DRAFT Section E - Inspection and Acceptance dated 15 Jul 15
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USAF C-12
Contractor Logistics Support
PART I - THE SCHEDULE
SECTION E
INSPECTION AND ACCEPTANCE
Page E-1
Contract: FA8106-15-R-0007
Contract: FA8106-15-R-0007
(15 Jun 15)
SECTION E
E.1 IN-PROCESS REVIEW
(a) Notwithstanding the right to inspection granted the Government under FAR 52.246-4, “Inspection of
Service”, the Government may perform an in-process review on the aircraft being serviced. The in-process review is intended to ensure conformance to contractual technical requirements. The review may be conducted at various process stages, such as, but not limited to: following initial evaluation (inspection); following completion of conditional maintenance; during rigging of flight controls; or, prior to functional flight checks.
(b) Written findings resulting from the in-process review will be submitted to the Contracting Officer and the
Program Manager’s (PM) Office. Any quality and/or process deficiencies noted will be documented and instruction for corrective action will be provided to the Contractor through the Contracting Officer.
CLAUSES INCORPORATED BY REFERENCE
52.246-4 Inspection Of Services--Fixed Price AUG 1996
52.246-16 Responsibility For Supplies APR 1984
252.246-7000 Material Inspection And Receiving Report MAR 2008
CLAUSES INCORPORATED BY FULL TEXT
52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)
(a) The Contractor shall comply with the higher-level quality standard(s) listed below.
Title Number Date Tailoring
1 ISO 9001 2008
[Contracting Officer insert the title, number, date, and tailoring (if any) of the higher-level quality standards.]
(b) The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in—
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require—
(i) Control of such things as design, work operations, in-process control, testing, and inspection; or
(ii) Attention to such factors as organization, planning, work instruction, documentation control, and advanced metrology.