still retains the right to disapprove any data that does not comply with contract requirements. The Contractor shall revise the disapproved data item in accordance with the specific written comments transmitted with the CDA form or PCO letter and resubmit not later than 30 calendar days, unless otherwise directed, from receipt of the disapproval. The resubmitted data will require a new approval cycle as indicated in Block 8 of the DD

Form 1423.

8. Data Accession List (DAL)

During performance of the contract, requests from the PCO for data ordered from the Data Accession List

(DAL) (with the application of DID DI-MGMT-81453A) shall be provided at no increase in contract price. Requests for quantities greater than two each per document shall be honored upon receipt of PCO direction and with Contractor concurrence that such request can be filled at no increase in contract price.

9. Organizational Cross Reference List

The following Organizational Cross Reference List shall be used in conjunction with the CDRLs to determine actual addressees for distribution of data. The ORG number will be entered in lieu of a address on the CDRL and will be a part of the CDRL package. Changes to the list will be identified by an asterisk next to the ORG number and a revision date to the list.

ORG#/ Name Address Attention/To Contact Info

ORG1/ AFNWC/NIBB 6059 Wardleigh Rd (Bldg.1204) Hill AFB UT 84056-5838

Program Manager

ORG2/AFNWC/NIBE 6030 Gum Ln (Bldg.1217) Hill AFB UT 84056-5825

Engineer

ORG3/AFNWC/NIEV 6054 Dogwood Ave (Bldg 1255) Hill AFB UT 84056-5816

TOMA

ORG4/AFNWC/NIES 6054 Dogwood Ave (Bldg 1255)

N/A

ORG5/AFNWC/NIEI 6054 Dogwood Ave (Bldg 1255) Hill AFB UT 84056-5816

N/A

ORG6/AFNWC/NIET 6054 Dogwood Ave (Bldg 1255) Hill AFB UT 84056-5816

N/A

ORG7/AFNWC/NIEV 6054 Dogwood Ave (Bldg 1255) Hill AFB UT 84056-5816

N/A

ORG8/AFGSC/A3I 245 Davis Ave E, Ste 256 Barksdale AFB LA 71110-2287

N/A

ORG9/75 ABW/SEG 7290 Weiner St., Bldg 383 Rm 215 Hill AFB UT 84056-5830

Safety

ORG10/AFNWC/PZBF 6014 Dogwood Ave (Bldg 1258) Hill AFB UT 84056-5816

Contracting Officer

ORG11/AFNWC/NIES 6054 Dogwood Ave (Bldg 1255) Hill AFB UT 84056-5816

Data Manager

ORG12/AFNWC/NIF 6054 Dogwood Ave (Bldg 1255)

Funds Manager

10. CDRL Master Listing Index

Full 1423’s for CDRL’s applicable to this program are included in section 11 of this document.

CDRL# Description DID

A001 Integrated Program Management Report (IPMR) DI-MGMT-81861

A002 Management Plan DI-MGMT-80004A/T

A003 Transition Plan DI-MGMT-80790/T

A004 Contractor's Risk Management Plan DI-MGMT-81808

A005 Conference Agenda (Meeting Agenda) DI-ADMIN-81249A

A006 Briefing Materials DI-MGMT-81605

Briefings for Meetings

Requirements Validation Board (RVB)

Point Papers

White Papers

Presentations

A007 Report, Record of Meeting/Minutes (Meeting Minutes) DI-ADMN-81505

A008 Status Report (Contract Update) DI-MGMT-80368A

A009 Item Unique Identification (IUID) Marking Plan DI-MGMT-81803

A010 Item Unique Identification (IUID) Marking Activity, Validation and Verification Report

DI-MGMT-81804A

A011 Performance & Cost Report DI-FNCL-80912/T

A012 RESERVED

A013 Contract Summary Report DI-ADMN-80447A/T

A014 Contract Funds Status Report (CFSR) DI-MGMT-81468

A015 Contract Work Breakdown Structure DI-MGMT-81334D

A016 Technical Report – Study/Services DI-MISC-80508B/T

A017 Flight Performance Report DI-MISC-80508B/T

A018 Environmental Management DI-MISC-80508B/T

A019 System/Subsystem Requirements DI-MISC-80508B/T

A020 RESERVED

A021 Risk Assessment Studies and/or Recommendations DI-MISC-80508B/T

A022 RESERVED

A023 Pollution Prevention Program DI-MISC-80508B/T

A024 National Environmental Policy Act (NEPA) DI-MISC-80508B/T

A025 Technical Summary Reports DI-MISC-80508B/T

A026 RESERVED

A027 Test Plan DI-NDTI-80566A

A028 Test Procedure DI-NDTI-80603A

A029 Test/Inspection Report DI-NDTI-80809B

A030 Quality Assurance Program Plan DI-QCIC-81794

A031 Technical Data Assessment DI-MISC-80734/T

A032 Technical Data Package Review Report DI-MISC-80750

A033 Product Drawings/Models & Associated List DI-SESS-81000D/T

A034 Engineering Change Proposal (ECP) DI-CMAN-80639C

A035 Specification Change Notice (SCN) DI-CMAN-80643C

A036 Interface Control Document (ICD) DI-CMAN-81248A

A037 Software/Firmware Change Request DI-MISC-81807

A038 Automated Computer Program Identification Number (ACPIN) Data & Control Record

DI-MISC-81454B

A039 Software Version Description (SVD) DI-IPSC-81442A

A040 Software Test Plan (STP) DI-IPSC-81438A

A041 Software Test Description (STD) DI-IPSC-81439A

A042 Software Test Report (STR) DI-IPSC-81440A

A043 System Safety Program Plan (SSPP) DI-SAFT-81626

A044 Safety Studies Plan DI-SAFT-81066/T

A045 Safety Studies Report DI-SAFT-81065/T

A046 Safety Assessment Report (SAR) DI-SAFT-80102B

A047 Pollution Incident Report DI-SAFT-80494A

A048 Environmental Permits DI-MISC-81274

A049 Chemical Accident or Incident Report DI-SAFT-80975

A050 Photographic Requirements DI-SAFT-81126

A051 Mishap Risk Assessment Report (MRAR) DI-SAFT-81300A

A052 Accident/Incident Report (Mishap Report) DI-SAFT-81563/T

A053 Deficiency Report (DR) DI-ALSS-81535/T

A054 Government Industry Data Exchange Program (GIDEP) Annual Progress Report DI-QCIC-80127A

A055 Programmatic Environmental Safety & Health Evaluation (PESHE) DI-ENVR-81840

A056 Environmental Health & Safety Plan (HSP) DI-ENVR-81375

A057 Corrosion Prevention & Control Plan DI-MFFP-81403/T

A058 Environmental Compliance Assessment and Management Program (ECAMP) Action Plan Report

DI-MGMT-80898

A059 Hazardous Materials Management Program (HMMP) Plan DI-MGMT-81398A

A060 Contractor's Corrective Action Plan DI-MGMT-80501

A061 Technical Manual Contracts Requirement TMCR TM-86-01

A062 Commercial Off-The-Shelf (COTS) Manuals and Associated Supplemental Data DI-TMSS-80527C

A063 Source Data for Forecasting Diminishing Manufacturing Sources & Materiel Shortages (DMSMS)

DI-SESS-81656

A064 Technical Data Package Index DI-EGDS-80918/T

A065 Proposed Spare Parts List DI-ILSS-80134A

A066 Data Accession List DI-MGMT-81453A/T

A067 Technical Manual Research and Analysis Source Data DI-TMSS-81354

11. DD Form 1423s (full 1423’s)

*1423’s, block A Reference Number: CLIN number to be added at time of award

**1423’s block E Reference Number: Contract and Mod/TO number to be added at time of award

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

ICBM/PROPULSION SUBSYSTEM

SUPPORT CONTRACT (PSSC)

FA8214-14-R-0003

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A001

INTEGRATED PROGRAM MANAGEMENT

REPORT (IPMR)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

TOTAL PRICE

DI-MGMT-81861 PWS Paras 1.6.5.5.1, 1.6.5.9 AFNWC/NIBB

7. DD 250 REQ 9.DIST STATEMENT

REQUIRED

10. FREQUENCY 12. DATE OF FIRST

SUBMISSION

14. DISTRIBUTION

LT

MTHLY SEE BLK 16

b. COPIES

8. APP CODE D 11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft Final

EOM SEE BLK 16

Reg

Repro

16. REMARKS: CHANGES TO OFFICE SYMBOLS, WHEN NECESSARY, SHALL

BE MADE BY THE CO/ACO WITHOUT REVISIONS TO THE CDRL.

BLOCK 4:

1. All formats shall be submitted electronically in accordance with the

DoD-approved XML schemas located in the EVM Central Repository

(EVM-CR) http://dcarc.cape.osd.mil/EVM/Uncefact.aspx.

2. All IPMR files must be electronically forwarded to the EVM-CR at the

DCARC Web site at http://dcarc.cape.osd.mil/EVM.

3. Section 2.2.3 – Formats 1 and 4 are required additionally to be submitted in Human readable format such as MS Excel/Word compatible.

4. Only Formats 1, 4, 5, and 7 are required.

5. Formats 1 & 4 shall be submitted using the DoD-approved cost XML guideline and schema.

6. Formats 5 shall be submitted in contractor format.

7. Format 7 shall be submitted using the DoD-approved time-phased cost

SML guideline and schema.

8. IPMRs, when required from subcontractors, will be provided electronically using the DoD-approved SML formats.

9. Format 1 Instructions: Work Breakdown Structure (WBS) elements shall be reported in accordance with the PMO approved contractually required WBS. This is also known as the “Reporting Level.”

The Government reserves the right, with prior notice, to request temporary visibility into WBS elements one level below the contractual WBS>

Only ACWP, BAC, EAC, and VAC are required to be filled out for reporting purposes to the Government.

10. Format 2 Instructions: Not Required

11. Format 3 Instructions: Not Required

12. Format 4 Instructions: Not Required

EVM-CR

ORG1 (Lt of delivery only)

ORG2 (Lt of delivery only)

ORG10 (Lt of delivery only)

ORG11 (Lt of delivery only)

ORG12 (Lt of delivery only)

15. TOTAL 1

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Nancy N. Baker, GS-12

Data Manager

AFNWC/NIES

22 Sep 14

DD Form 1423-1, FEB 2001 Page___1__of__2_ Page

LM 11-50

http://dcarc.cape.osd.mil/EVM/Uncefact.aspx http://dcarc.cape.osd.mil/EVM

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP X TM OTHER _____ ____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued): CDRL A001 Continued.

Significant changes that require explanations in Format 5 are those that change the absolute value of the projected total staff-months at completion of any organizational or functional category by more than =/-5%.

Staffing forecast should be by month for the next six months and quarterly thereafter.

13. Format 5 Instructions:

Format 5 shall address major accomplishments and tasks worked during the month along with major barriers to accomplishing the planned work.

The variance analysis thresholds are:

o 10% for current period variances (ACWP greater than planned).

o 5% for cumulative cost variances (ACWP greater than planned).

o 5% for at complete variances.

Narrative explanations required and variance thresholds will be reviewed periodically and may be adjusted by contract modification with no change to contract price.

The contractor will notify the Government monthly on which reportable WBSs exceeded the threshold no later than the 7 th working day after the accounting close.

o The Government may notify the contractor which 15 variances are reportable in the current period no later than the 10 th working day after accounting close.

o Without Government direction, the contractor shall report the top three current months, cumulative, and at complete variances. A total of 15 WBS elements are reported, as applicable.

o The contractor or the Government may identify additional variances to report over the 15 to cover emerging trends. Items shall be reviewed monthly to see if still required; the intent of the requirement is temporary. This can be at one level below the established Format 1 WBS level.

Variance analysis narratives shall be reported at the reporting level as determined by the WBS level on

Format 1. The narratives also shall:

o Quantify and explain the root cause of the variance and account for at least the majority of the variance amount exceeding the threshold.

o Specific corrective actions, forecasted closure date, and impact to the Estimate at Completion

(EAC) shall be included in each variance narrative.

o If there are no changes to the reportable element problem analysis, the expected impacts, or corrective action status, then specify, “no changes since the last reported analysis” and reference the IPMR date when the narrative was reported.

14. Format 6 Instructions: Not Required.

15. Format 7 Instructions: Work Breakdown Structure (WBS) elements shall be reported in accordance with the

PMO approved contractually required WBS (ACWP, BAC, EAC, & VAC).

BLOCK 9:

Distribution Statement D: (see pages 3 & 4 for distribution statement, warning, and destruction notices)

BLOCKS 10, 11, 12 & 13:

Initial Submittal:

Contractor shall submit initial Integrated Program Management Report (IPMR) (Formats 1, 4, 5, & 7) NLT the 17 business days after the end of the second full accounting period following Authorization to Proceed (ATP).

Subsequent Submittals:

Contractor shall submit subsequent IPMR, containing the required Formats, NLT 17 days after the close of the contractor’s monthly or periodic accounting cycle. Format 7 is due annually, NLT 20 days after the end of the fiscal year. Final submissions are due when the last significant milestone/deliverable as defined by the contract has been achieved and remaining risk areas have been mitigated. Government will be allowed 10 days, after receipt from contractor, to review comments. Contractor shall submit revised IPMR incorporating Government comments, if applicable, on the following month’s IPMR.

BLOCK 14: Contractor shall submit IPMR to EVM-CR as directed.

DD Form 1423-1, FEB 2001 Page___2__of___2__Page

(1 Data Item)

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

A002

MANAGEMENT PLAN

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MGMT-80004A/T PWS Paras 1.6.5.6.1, 1.6.5.9 AFNWC/NIBB

10. FREQUENCY 12. DATE OF FIRST

SUBMISSION

ANNLY SEE BLK 16

a. ADDRESSEE

Draft

A

SEE BLK 16 SEE BLK 16

1. Delete paragraph 2.c. in its entirety.

Distribution Statement D: (see page 3 & 4 for distribution statement, warning, and destruction notices)

Contractor shall submit Management Plan NLT 30 days after award of contract. Government will be allowed 30 days, after receipt from contractor, to review for approval/disapproval/comments. Contractor shall submit updated Management Plan incorporating Government comments, if applicable, NLT 30 days after receipt from Government.

Contractor shall submit revised Management Plan no more than once a year. Government will be allowed 15 days after receipt from contractor, to review for approval/disapproval/comments. Contractor shall submit updated change pages incorporating Government comments, if applicable, NLT 15 days after receipt of comments from

Government.

BLOCK 14: Contractor shall submit Management Plan to ORG1 (see page 7 for address).

ORG1

DD Form 1423-1, FEB 2001 Page___1__of__1_ Page

(1 Data Item)

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE

GROUP

A003 TRANSITION PLAN SEE BLK 16

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MGMT-80790/T PWS Paras 1.6.5.8.3, 1.6.5.9 AFNWC/NIBB

10. FREQUENCY 12. DATE OF FIRST

SUBMISSION

2TIME SEE BLK 16

a. ADDRESSEE

Draft

N/A SEE BLK 16

16. REMARKS: CHANGES TO OFFICE SYMBOLS, WHEN NECESSARY,

SHALL BE MADE BY THE CO/ACO WITHOUT REVISIONS TO THE CDRL.

BLOCK 3:

Includes: Data Transition and Housing

1. Paragraph 3.1: delete “from development to production” replace with “support operations”

2. Paragraph 10.2.1: delete everything after “all” and replace with “GFP/data/tools/models, and tasks to be transferred.”

3. Paragraph 10.2.2: delete in its entirety.

4. Paragraph 10.2.3: delete everything after “Plan”

5. Paragraph 10.2.4: delete everything after “as” and replace with “impacts, risks, and mitigation(s) of on-going

Propulsion efforts and transfer of GFP/GFE.”

6. Paragraph 10.3: delete everything after “Format” and replace with “Contractor format acceptable.”

7. Paragraph 10.3.1: replace “utilized” with “implemented”

8. Paragraph 10.3.2: delete in its entirety.

9. Paragraph 10.3.3: delete in its entirety.

Distribution Statement D: (see pages 3 & 4 for distribution statement, warning, and destruction notices)

DD Form 1423-1, FEB 2001 Page___1__of__2_ Page

LM 12-13

(1 Data Item)

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued): CDRL A003 Continued.

BLOCKS 10, 12 & 13:

Contractor shall submit initial Transition Plan NLT 20 days after award of contract. Government will be allowed 20 days, after receipt from contractor, to review for approval/disapproval/ comments. Contractor shall submit revised Transition Plan incorporating Government comments, if applicable, NLT 15 business days after receipt from Government.

Contractor shall submit a draft Transition Plan (Phase Out/Follow On) NLT nine months prior to contract completion. Government will be allowed 30 days after receipt from contractor to review for comments.

Contractor shall submit revised Transition Plan (Phase Out/Follow On) NLT 60 days prior to contract completion. Government will be allowed 20 days after receipt to review for approval/disapproval/comments.

Contractor shall submit revised Transition Plan incorporating Government comments, if applicable, NLT 15 days after receipt from Government.

BLOCK 14: Contractor shall submit initial Transition Plan to ORG1 (see page 7 for address).

DD Form 1423-1, FEB 2001 Page___2__of___2__Page

(1 Data Item)

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

A004 CONTRACTOR’S RISK MANAGEMENT PLAN

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MGMT-81808 PWS Paras 1.6.5.1.3, 1.6.5.9 AFNWC/NIBB & AFNWC/NIES

10. FREQUENCY 12. DATE OF FIRST

SUBMISSION

1TIME SEE BLK 16

a. ADDRESSEE

Draft

Contractor shall submit Contractor’s Risk Management Plan NLT 30 days after award of contract. Government will be allowed 20 days, after receipt from contractor, to review for comment. Contractor shall submit revised Risk Management Plan incorporating Government comments, if applicable, NLT 15 days after receipt from Government.

Contractor shall submit subsequent submittals as required by the

BLOCK 14: Contractor shall submit Contractor’s Risk Management

Plan to ORGs 1&4 (see page 7 for address).

ORG 4

15. TOTAL 2

DD Form 1423-1, FEB 2001 Page___1__of__1_ Page

(1 Data Item)

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

A005 CONFERENCE AGENDA Meeting Agenda

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-ADMN-81249A PWS Paras 1.6.5.4.3.3, 1.6.5.9 AFNWC/NIBB

10. FREQUENCY 12. DATE OF FIRST

SUBMISSION

ASREQ N/A

a. ADDRESSEE

Draft

N/A N/A

Contractor shall submit the following Conference Agenda (Meeting

Agenda) NLT 5 days prior to scheduled meetings: Technical Council, Technical Interchange Meetings, Corrosion Prevention Advisory

Board, Task Log Review (Management Review), Interface Control

Working Group, DMSMS Working Group, Materiel Review Boards, ICBMSD System Engineering, Environment, Safety, & Technical

Data (NIEV) Safety IPTs, ICBM Nuclear Surety Working Group

(NSWG), Air Force Nuclear Weapon System Safety Groups

(NWSSG), ICBM Project Officers Working Group (POG), Nuclear

Security Working Groups, ICBM Codes Conference, and Risk

Management Boards.

Agenda) NLT 10 days prior to scheduled meetings: Reliability

Scoring Panel, and Configuration Control Board (CCB) to include

Technical Requirements Working Group (TRWG), and Technical

Review Board (TRB).

Agenda) NLT 15 days prior to scheduled meetings: Program

Management Reviews.

DD Form 1423-1, FEB 2001 Page___1__of__2_ Page

(1 Data Item)

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued): CDRL A005 Continued.

Government will be allowed 2 days, after receipt from contractor, to review for comments. Contractor shall submit revised Conference Agenda (Meeting Agenda) incorporating Government comments, if applicable, NLT

2 days after receipt from Government.

Contractor shall provide Conference Agenda (Meeting Agenda) NLT 5 days prior to all meetings deemed necessary by the Government unless specifically stated above or agreed upon by Government and contractor. If deemed necessary, Government may require specific meeting agendas further in advance than outlined.

Reasonable notice and deadlines will be given for such instances.

BLOCK 14: Contractor shall submit Conference Agenda (Meeting Agenda) to ORG1 (see page 7 for address).

DD Form 1423-1, FEB 2001 Page___2__of___2__Page

(1 Data Item)

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

A006

BRIEFING MATERIALS

1. Briefings for Meetings

2. Requirements Validation Board

3. Point Papers

4. White Papers

5. Presentations

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MGMT-81605

PWS Paras 1.6.5.4.3.3, 1.6.5.9, 1.6.6.1.3.4.1, 1.6.6.1.3.4.2, 1.6.6.1.7.1.1, 1.6.6.1.8.5, 1.6.6.1.9.1, 1.6.6.1.12.1, 1.6.6.1.16.2.2, 1.6.6.1.21.7.1, 1.6.6.2.1.2, 1.6.6.2.5.8

AFNWC/NIBB

10. FREQUENCY 12. DATE OF FIRST

SUBMISSION

ASREQ SEE BLK 16

a. ADDRESSEE

Draft

This CDRL may contain technical or non-technical data.

Contractor shall submit the following Briefing Material NLT 5 days prior to scheduled meetings: Technical Council, Technical Interchange

Meetings, Corrosion Prevention Advisory Board, Task Log Review

(Management Review), Interface Control Working Group, DMSMS

Working Group, Materiel Review Boards, ICBMSD System

Engineering, Environment, Safety, & Technical Data (NIEV) Safety

IPTs, ICBM Nuclear Surety Working Group (NSWG), Air Force

Nuclear Weapon System Safety Groups (NWSSG), ICBM Project

Officers Working Group (POG), Nuclear Security Working Groups, ICBM Codes Conference, and Risk Management Boards.

Contractor shall submit the following Briefing Material NLT 10 days prior to scheduled meetings: Reliability Scoring Panel, and

Configuration Control Board (CCB) to include Technical

Requirements Working Group (TRWG), and Technical Review Board

(TRB).

ORG2

15. TOTAL 1 1

DD Form 1423-1, FEB 2001 Page___1__of__2_ Page

(1 Data Item)

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued): CDRL A006 Continued.

Contractor shall submit the following Briefing Material NLT 15 days prior to scheduled meetings: Program

Management Reviews.

Government will be allowed 2 days, after receipt from contractor, to review for approval/disapproval/comments.

Contractor shall submit revised Briefing Material incorporating Government comments, if applicable, NLT 2

Contractor shall provide Briefing Material NLT 5 days prior to all meetings deemed necessary by the

Government unless specifically stated above or agreed upon by Government and contractor. If deemed necessary, Government may require specific meeting agendas further in advance than outlined. Reasonable notice and deadlines will be given for such instances.

BLOCK 14: Contractor shall submit Briefing Material to ORG1 (see page 7 for address).

DD Form 1423-1, FEB 2001 Page___2__of___2__Page

(1 Data Item)

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

A007

REPORT, RECORD OF MEETING/MINUTES

Meeting Minutes

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-ADMN-81505

PWS Paras 1.6.5.4.3.3, 1.6.5.9, 1.6.6.1.20.3

10. FREQUENCY 12. DATE OF FIRST

SUBMISSION

a. ADDRESSEE

Draft

Contractor shall submit Report, Record of Meeting Minutes (Meeting

Minutes) NLT 15 days after meeting or event has been held.

Government will be allowed 5 days, after receipt from contractor, to review for approval/disapproval/comments. Contractor shall submit revised Meeting Minutes incorporating Government comments, if applicable, NLT 5 days after receipt from Government.

BLOCK 14: Contractor shall submit Meeting Minutes to ORG1 (see

DD Form 1423-1, FEB 2001 Page___1__of__1_ Page

(1 Data Item)

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

A008

STATUS REPORT

Contract Update

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MGMT-80368A PWS Paras 1.6.5.4.1, 1.6.5.9 AFNWC/NIBB

10. FREQUENCY 12. DATE OF FIRST

SUBMISSION

MTHLY SEE BLK 16

a. ADDRESSEE

Draft

Contractor shall submit initial Status Report for Contract Update the th day of the month following the first complete month of the contract.

Subsequent Submittals:

Contractor shall submit subsequent Status Report for Contract Update the 10 th day of each month thereafter for the duration of the contract.

Government will be allowed 10 days, after receipt from contractor, to review for comments. Contractor shall submit revised Status Report for Contract Update incorporating Government comments, if applicable, NLT 10 days after receipt from Government.

BLOCK 14: Contractor shall submit Status Report for Contract

Update to ORG1 (see page 7 for address).

DD Form 1423-1, FEB 2001 Page___1__of__1_ Page

(1 Data Item)

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

A009

ITEM UNIQUE IDENTIFICATION (IUID)

MARKING PLAN

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MGMT-81803 PWS Paras 1.6.5.9, 1.6.6.1.19.1 AFNWC/NIBB

10. FREQUENCY 12. DATE OF FIRST

SUBMISSION

a. ADDRESSEE

Draft

This CDRL contains technical data.

Contractor shall submit Item Unique Identification (IUID) Marking

Plan NLT 30 days after contract award. Government will be allowed

20 days after receipt from contractor to review for approval/ disapproval/comments. Contract shall submit revised IUID Marking

Plan incorporating Government comments, if applicable, NLT 10 days after receipt from Government.

BLOCK 14: Contractor shall submit IUID Marking Plan to ORG1

(see page 7 for address).

DD Form 1423-1, FEB 2001 Page___1__of__1_ Page

(1 Data Item)

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

A010

ITEM UNIQUE IDENTIFICATION (IUID)

MARKING ACTIVITY, VALIDATION AND

VERIFICATION REPORT

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MGMT-81804A PWS Paras 1.6.5.9, 1.6.6.1.19.1 AFNWC/NIBB

10. FREQUENCY 12. DATE OF FIRST

SUBMISSION

a. ADDRESSEE

Draft

Contractor shall submit Item Unique Identification (IUID) Marking

Activity, Validation and Verification Report NLT 45 days prior to contract end. Government will be allowed 15 days after receipt from contractor to review for approval/disapproval/comments. Contractor shall submit revised IUID Marking Activity, Validation and

Verification Report incorporating Government comments, if applicable, NLT 15 days after receipt from Government.

BLOCK 14: Contractor shall submit IUID Marking Activity, Validation and Verification Report to ORG1 (see page 7 for address).

DD Form 1423-1, FEB 2001 Page___1__of__1_ Page

(1 Data Item)

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER ___X_____

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

A011 PERFORMANCE & COST REPORT…