Questions_and_Answers_dated_25Jul2017.pdf

PDF 17 KB Posted

Attached to
Paving Federal contract opportunity
Solicitation number
FA8201-17-R-0007
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Questions and Answers dated 25Jul2017

View the file

Other files for this federal contract opportunity

Other files attached to Paving, newest first.
File Type Posted
Questions_and_Answers_dated_25Jul2017_B.pdf PDF
Site_Visit_12Jul2017-_Attendee_Roster-_Corrected24Jul2017.pdf PDF
Site_Visit_12Jul2017-_Attendee_Roster.pdf PDF
Questions_and_Answers_Dated_20_Jul_2017.pdf PDF
ProjectLimits_New_Waterway_and_ADA_Ramp.JPG JPG image
Concrete_Vault.pdf PDF
ProjectLimits_Southwest_Gate.JPG JPG image
Core_Sample_Results.pdf PDF
Questions_and_Answers_19Jul2017.pdf PDF
HWY_&_Roads_223.pdf PDF
HWY_&_Roads_121.pdf PDF
HWY_&_Roads_142.pdf PDF
HWY_&_Roads_141.pdf PDF
Seed_Project_Statement_of_Work_-6th_Street_Southgate_to_SW_Gate_Revised_19Jul2017.pdf PDF
HWY_&_Roads_131.pdf PDF
Waterway_drawing.JPG JPG image
ProjectLimits_Southgate_Avenue.JPG JPG image
Questions_and_Answers_10Jul2017.pdf PDF
Questions_and_Answers_dated_6Jul2017.pdf PDF
Seed_project_site_maps.pdf PDF
Basic_IDIQ_Statement_of_Work_26JUN2017.pdf PDF
SF_1442_Paving_Solicitation.pdf PDF
Section_M_13_June_2017.docx DOCX document
Paving_Wage_Decisions.pdf PDF
Seed_Project_Statement_of_Work_-6th_Street_Southgate_to_SW_Gate.docx DOCX document
Paving_Site_Visit_memo.pdf PDF
Pricing_Matrix_16Jun2017.xlsx XLSX spreadsheet
Section_L_13_June_2017.docx DOCX document
BASE_FACILITY_DESIGN_STANDARD_-_13_Apr_2017.docx DOCX document
Section_M_Draft.pdf PDF
APPENDIX_A.docx DOCX document
Paving__Draft_SOW_15_March_2017.pdf PDF
Section_L_Draft.pdf PDF
FA8201-17-R-0007_Draft_RFP.pdf PDF
6th_Street_Southgate_to_SW_Gate_Seed_SOW.pdf PDF
APPENDIX_E_Landfill_Map.pdf PDF
APPENDIX_C_Safety_Plan.pdf PDF
APPENDIX_D_Explosive_awareness.pdf PDF
Question_Comment_Res_Matrix_Paving.xlsx XLSX spreadsheet
APPENDIX_B.docx DOCX document
Copy_of_Attachment_14_-_Construction_cost_estimate_breakdown_Rev2.xlsx XLSX spreadsheet
Show all 41

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Source Selection Information - FAR 2.101 and 3.104

Question # Contractor Question Government Response

We were told to provide an RS Means estimate however we were also told to use the spreadsheet provided. Are we to use specific RS Means line items and then apply our mark-up etc to them? Typically there is a multiplier that is added to deducted to those line items. How do we account for that? This creates a bid tabulation that is exported, should we provide this export?

Applying multipliers/deductions is permissible, however please ensure that each multiplier/deduction is explained/justified.

Please annotate if multipliers/deductions are applied globally to all lines, or to specific line items. Any bid tabulation created from a software tool may be submitted as supporting documentation to the Construction Cost Estimate worksheets. As a reminder, for the Government to understand your estimating techniques and methods within your price proposal volume, Section L paragraph

4.5 states to provide a summary description of your standard estimate system or methods.

During the meeting portion of the site walk we were told to create line items in the spreadsheet for our pricing. Are these required to be copied from RS Means or can we use Contractor Created line items? If our subcontractor does not use RS Means line items can we itemize their bids as long as we use the pricing template form provided in the RFP docs?

During the Questions and Answers (Q&A) session of the site visit, the Government briefly reiterated the information provided on FBO regarding the Pricing Matrix. In accordance with (IAW) Section L paragraph 4.2 The offeror shall not alter the formulas or content of the spreadsheets, and shall only populate the shaded cells. IAW Section L paragraph 4.5, when responding to the Price Volume requirements in the solicitation, the offeror and associated subcontractors shall use generally accepted construction estimating techniques using an RS Means based estimating system, such as RSMeans, e4Clicks, or CO approved equivalent, to develop their estimates on the “Seed” Project. If necessary the offeror may create line items if no appropriate ones exist. If a subcontractor does not use RS Means based estimating system, the prime can itemize the subcontract bids on the pricing template form themselves.

Paving Indefinite Delivery Indefinite Quantity (IDIQ)

Solicitation # FA8201-17-R-0007

Questions and Answers Date: 25-Jul-2017

Could you please provide some type of background for the TCIR and DART rate? If a company does not have those rates, is there a particular format you would like us to follow when completing the Volume III-Contract Documentation portion?

Please visit https://www.osha.gov/ for additional information on TCIR and DART rates. IAW Section L paragraph 6.1.5 an offeror that does not possess established TCIR and DART rates shall submit consecutive recording data for the time period available such as workers compensation, insurance rates, etc. and shall provide a document with an explanation regarding why the offeror does not have TCIR and DART rates and how the recording data provided is comparable to TCIR and DART rates. Format information is provided in Section L paragraph 3.18.