FA8101-15-R-0007.pdf
PDF 2 MB Posted
- Attached to
- Tinker AFB CE Services-Operations Mgmt Federal contract opportunity
- Solicitation number
- FA8101-15-R-0007
About this file
FA8101-15-R-0007
View the file
Other files for this federal contract opportunity
Show all 41
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until 03:00 PM local t ime 07 Aug 2015
X
A X B
C D
EX
X G F 416 - 427
428 - 431 X H 432
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
1 432
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
FA8101 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 4 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 347
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
349 - 367 X K REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 368 - 370 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 371 - 378 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIO NS AND INSTRUCTIO NS
PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS
379 - 414
PART II - CO NTRACT CLAUSES
AFSC/PZIOA
KIMBERLY DELONG/405-739-3744
7858 5TH ST STE 1
TINKER AFB OK 73145-9125 405-739-3744
405-739-7957FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.
F3Y0AA3003A006
5. DATE ISSUED
08 Jul 2015
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
FA8101-15-R-0007
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lump Sum
Transition-in
FFP
Transition-In
PWS 1.6 to 1.6.2.4
FOB: Destination
NET AMT
1001 12 Months
OPTION Work Request & Management
FFP
Work Request & Management of Service Calls (DSW)
PWS 1.1.1 to 1.1.2.2.2.3
Option I
1 July 2016 - 30 June 2017
PURCHASE REQUEST NUMBER: F3Y0AA3003A006
1002 12 Months
OPTION Work Request Review Board
FFP
Work Request Review Board Management
PWS 1.1.2.3 to 1.1.2.3.1.2
Option I
1003 12 Months
OPTION Work Order Allocation Program Management
FFP
Work Order Allocation Program Management
PWS 1.1.2.3.2 to 1.1.2.3.3
Option I
1004 12 Months
OPTION Preventive Maintenance Program Manageme
FFP
Preventive Maintenance Program Management
PWS 1.1.3 to 1.1.3.7
1005 12 Months
OPTION Operations Overhead Management
FFP
Operations Overhead Management
PWS 1.1.4 to 1.1.7.3.1
1006 12 Months
OPTION Emergency Corrective & Scheduled Sustain
FFP
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25) COLS 1 - Priority 1 & 3A thru 3C (100%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price:_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 2 - Priority 1, 3A and 3B (100%); 3C (50%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price::_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 3 - Priority 1, 3A and 3B (100%); 3C (25%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price::_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 4 - Priority 1, 3A and 3B (100%); 3C (10%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price::_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 5 - Priority 1, 3A (100%); 3B (50%); 3C (10%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price:_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 6 - Priority 1, 3A (100%); 3B (25%); 3C (10%)
Unit Price:_____________ Qty: 12 Extended Price::_______________
*COLS funding levels will be determined at the beginning of each contract period, as identified in the written notice required IAW FAR 52.217-9, Option to Extend the Term of the Contract.
1007 12 Months
OPTION Preventive Maint Base Wide (PM) SRM
FFP
PM for Facilities/Infrastructure Base Wide SRM (less DMAG, Navy, DLA, & work covered in CLINS 13-25) COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
PM for Facilities/Infrastructure Base Wide SRM (less DMAG, Navy, DLA, & work covered in CLINS 13-25)
COLS 2 - TMDI (50-99) & ORM (>4)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price:_______________
PM for Facilities/Infrastructure Base Wide SRM (less DMAG, Navy, DLA, & work covered in CLINS 13-25)
COLS 3 - TMDI (60-99) & ORM (>4.15)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price:_______________
PM for Facilities/Infrastructure Base Wide SRM (less DMAG, Navy, DLA, & work covered in CLINS 13-25)
COLS 4 - TMDI (80-99) & ORM (>0)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1 the Term of the Contract.
1008 12 Months
OPTION Preventive Maint DMAG (PM)
FFP
PM for Facilities/Infrastructure DMAG (less Base Wide, Navy, DLA, & work covered in CLINS 13-25)
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
PM for Facilities/Infrastructure DMAG (less Base Wide, Navy, DLA, & work covered in CLINS 13-25)
COLS 2 - ORM (>4.0)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price:_______________
PM for Facilities/Infrastructure DMAG (less Base Wide, Navy, DLA, & work covered in CLINS 13-25)
COLS 3 - ORM (>4.5)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price:_______________
PM for Facilities/Infrastructure DMAG (less Base Wide, Navy, DLA, & work
COLS 4 - ORM (>4.7)
the Term of the Contract.
1009 12 Months
OPTION Preventive Maint NAVY (PM)
FFP
PM for Facilities/Infrastructure U.S. Navy (less Base Wide, DMAG, DLA, & work covered in CLINS 13-25)
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
PM for Facilities/Infrastructure U.S. Navy (less Base Wide, DMAG, DLA, & work covered in CLINS 13-25)
COLS 2 - ORM (>4)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price:_______________
PM for Facilities/Infrastructure U.S. Navy (less Base Wide, DMAG, DLA, & work covered in CLINS 13-25)
COLS 3 - ORM (>4.15)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
PM for Facilities/Infrastructure U.S. Navy (less Base Wide, DMAG, DLA, & work covered in CLINS 13-25)
COLS 4 - ORM (>4.25)
the Term of the Contract.
1010 12 Months
OPTION Preventive Maint DLA (PM)
FFP
PM for Facilities/Infrastructure DLA (less Base Wide, DMAG, Navy, & work covered in CLINS 13-25)
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
PM for Facilities/Infrastructure DLA (less Base Wide, DMAG, Navy, & work covered in CLINS 13-25)
COLS 2 - ORM (>4.0)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Extended Price:_______________
PM for Facilities/Infrastructure DLA (less Base Wide, DMAG, Navy, & work covered in CLINS 13-25)
COLS 3 - ORM (>4.15)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
PM for Facilities/Infrastructure DLA (less Base Wide, DMAG, Navy, COLS 4 - ORM (>4.7) the Term of the Contract.
1011 12 Months
OPTION Work Order Allocation Project (WOAP) Exe
FFP
Work Order Allocation Project (WOAP) Execution
(Base Wide)
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 1 - 50,000 man-hours (mh)
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Extended Price:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 2 - 45,000 mh
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Extended Price:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 3 - 40,000 mh
PWS 1.1.2.3 to 1.1.2.3.3
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 4 - 35,000 mh
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Extended Price:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 5 - 30,000 mh
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Extended Price:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 6 - 25,000 mh
1012 12 Months
OPTION Repair & Maintenance for Pavements and F
FFP
Repair & Maintenance for Pavements and Fence
(Base Wide: PM & DSW less WOAPs)
Repair & Maintenance Pavements and Fence
COLS 1 - 100%
PWS 1.2.2 to 1.2.2.2.5
Unit Price:_____________ Qty: 12 Extended Price:_______________
Repair & Maintenance Pavements and Fence COLS 2 - DSWs only
PWS 1.2.2 to 1.2.2.2.5 the Term of the Contract.
1013 12 Months
OPTION O&M for Exterior Water Distro & Sanitary
FFP
O&M for Exterior Water Distribution & Sanitary Sewer Systems
(Base Wide: Operation, PM & DSW less WOAPs)
Exterior Water Distribution & Sanitary Sewer Systems
PWS 1.2.2.3 to 1.2.2.3.13
1014 12 Months
OPTION O&M for Exterior Natural Gas Distro
FFP
O&M for Exterior Natural Gas Distribution Systems
(Base Wide: Operation, PM & DSW less WOAPs)
Exterior Natural Gas Distribution Systems
PWS 1.2.2.6
1015 12 Months
OPTION O&M for Flood Gates and Exterior Storm
FFP
O&M for Flood Gates and Exterior Storm Water Distribution Systems
(Base Wide: Operation, PM & DSW less WOAPs)
Flood Gates & Exterior Storm Water Distribution Systems
PWS 1.2.2.5 to 1.2.2.5.3
1016 12 Months
OPTION O&M for Generators (Power Production)
FFP
O&M for Generators (Power Production) (Base Wide: Operation, PM & DSW less WOAPs)
Generators (Power Production)
PWS 1.2.2.9 to 1.2.2.9.3.3
1017 12 Months
OPTION O&M for Meter and Metering Mgt
FFP
O&M for Meter and Metering Management
(Base Wide: Operation, PM & DSW less WOAPs)
Metering and Metering Management
COLS 1 - 100%
PWS 1.2.2.8 through 1.2.2.8.3
Unit Price:_____________ Qty: 12 Extended Price:_______________
Metering and Metering Management
COLS 2 - Manual Meter Read & DSW
PWS 1.2.2.8 through 1.2.2.8.3 the Term of the Contract.
1018 12 Months
OPTION O&M for Pest Management
FFP
O&M for Pest Management
(Base Wide: Operation, PM & DSW less WOAPs)
Option I
1 July 2016 - 30 June 2017
Pest Management
COLS 1 - 100% DSW & PM
PWS 1.2.2.12 to 1.2.2.12.13
Unit Price:_____________ Qty: 12 Extended Price:_______________
Pest Management
COLS 2 - 75% DSW & PM
PWS 1.2.2.12 to 1.2.2.12.13
Unit Price:_____________ Qty: 12 Extended Price:_______________
Pest Management
COLS 3 - 50% DSW & PM
PWS 1.2.2.12 to 1.2.2.12.13
Unit Price:_____________ Qty: 12 Extended Price:_______________
Pest Management
COLS 4 - DSW Only
PWS 1.2.2.12 to 1.2.2.12.13 the Term of the Contract.
1019 5 Months
OPTION ECP Snow/Ice Removal
FFP
Entry Control Points (ECPs)
Snow & Ice Removal
Option I
1 November 2016 - 31 March 2017
ECPs Snow & Ice Removal
COLS 1 - 100% (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Extended Price:_______________
ECPs
COLS 2 - Red, Yellow, & Green (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Extended Price:_______________
ECPs
COLS 3 - Red & Yellow (see MAP)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Extended Price:_______________
ECPs
COLS 4 - Red ( see MAP)
PWS 1.2.2.2 to 1.2.2.2.6 the Term of the Contract.
1020 5 Months
OPTION Pavements Base Wide (Streets) Snow/Ice
FFP
Pavements - Base Wide (Streets) Snow & Ice Removal
Option I
1 November 2016 - 31 March 2017
COLS 1 - 100% (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Extended Price:_______________
Pavements - Base Wide (Streets) Snow & Ice Removal
COLS 2 - Red, Yellow & Green (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Extended Price:_______________
Pavements - Base Wide (Streets) Snow & Ice Removal
COLS 3 - Red & Yellow (see Map
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Extended Price:_______________
Pavements - Base Wide (Streets) Snow & Ice Removal
COLS 4 - Red (see Map) the Term of the Contract.
1021 5 Months
OPTION Pavements Base Wide (Airfield, less DMAG
FFP
Pavements - Base Wide (Airfield, less DMAG))
Snow & Ice Removal
PWS 1.2.2.2 to 1.2.2.2.6
1 November 2016 - 31 March 2017
1022 5 Months
OPTION Pavements - DMAG (Airfield - less Base
FFP
Pavements - DMAG (Airfield - less Base Wide)
Snow & Ice Removal
Labor/Equipment
PWS 1.2.2.2 to 1.2.2.2.6
1 November 2016 - 31 March 2017
1023 12 Months
OPTION Pavements - Base Wide (Streets)
FFP
Pavements - Base Wide (Streets)
Sweeping
Option I
1 July 2016 - 30 June 2017
COLS 1 - 100%
PWS 1.2.2.2.4 to 1.2.2.2.5
Unit Price:_____________ Qty: 12 Extended Price:_______________
Pavements - Base Wide (Streets)
COLS 2 - Red & Yellow (see Map)
PWS 1.2.2.2.4 to 1.2.2.2.5
Unit Price:_____________ Qty: 12 Extended Price:_______________
Pavements (Streets)
COLS 3 - Red (see Map)
PWS 1.2.2.2.4 to 1.2.2.2.5
1024 12 Months
OPTION Pavements - Base Wide Sweeping
FFP
Pavements - Base Wide (Airfield less DMAG)
PWS 1.2.2.2.4 to 1.2.2.2.5
Option I
1025 12 Months
OPTION Pavements - DMAG Sweeping
FFP
Pavements - DMAG (Airfield less Base Wide)
Sweeping
PWS 1.2.2.2.4 to 1.2.2.2.5
Option I
1026 12 Months
OPTION Predictability Based Maintenance Program
FFP
Predictability Based Maintenance Program (PdM)
(DMAG) PdM Team
PWS 1.2.4 to 1.2.4.3.1.6
Option I
1027 12 Months
OPTION Building Automation System Program (BAS)
FFP
Building Automation System Program (BAS)
PWS 1.2.5
Option I
1028 12 Months
OPTION Retro-Commissioning (RcX) Program
FFP
Retro-Commissioning (RcX) Program
PWS 1.2.5.1 to 1.2.5.1.6
Option I
1029 12 Months
OPTION Appliance Maintenance(UH)
FFP
Unaccompanied Housing (UH)
Appliance Maintenance
PWS 1.2.9.1
Option I
1030 12 Months
OPTION Furnishings Management (UH)
FFP
Unaccompanied Housing (UH)
Furnishings Management
PWS 1.2.9.2
Option I
1031 12 Months
OPTION Change of Occupancy Maintenance (UH)
FFP
Unaccompanied Housing (UH)
Change of Occupancy Maintenance
PWS 1.2.9.3
1032 12 Months
OPTION B3001 - Boiler Plant
FFP
B3001 - Boiler Plant and Steam Distribution System
(Operations, DSWs & PM)
PWS 1.2.3.1 to 1.2.3.1.1 & 1.2.2 to 1.2.3.2.11
Option I
1033 12 Months
OPTION B3001 & B-9301 - Chillers
FFP
B3001 & B-9301 - Chillers and Chilled Water Distribution System
(Operations, DSWs & PM)
PWS 1.2.3.1 to 1.2.3.1.1 & 1.2.3.3
Option I
1034 12 Months
OPTION B3001 & B9301 - Compressors
FFP
B3001 & B9301 - Compressors and Compressed Air Loop Distribution System(Operations, DSWs & PM)
PWS 1.2.3.1 to 1.2.3.1.1 & 1.2.3.4 to 1.2.3.4.1
Option I
1035 12 Months
OPTION B9301 - Boiler Plant and Steam
FFP
B9301 - Boiler Plant and Steam Distribution System
(Operations, DSWs & PM)
PWS 1.2.3.1 to 1.2.3.1.1 & 1.2.2 to 1.2.3.2.11
Option I
1036 12 Months
OPTION Industrial Wastewater Treatment Plant (I
FFP
Industrial Wastewater Treatment Plant (IWTP) - Plant and Collection System
(Operations, DSWs & PM)
PWS 1.2.2.4 to 1.2.2.5.3 & 1.2.3.5 to 1.2.3.5.8
Option I
1037 12 Months
OPTION Facility Managers Program
FFP
Facility Managers Program
PWS 1.2.7 to 1.2.7.2
Option I
1038 12 Months
OPTION Barcoding Program
FFP
Barcoding Program
PWS 1.2.8
Option I
1039 12 Months
OPTION Denial Barrier Maintenance
FFP
Denial Barrier Maintenance
Maintenance/Work
(Base Wide)
PWS 1.2.2.1.8
Option I
1040 12 Months
OPTION Self-Help Program
FFP
Self-Help Program
PWS 1.5.20
Option I
1041 12 Months
OPTION CE Virtual LAN
FFP
CE Virtual LAN (VLAN)
PWS 1.2.12
Option I
1 July 2016 - 30 June 2017
1042 12 Months
OPTION Maintenance Engineering Support
FFP
Maintenance Engineering Support.
PWS 1.3 to 1.3.4.5
1043 12 Months
OPTION Civil Engineer Material Acquisition Syst
FFP
Civil Engineer Material Acquisition System (CEMAS)
PWS 1.4.1 to 1.4.2.4.2
Option I
1044 12 Months
OPTION CAP Management - FO
FFP
CAP Management - FO
PWS 1.4.2 to 1.4.2.4.2
Option I
1 July 2016 - 30 June 2017
Price for CAP Management shall be evenly proposed between CAP Management - FO and CAP - Management SRM (total price divided by 2).
All costs associated with the purchasing and managing of contractor acquired parts (CAP) shall be priced as a FFP monthly amount in this CLIN. Additional costs for CAP will not be considered and are not allowable under this contract (e.g. material handling rate).
1045 12 Months
OPTION CAP Management - SRM
FFP
CAP Management - SRM
PWS 1.4.2 to 1.4.2.4.2
CAP will not be considered and are not allowable under this contract (e.g. material
1046 Lot
OPTION CAP FO
COST
CAP FO (material cost ONLY)
PWS 1.4.2 to 1.4.2.4.2
Option I
1 July 2016 - 30 June 2017
***DO NOT BID***
ESTIMATED COST
1047 Lot
OPTION CAP SRM
COST
CAP SRM (material cost)
PWS 1.4.2 to 1.4.2.4.2
Option I
1 July 2016 - 30 June 2017
***DO NOT BID***
1048 12 Months
OPTION Required General Services – FO
FFP
Required General Services – FO
PWS 1.5 to 1.5.19
1049 12 Months
OPTION Required General Services - SRM
FFP
Required General Services - SRM
PWS 1.5 to 1.5.19
1050 12 Months
OPTION Required General Services - DMAG
FFP
Required General Services - DMAG
PWS 1.5 to 1.5.19
OPTION Performance during National Crisis
FFP
Performance of Services during National Crisis. PWS 1.2.11 to 1.2.11.2.
Option I
1 July 2016 - 30 June 2017
Unit Price:_________ Qty: 14 U/I: Days Extended Price:___________
This CLIN may be unilaterally awarded at any time during the active period of performance if required per contract clause DFARS 252.237-7023 Continuation of Essential Contractor Services
1052 12 Months
OPTION Quality Performance Indicator
FFP
Quality Performance Indicator (QPI)
Option I
1 July 2016 - 30 June 2017
IAW H-1 Performance Incentive/Quality Performance Indicators, 8% of all FFP CLIN will be allocated to this CLIN prior to award or exercise of options, thereby also decreasing the pricing on all other CLIN by 8%. The contractor may earn a percentage of the performance incentive based on the percentage of QPI earned during the period.
1053 Lump Sum
OPTION Deliverables
FFP
Deliverables--- NOT SEPARATELY PRICED (NSP)
Option I
1 July 2016 - 30 June 2017
See PWS Appendix 4.3 for numbering, description and delivery date for required deliverables.
See Exhibit A
2001 12 Months
OPTION Work Request & Management
FFP
Work Request & Management of Service Calls (DSW)
PWS 1.1.1 to 1.1.2.2.2.3
Option II
1 July 2017 - 30 June 2018
2002 12 Months
OPTION Work Request Review Board
FFP
Work Request Review Board Management
PWS 1.1.2.3 to 1.1.2.3.1.2
Option II
2003 12 Months
OPTION Work Order Allocation Program Management
FFP
Work Order Allocation Program Management
PWS 1.1.2.3.2 to 1.1.2.3.3
Option II
2004 12 Months
OPTION Preventive Maintenance Program Manageme
FFP
Preventive Maintenance Program Management
PWS 1.1.3 to 1.1.3.7
Option II
2005 12 Months
OPTION Operations Overhead Management
FFP
Operations Overhead Management
PWS 1.1.4 to 1.1.7.3.1
2006 12 Months
OPTION Emergency Corrective & Scheduled Sustain
FFP
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
Option II
1 July 2017 - 30 June 2018
COLS 1 - Priority 1 & 3A thru 3C (100%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 2 - Priority 1, 3A and 3B (100%); 3C (50%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 3 - Priority 1, 3A and 3B (100%); 3C (25%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 5 - Priority 1, 3A (100%); 3B (50%); 3C (10%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 6 - Priority 1, 3A (100%); 3B (25%); 3C (10%)
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
2007 12 Months
OPTION Preventive Maint Base Wide (PM) SRM
FFP
PM for Facilities/Infrastructure Base Wide SRM (less DMAG, Navy, DLA, & work covered in CLINS 13-25)
Option II
1 July 2017 - 30 June 2018
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure Base Wide SRM (less DMAG, Navy, DLA, & work covered in CLINS 13-25)
COLS 2 - TMDI (50-99) & ORM (>4)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure Base Wide SRM (less DMAG, Navy, DLA, & work covered in CLINS 13-25)
COLS 3 - TMDI (60-99) & ORM (>4.15)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
2008 12 Months
OPTION Preventive Maint DMAG (PM)
FFP
PM for Facilities/Infrastructure DMAG (less Base Wide, Navy, DLA, & work covered in CLINS 13-25)
Option II
1 July 2017 - 30 June 2018
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure DMAG (less Base Wide, Navy, DLA, & work covered in CLINS 13-25)
COLS 2 - ORM (>4.0)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure DMAG (less Base Wide, Navy, DLA, & work covered in CLINS 13-25)
COLS 3 - ORM (>4.5)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
2009 12 Months
OPTION Preventive Maint NAVY (PM)
FFP
PM for Facilities/Infrastructure U.S. Navy (less Base Wide, DMAG, DLA, & work covered in CLINS 13-25)
Option II
1 July 2017 - 30 June 2018
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure U.S. Navy (less Base Wide, DMAG, DLA, & work covered in CLINS 13-25)
COLS 2 - ORM (>4)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure U.S. Navy (less Base Wide, DMAG, DLA, & work covered in CLINS 13-25)
COLS 3 - ORM (>4.15)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
COLS 4 - ORM (>4.25)
2010 12 Months
OPTION Preventive Maint DLA (PM)
FFP
PM for Facilities/Infrastructure DLA (less Base Wide, DMAG, Navy, & work covered in CLINS 13-25)
Option II
1 July 2017 - 30 June 2018
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure DLA (less Base Wide, DMAG, Navy, & work covered in CLINS 13-25)
COLS 2 - ORM (>4.0)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure DLA (less Base Wide, DMAG, Navy, & work covered in CLINS 13-25)
COLS 3 - ORM (>4.15)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
2011 12 Months
OPTION Work Order Allocation Project (WOAP) Exe
FFP
Work Order Allocation Project (WOAP) Execution
(Base Wide)
Option II
1 July 2017 - 30 June 2018
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 1 - 50,000 man-hours (mh)
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 2 - 45,000 mh
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 4 - 35,000 mh
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 5 - 30,000 mh
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 6 - 25,000 mh
2012 12 Months
OPTION Repair & Maintenance for Pavements and F
FFP
Repair & Maintenance for Pavements and Fence
(Base Wide: PM & DSW less WOAPs)
Option II
1 July 2017 - 30 June 2018
Repair & Maintenance Pavements and Fence
COLS 1 - 100%
PWS 1.2.2 to 1.2.2.2.5
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Repair & Maintenance Pavements and Fence COLS 2 - DSWs only
2013 12 Months
OPTION O&M for Exterior Water Distro & Sanitary
FFP
O&M for Exterior Water Distribution & Sanitary Sewer Systems
(Base Wide: Operation, PM & DSW less WOAPs)
Option II
1 July 2017 - 30 June 2018
Exterior Water Distribution & Sanitary Sewer Systems
PWS 1.2.2.3 to 1.2.2.3.13
2014 12 Months
OPTION O&M for Exterior Natural Gas Distro
FFP
O&M for Exterior Natural Gas Distribution Systems
(Base Wide: Operation, PM & DSW less WOAPs)
Option II
1 July 2017 - 30 June 2018
2015 12 Months
OPTION O&M for Flood Gates and Exterior Storm
FFP
O&M for Flood Gates and Exterior Storm Water Distribution Systems
(Base Wide: Operation, PM & DSW less WOAPs)
Option II
1 July 2017 - 30 June 2018
Flood Gates & Exterior Storm Water Distribution Systems
PWS 1.2.2.5 to 1.2.2.5.3
2016 12 Months
OPTION O&M for Generators (Power Production)
FFP
O&M for Generators (Power Production) (Base Wide: Operation, PM & DSW less WOAPs)
Option II
1 July 2017 - 30 June 2018
Generators (Power Production)
PWS 1.2.2.9 to 1.2.2.9.3.3
2017 12 Months
OPTION O&M for Meter and Metering Mgt
FFP
O&M for Meter and Metering Management
(Base Wide: Operation, PM & DSW less WOAPs)
Option II
1 July 2017 - 30 June 2018
Metering and Metering Management
COLS 1 - 100%
PWS 1.2.2.8 through 1.2.2.8.3
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Metering and Metering Management
COLS 2 - Manual Meter Read & DSW
2018 12 Months
OPTION O&M for Pest Management
FFP
O&M for Pest Management
(Base Wide: Operation, PM & DSW less WOAPs)
Option II
1 July 2017 - 30 June 2018
Pest Management
COLS 1 - 100% DSW & PM
PWS 1.2.2.12 to 1.2.2.12.13
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pest Management
COLS 2 - 75% DSW & PM
PWS 1.2.2.12 to 1.2.2.12.13
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pest Management
COLS 3 - 50% DSW & PM
PWS 1.2.2.12 to 1.2.2.12.13
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
2019 5 Months
OPTION ECP Snow/Ice Removal
FFP
Entry Control Points (ECPs)
Snow & Ice Removal
Option II
1 November 2017 - 31 March 2018
ECPs Snow & Ice Removal
COLS 1 - 100% (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
ECPs
COLS 2 - Red, Yellow, & Green (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
ECPs
COLS 3 - Red & Yellow (see MAP)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
2020 5 Months
OPTION Pavements Base Wide (Streets) Snow/Ice
FFP
Pavements - Base Wide (Streets) Snow & Ice Removal
Option II
1 November 2017 - 31 March 2018
COLS 1 - 100% (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pavements - Base Wide (Streets) Snow & Ice Removal
COLS 2 - Red, Yellow & Green (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pavements - Base Wide (Streets) Snow & Ice Removal
COLS 3 - Red & Yellow (see Map
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pavements - Base Wide (Streets) Snow & Ice Removal
COLS 4 - Red (see Map)
2021 5 Months
OPTION Pavements Base Wide (Airfield, less DMAG
FFP
Pavements - Base Wide (Airfield, less DMAG))
Snow & Ice Removal
PWS 1.2.2.2 to 1.2.2.2.6
Option II
1 November 2017 - 31 March 2018
2022 5 Months
OPTION Pavements - DMAG (Airfield - less Base
FFP
Pavements - DMAG (Airfield - less Base Wide)
Snow & Ice Removal
Labor/Equipment
PWS 1.2.2.2 to 1.2.2.2.6
Option II
1 November 2017 - 31 March 2018
2023 12 Months
OPTION Pavements - Base Wide (Streets)
FFP
Pavements - Base Wide (Streets)
Sweeping
Option II
1 July 2017 - 30 June 2018
COLS 1 - 100%
PWS 1.2.2.2.4 to 1.2.2.2.5
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pavements - Base Wide (Streets)
COLS 2 - Red & Yellow (see Map)
PWS 1.2.2.2.4 to 1.2.2.2.5
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pavements (Streets)
COLS 3 - Red (see Map)
2024 12 Months
OPTION Pavements - Base Wide Sweeping
FFP
Pavements - Base Wide (Airfield less DMAG)
PWS 1.2.2.2.4 to 1.2.2.2.5
Option II
2025 12 Months
OPTION Pavements - DMAG Sweeping
FFP
Pavements - DMAG (Airfield less Base Wide)
Sweeping
PWS 1.2.2.2.4 to 1.2.2.2.5
Option II
2026 12 Months
OPTION Predictability Based Maintenance Program
FFP
Predictability Based Maintenance Program (PdM)
(DMAG) PdM Team
PWS 1.2.4 to 1.2.4.3.1.6
Option II
2027 12 Months
OPTION Building Automation System Program (BAS)
FFP
Building Automation System Program (BAS)
PWS 1.2.5
Option II
2028 12 Months
OPTION Retro-Commissioning (RcX) Program
FFP
Retro-Commissioning (RcX) Program
PWS 1.2.5.1 to 1.2.5.1.6
Option II
2029 12 Months
OPTION Appliance Maintenance(UH)
FFP
Unaccompanied Housing (UH)
Appliance Maintenance
PWS 1.2.9.1
Option II
2030 12 Months
OPTION Furnishings Management (UH)
FFP
Unaccompanied Housing (UH)
Furnishings Management
PWS 1.2.9.2
Option II
2031 12 Months
OPTION Change of Occupancy Maintenance (UH)
FFP
Unaccompanied Housing (UH)
Change of Occupancy Maintenance
PWS 1.2.9.3
2032 12 Months
OPTION B3001 - Boiler Plant
FFP
B3001 - Boiler Plant and Steam Distribution System
(Operations, DSWs & PM)
PWS 1.2.3.1 to 1.2.3.1.1 & 1.2.2 to 1.2.3.2.11
Option II
2033 12 Months
OPTION B3001 & B-9301 - Chillers
FFP
B3001 & B-9301 - Chillers and Chilled Water Distribution System
(Operations, DSWs & PM)
PWS 1.2.3.1 to 1.2.3.1.1 & 1.2.3.3
Option II
2034 12 Months
OPTION B3001 & B9301 - Compressors
FFP
B3001 & B9301 - Compressors and Compressed Air Loop Distribution System(Operations, DSWs & PM)
PWS 1.2.3.1 to 1.2.3.1.1 & 1.2.3.4 to 1.2.3.4.1
Option II
2035 12 Months
OPTION B9301 - Boiler Plant and Steam
FFP
B9301 - Boiler Plant and Steam Distribution System
(Operations, DSWs & PM)
PWS 1.2.3.1 to 1.2.3.1.1 & 1.2.2 to 1.2.3.2.11
Option II
2036 12 Months
OPTION Industrial Wastewater Treatment Plant (I
FFP
Industrial Wastewater Treatment Plant (IWTP) - Plant and Collection System
(Operations, DSWs & PM)
PWS 1.2.2.4 to 1.2.2.5.3 & 1.2.3.5 to 1.2.3.5.8
Option II
2037 12 Months
OPTION Facility Managers Program
FFP
Facility Managers Program
PWS 1.2.7 to 1.2.7.2
Option II
2038 12 Months
OPTION Barcoding Program
FFP
Barcoding Program
PWS 1.2.8
Option II
2039 12 Months
OPTION Denial Barrier Maintenance
FFP
Denial Barrier Maintenance
Maintenance/Work
(Base Wide)
PWS 1.2.2.1.8
Option II
2040 12 Months
OPTION Self-Help Program
FFP
Self-Help Program
PWS 1.5.20
Option II
2041 12 Months
OPTION CE Virtual LAN
FFP
CE Virtual LAN (VLAN)
PWS 1.2.12
Option II
2042 12 Months
OPTION Maintenance Engineering Support
FFP
Maintenance Engineering Support.
PWS 1.3 to 1.3.4.5
2043 12 Months
OPTION Civil Engineer Material Acquisition Syst
FFP
Civil Engineer Material Acquisition System (CEMAS)
PWS 1.4.1 to 1.4.2.4.2
Option II
2044 12 Months
OPTION CAP Management - FO
FFP
CAP Management - FO
PWS 1.4.2 to 1.4.2.4.2
CAP will not be considered and are not allowable under this contract (e.g. material
2045 12 Months
OPTION CAP Management - SRM
FFP
CAP Management - SRM
PWS 1.4.2 to 1.4.2.4.2
CAP will not be considered and are not allowable under this contract (e.g. material
2046 Lot
OPTION CAP FO
COST
CAP FO (material cost ONLY)
PWS 1.4.2 to 1.4.2.4.2
2047 Lot
OPTION CAP SRM
COST
CAP SRM (material cost)
PWS 1.4.2 to 1.4.2.4.2
2048 12 Months
OPTION Required General Services – FO
FFP
Required General Services – FO
PWS 1.5 to 1.5.19
2049 12 Months
OPTION Required General Services - SRM
FFP
Required General Services - SRM
PWS 1.5 to 1.5.19
2050 12 Months
OPTION Required General Services - DMAG
FFP
Required General Services - DMAG
PWS 1.5 to 1.5.19
OPTION Performance during National Crisis
FFP
Performance of Services during National Crisis. PWS 1.2.11 to 1.2.11.2.
Option II
1 July 2017 - 30 June 2018
Unit Price:_________ Qty:14 U/I: Days Extended Price:___________
This CLIN may be unilaterally awarded at any time during the active period of performance if required per contract clause DFARS 252.237-7023 Continuation of Essential Contractor Services
2052 12 Months
OPTION Quality Performance Indicator
FFP
Quality Performance Indicator (QPI)
IAW H-1 Performance Incentive/Quality Performance Indicators, 8% of all FFP CLIN will be allocated to this CLIN prior to award or exercise of options, thereby also decreasing the pricing on all other CLIN by 8%. The contractor may earn a percentage of the performance incentive based on the percentage of QPI earned during the period.
2053 Lump Sum
OPTION Deliverables
FFP
Deliverables--- NOT SEPARATELY PRICED (NSP)
Option II
1 July 2017 - 30 June 2018
See PWS Appendix 4.3 for numbering, description and delivery date for required deliverables.
3001 12 Months
OPTION Work Request & Management
FFP
Work Request & Management of Service Calls (DSW)
PWS 1.1.1 to 1.1.2.2.2.3
Option III
1 July 2018 - 30 June 2019
3002 12 Months
OPTION Work Request Review Board
FFP
Work Request Review Board Management
PWS 1.1.2.3 to 1.1.2.3.1.2
Option III
3003 12 Months
OPTION Work Order Allocation Program Management
FFP
Work Order Allocation Program Management
PWS 1.1.2.3.2 to 1.1.2.3.3
Option III
3004 12 Months
OPTION Preventive Maintenance Program Manageme
FFP
Preventive Maintenance Program Management
PWS 1.1.3 to 1.1.3.7
3005 12 Months
OPTION Operations Overhead Management
FFP
Operations Overhead Management
PWS 1.1.4 to 1.1.7.3.1
3006 12 Months
OPTION Emergency Corrective & Scheduled Sustain
FFP
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
Option III
1 July 2018 - 30 June 2019
COLS 1 - Priority 1 & 3A thru 3C (100%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 2 - Priority 1, 3A and 3B (100%); 3C (50%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 3 - Priority 1, 3A and 3B (100%); 3C (25%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 5 - Priority 1, 3A (100%); 3B (50%); 3C (10%)
PWS 1.1.2.2.1 & 1.1.2.2.2 to 1.1.2.2.2.3 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Emergency Corrective & Scheduled Sustainment Work Base Wide (less work covered in CLINS 13-25)
COLS 6 - Priority 1, 3A (100%); 3B (25%); 3C (10%)
3007 12 Months
OPTION Preventive Maint Base Wide (PM) SRM
FFP
PM for Facilities/Infrastructure Base Wide SRM (less DMAG, Navy, DLA, & work covered in CLINS 13-25)
Option III
1 July 2018 - 30 June 2019
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure Base Wide SRM (less DMAG, Navy, DLA, & work covered in CLINS 13-25)
COLS 2 - TMDI (50-99) & ORM (>4)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure Base Wide SRM (less DMAG, Navy, DLA, & work covered in CLINS 13-25)
COLS 3 - TMDI (60-99) & ORM (>4.15)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
3008 12 Months
OPTION Preventive Maint DMAG (PM)
FFP
PM for Facilities/Infrastructure DMAG (less Base Wide, Navy, DLA, & work covered in CLINS 13-25)
Option III
1 July 2018 - 30 June 2019
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure DMAG (less Base Wide, Navy, DLA, & work covered in CLINS 13-25)
COLS 2 - ORM (>4.0)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure DMAG (less Base Wide, Navy, DLA, & work covered in CLINS 13-25)
COLS 3 - ORM (>4.5)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
3009 12 Months
OPTION Preventive Maint NAVY (PM)
FFP
PM for Facilities/Infrastructure U.S. Navy (less Base Wide, DMAG, DLA, & work covered in CLINS 13-25)
Option III
1 July 2018 - 30 June 2019
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure U.S. Navy (less Base Wide, DMAG, DLA, & work covered in CLINS 13-25)
COLS 2 - ORM (>4)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure U.S. Navy (less Base Wide, DMAG, DLA, & work covered in CLINS 13-25)
COLS 3 - ORM (>4.15)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
COLS 4 - ORM (>4.25)
3010 12 Months
OPTION Preventive Maint DLA (PM)
FFP
PM for Facilities/Infrastructure DLA (less Base Wide, DMAG, Navy, & work covered in CLINS 13-25)
Option III
1 July 2018 - 30 June 2019
COLS 1 - 100% of PM Workload
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure DLA (less Base Wide, DMAG, Navy, & work covered in CLINS 13-25)
COLS 2 - ORM (>4.0)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
PM for Facilities/Infrastructure DLA (less Base Wide, DMAG, Navy, & work covered in CLINS 13-25)
COLS 3 - ORM (>4.15)
PWS 1.2 to 1.2.12.13 & 1.2.6 to 1.2.6.1
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
3011 12 Months
OPTION Work Order Allocation Project (WOAP) Exe
FFP
Work Order Allocation Project (WOAP) Execution
(Base Wide)
Option III
1 July 2018 - 30 June 2019
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 1 - 50,000 man-hours (mh)
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 2 - 45,000 mh
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 4 - 35,000 mh
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 5 - 30,000 mh
PWS 1.1.2.3 to 1.1.2.3.3
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Work Order Allocation Project (WOAP) Execution
(Base Wide)
COLS 6 - 25,000 mh
3012 12 Months
OPTION Repair & Maintenance for Pavements and F
FFP
Repair & Maintenance for Pavements and Fence
(Base Wide: PM & DSW less WOAPs)
Option III
1 July 2018 - 30 June 2019
Repair & Maintenance Pavements and Fence
COLS 1 - 100%
PWS 1.2.2 to 1.2.2.2.5
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Repair & Maintenance Pavements and Fence COLS 2 - DSWs only
3013 12 Months
OPTION O&M for Exterior Water Distro & Sanitary
FFP
O&M for Exterior Water Distribution & Sanitary Sewer Systems
(Base Wide: Operation, PM & DSW less WOAPs)
Option III
1 July 2018 - 30 June 2019
Exterior Water Distribution & Sanitary Sewer Systems
PWS 1.2.2.3 to 1.2.2.3.13
3014 12 Months
OPTION O&M for Exterior Natural Gas Distro
FFP
O&M for Exterior Natural Gas Distribution Systems
(Base Wide: Operation, PM & DSW less WOAPs)
Option III
1 July 2018 - 30 June 2019
3015 12 Months
OPTION O&M for Flood Gates and Exterior Storm
FFP
O&M for Flood Gates and Exterior Storm Water Distribution Systems
(Base Wide: Operation, PM & DSW less WOAPs)
Option III
1 July 2018 - 30 June 2019
Flood Gates & Exterior Storm Water Distribution Systems
PWS 1.2.2.5 to 1.2.2.5.3
3016 12 Months
OPTION O&M for Generators (Power Production)
FFP
O&M for Generators (Power Production) (Base Wide: Operation, PM & DSW less WOAPs)
Option III
1 July 2018 - 30 June 2019
Generators (Power Production)
PWS 1.2.2.9 to 1.2.2.9.3.3
3017 12 Months
OPTION O&M for Meter and Metering Mgt
FFP
O&M for Meter and Metering Management
(Base Wide: Operation, PM & DSW less WOAPs)
Option III
1 July 2018 - 30 June 2019
Metering and Metering Management
COLS 1 - 100%
PWS 1.2.2.8 through 1.2.2.8.3
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Metering and Metering Management
COLS 2 - Manual Meter Read & DSW
3018 12 Months
OPTION O&M for Pest Management
FFP
O&M for Pest Management
(Base Wide: Operation, PM & DSW less WOAPs)
Option III
1 July 2018 - 30 June 2019
Pest Management
COLS 1 - 100% DSW & PM
PWS 1.2.2.12 to 1.2.2.12.13
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pest Management
COLS 2 - 75% DSW & PM
PWS 1.2.2.12 to 1.2.2.12.13
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pest Management
COLS 3 - 50% DSW & PM
PWS 1.2.2.12 to 1.2.2.12.13
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
3019 5 Months
OPTION ECP Snow/Ice Removal
FFP
Entry Control Points (ECPs)
Snow & Ice Removal
Option III
1 November 2018 - 31 March 2019
ECPs Snow & Ice Removal
COLS 1 - 100% (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
ECPs
COLS 2 - Red, Yellow, & Green (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
ECPs
COLS 3 - Red & Yellow (see MAP)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
3020 5 Months
OPTION Pavements Base Wide (Streets) Snow/Ice
FFP
Pavements - Base Wide (Streets) Snow & Ice Removal
Option III
1 November 2018 - 31 March 2019
COLS 1 - 100% (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pavements - Base Wide (Streets) Snow & Ice Removal
COLS 2 - Red, Yellow & Green (see Map)
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pavements - Base Wide (Streets) Snow & Ice Removal
COLS 3 - Red & Yellow (see Map
PWS 1.2.2.2 to 1.2.2.2.6
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pavements - Base Wide (Streets) Snow & Ice Removal
COLS 4 - Red (see Map)
3021 5 Months
OPTION Pavements Base Wide (Airfield, less DMAG
FFP
Pavements - Base Wide (Airfield, less DMAG))
Snow & Ice Removal
PWS 1.2.2.2 to 1.2.2.2.6
Option III
1 November 2018 - 31 March 2019
3022 5 Months
OPTION Pavements - DMAG (Airfield - less Base
FFP
Pavements - DMAG (Airfield - less Base Wide)
Snow & Ice Removal
Labor/Equipment
PWS 1.2.2.2 to 1.2.2.2.6
Option III
1 November 2018 - 31 March 2019
3023 12 Months
OPTION Pavements - Base Wide (Streets)
FFP
Pavements - Base Wide (Streets)
Sweeping
Option III
1 July 2018 - 30 June 2019
COLS 1 - 100%
PWS 1.2.2.2.4 to 1.2.2.2.5
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pavements - Base Wide (Streets)
COLS 2 - Red & Yellow (see Map)
PWS 1.2.2.2.4 to 1.2.2.2.5
Unit Price:_____________ Qty: 12 Line Item Cost:_______________
Pavements (Streets)
COLS 3 - Red (see Map)
3024 12 Months
OPTION Pavements - Base Wide Sweeping
FFP
Pavements - Base Wide (Airfield less DMAG)
PWS 1.2.2.2.4 to 1.2.2.2.5
Option III
3025 12 Months
OPTION Pavements - DMAG Sweeping
FFP
Pavements - DMAG (Airfield less Base Wide)
Sweeping
Option III
1 July 2018 - 30 June 2019
3026 12 Months
OPTION Predictability Based Maintenance Program
FFP
Predictability Based Maintenance Program (PdM)
(DMAG) PdM Team
Option III
1 July 2018 - 30 June 2019
PWS 1.2.4 to 1.2.4.3.1.6
3027 12 Months
OPTION Building Automation System Program (BAS)
FFP
Building Automation System Program (BAS)
Option III
1 July 2018 - 30 June 2019
PWS 1.2.5
3028 12 Months
OPTION Retro-Commissioning (RcX) Program
FFP
Retro-Commissioning (RcX) Program
Option III
1 July 2018 - 30 June 2019
PWS 1.2.5.1 to 1.2.5.1.6
3029 12 Months
OPTION Appliance Maintenance(UH)
FFP
Unaccompanied Housing (UH)
Appliance Maintenance
Option III
1 July 2018 - 30 June 2019
PWS 1.2.9.1
3030 12 Months
OPTION Furnishings Management (UH)
FFP
Unaccompanied Housing (UH)
Furnishings Management
Option III
1 July 2018 - 30 June 2019
PWS 1.2.9.2
3031 12 Months
OPTION Change of Occupancy Maintenance (UH)
FFP
Unaccompanied Housing (UH)
Change of Occupancy Maintenance
Option III
PWS 1.2.9.3
3032 12 Months
OPTION B3001 - Boiler Plant
FFP
B3001 - Boiler Plant and Steam Distribution System
(Operations, DSWs & PM)
Option III
1 July 2018 - 30 June 2019
PWS 1.2.3.1 to 1.2.3.1.1 & 1.2.2 to 1.2.3.2.11
3033 12 Months
OPTION B3001 & B-9301 - Chillers
FFP
B3001 & B-9301 - Chillers and Chilled Water Distribution System
(Operations, DSWs & PM)
Option III
1 July 2018 - 30 June 2019
PWS 1.2.3.1 to 1.2.3.1.1 & 1.2.3.3
ITEM
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .