00 80 00.pdf

PDF 8 KB Posted

Attached to
WWYK170123, Repair Roof, Log Facility Dep Ops B201
Solicitation number
FA8137-26-R-0035
Issued by

About this file

This document is a Special Provisions section (Section 00 80 00) of the Tinker Air Force Base General Requirements specification for contractors working on the installation.

The specification establishes mandatory requirements for contractor operations at Tinker AFB, with emphasis on airfield safety and construction site management. Contractors must protect excavated areas from rainwater damage by providing and maintaining sufficient pumping equipment onsite. All haul routes must be directed by the Contracting Officer, and contractor activities on the airfield require pre-coordination with the Contracting Officer and Chief of Airfield Management (CAM) in compliance with TAFBI 13-204. Construction equipment is limited to 12 feet in height, and no equipment or personnel may access aircraft movement areas or approach within 200 feet of runways without Tinker Control Tower authorization. For projects exceeding seven days, all contractor personnel operating in movement areas or on aircraft-parking ramps must complete flight line driver training and maintain portable radios for Ground Control communication. Shorter projects may receive expedited authorization with flight line orientation briefing instead. Contractors must coordinate with the Contracting Officer for required airfield authorization passes. All runways, taxiways, and aprons must remain open unless otherwise specified. Traffic control in automobile movement areas must comply with the Department of Transportation's Manual on Uniform Traffic Control Devices, with barricades, warning lights, signs, and flagmen provided at contractor expense. Road closures are restricted to one lane on two-lane roads and must maintain two open lanes on four-lane roads at all times, with three lanes during rush hours. Waste materials become contractor property and must be removed from base at contractor expense. A winter recess period between December 1 and March 1 may be negotiated as a no-cost modification adjusting the delivery order completion date accordingly.

View the file

Other files

File Type Posted
WWYK170123 B201 Roof Repair RFIs.pdf PDF
Tinker General Requirements Specifications_Nov 2022_Change Log.pdf PDF
00 71 00.pdf PDF
01 78 00.pdf PDF
01 50 00.pdf PDF
00 72 00.pdf PDF
00 70 00.pdf PDF
01 78 23.pdf PDF
01 32 16.00 20.pdf PDF
Core Samples.pdf PDF
2026 TAFB Electrical Standard - Signed.pdf PDF
2026 TAFB FIRE PROTECTION STANDARD.pdf PDF
01 33 16.00 10.pdf PDF
01 42 00.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
01 45 00.00 10.pdf PDF
2020 TAFB Facility Standard.pdf PDF
2026 TAFB Mechanical Standard.pdf PDF
01 33 00.pdf PDF
00 80 05.pdf PDF
WWYK170123 Site Visit Sign in.pdf PDF
Wage Determination.pdf PDF
Solicitation - FA813726R0035.pdf PDF
Att9_170123_Liquidated Damages Signed.pdf PDF
Att12_170123-Drawings_2026.pdf PDF
Att10_170123 MACB Roofing SOW.pdf PDF
Att11_170123_Submittal Register_ROOF_v0.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB Tinker General Requirements

SECTION 00 80 00

SPECIAL PROVISIONS FOR WORKING ON TINKER AFB

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only. The most current edition of the listed publications at the time of contract/delivery order award shall be used.

TINKER AIR FORCE BASE (TAFB)

TAFBI 13-204 (2021) Airfield Operations

1.2 DEWATERING EXCAVATED AREA

It shall be the Contractor's responsibility to protect the construction area from damage due to rainwater. The Contractor shall provide and maintain at the job site sufficient pumps to remove rainwater from the excavated area as soon as practicable.

1.3 HAUL ROUTES

The haul routes to be used by the Contractor shall be as directed on the project drawings or by the Contracting Officer.

1.4 AIRFIELD OPERATIONS

All contractor activities on the airfield shall be pre-coordinated with the Contracting Officer in conjunction with the Chief, Airfield Management (CAM) prior to the Contractor proceeding on the airdrome. The provisions of TAFBI 13-204 and Section 00 80 05 SPECIAL PROVISIONS FOR WORKING ON OR NEAR THE AIRFIELD shall be strictly adhered to.

All runways, taxiways and aprons shall remain open during this project, unless specified otherwise by the Contracting Officer. The height of construction vehicles and equipment shall be limited to 12 feet above the surface. Absolutely no equipment or personnel will be allowed on the aircraft movement area or within 200 feet of the runways without permission from the Tinker Control Tower.

All Contractor personnel who will be operating their equipment or vehicles within the movement area or on any aircraft-parking ramp shall receive flight line driver training and have portable radios capable of communicating with Tinker Ground Control for projects over seven days.

The CAM may authorize certain contractors and other personnel to drive on the airdrome for short specified periods without completing the flight line driving training. However, Airfield Management will brief contractors and project engineers (or other supervisors responsible for the work being accomplished) and will provide flight line orientation for contractor vehicle operators prior to allowing them to drive on the airdrome.

January 2022 Page 1 Section 00 80 00

Tinker AFB Tinker General Requirements

Prior to commencing work on this project, the Contractor shall coordinate with the Contracting Officer for any airfield authorization passes that may be required.

Taxiing and towed aircraft shall have the right-of-way at all times.

Close coordination will be maintained between the Contractor's on-site foreman and the Airfield Manager.

1.5 TRAFFIC CONTROL AND BARRICADES

1.5.1 Automobile Movement Areas

Construction areas affecting automobile movement areas shall be protected by an adequate number of barricades with working flashing lights, warning devices, construction signs, flagmen and personnel. The barricades and warning devices shall be in accordance with the "Manual on Uniform Traffic Control Devices for Streets and Highways" developed by the U.S. Department of Transportation as an approved national standard. All costs associated with providing the traffic control and barricades shall be considered incidentals and shall be borne by the Contractor at no additional cost to the Government.

1.5.2 Road Closures

On two lane roads, only one lane may be blocked at a time. On four lane roads, at least two lanes shall be kept open at all times and three at rush hour.

1.6 WASTE AREA

Unless otherwise specified in these specifications, all waste materials removed shall become property of the Contractor and shall be taken off base for disposal. Disposal site location shall be the responsibility of the Contractor.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 WINTER RECESS

A winter recess, between December 1 and March 1, can be negotiated per Delivery Order between the Contracting Officer and the Contractor. It shall be a no cost modification to the contract moving the Delivery Order completion date the amount of the recess time.

-- End of Section --