Att9_170123_Liquidated Damages Signed.pdf

PDF 185 KB Posted

Attached to
WWYK170123, Repair Roof, Log Facility Dep Ops B201
Solicitation number
FA8137-26-R-0035
Issued by

About this file

This is a Liquidated Damages assessment document for a roof repair project at a logging facility. Project WWYK170123 concerns repair work on the roof of the Log Facility Department Operations Building B201. The document establishes liquidated damages of $227.75 per calendar day for any delay in completing the work, assessed in accordance with FAR 36.206 and DFARS 236.206.

The daily liquidated damages calculation comprises two components: engineering costs totaling $122.36 per day and government costs totaling $105.39 per day. Engineering costs include 0.5 hours of Engineering Manager time at $57.69/hour, 1 hour of Project Manager time at $36.06/hour, 1 hour of Engineering Tech/Inspector time at $28.52/hour, 0.5 hours of Project Engineers time at $38.46/hour, and 0.5 hours of Clerical time at $19.41/hour. Government costs include 0.5 hours of FAS (GS-12/5) time at $39.19/hour, 1 hour of Legal (GS-13/5) time at $46.60/hour, and 1 hour of Contracting (GS-12/5) time at $39.19/hour. The assessment is justified based on the contractor's complete control of work pace, the contract's provision for daily liquidated damages, and the reasonableness of the rate relative to project requirements. The document was signed by Contracting Officer Sara Hinds on 8 May 2026.

View the file

Other files

File Type Posted
WWYK170123 B201 Roof Repair RFIs.pdf PDF
01 78 00.pdf PDF
01 50 00.pdf PDF
00 80 05.pdf PDF
2020 TAFB Facility Standard.pdf PDF
01 78 23.pdf PDF
2026 TAFB Mechanical Standard.pdf PDF
00 71 00.pdf PDF
01 33 00.pdf PDF
01 32 16.00 20.pdf PDF
00 72 00.pdf PDF
00 70 00.pdf PDF
Tinker General Requirements Specifications_Nov 2022_Change Log.pdf PDF
2026 TAFB FIRE PROTECTION STANDARD.pdf PDF
2026 TAFB Electrical Standard - Signed.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
Core Samples.pdf PDF
01 42 00.pdf PDF
00 80 00.pdf PDF
01 45 00.00 10.pdf PDF
01 33 16.00 10.pdf PDF
WWYK170123 Site Visit Sign in.pdf PDF
Wage Determination.pdf PDF
Solicitation - FA813726R0035.pdf PDF
Att12_170123-Drawings_2026.pdf PDF
Att10_170123 MACB Roofing SOW.pdf PDF
Att11_170123_Submittal Register_ROOF_v0.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NUMBER & TITLE: WWYK170123_REPAIR ROOF, LOG FCLTY DEP OPS B201

FACILITY/USER DAMAGES Impact / Day Daily Consideration of Delivery Extension -$

ENGINEERING TITLE Hrs RATE TOTAL Engineering Manager 0.5 57.69$ 28.85$ Project Manager 1 36.06$ 36.06$ Engineering Tech, Inspector 1 28.52$ 28.52$ Project Engineers 0.5 38.46$ 19.23$ Clerical 0.5 19.41$ 9.71$

SUBTOTAL 122.36$

GOVERNMENT TITLE Hrs RATE TOTAL

FAS (GS-12/5) 0.5 39.19$ 19.60$

Legal (GS-13/5) 1 46.60$ 46.60$ Contracting (GS-12/5) 1 39.19$ 39.19$

SUBTOTAL 105.39$

TOTAL AMOUNT OF LIQUIDATED DAMAGES PER DAY - PHASE 1 227.75$

Contracting Officer (Signature)

Contracting Officer (Print)

Date: 8 May 2026

LIQUIDATED DAMAGES

In accordance with FAR 36.206 and DFARS 236.206, liquidated damages (LDs) will be assessed for each calendar day of delay required to complete work on the subject contract/delivery order. As a minimum, LDs in the amount of $227.75 for each day thereafter will be changed based upon the following:

a. The contractor has complete control of the pace of work.

b. The contract provides for LDs for delay of work for each calendar day of the contract.

c. Considering the requirement, the rate of assessment is reasonable.

Sara Hinds