Section C - Descriptions and Specifications
Contents Section C - Descriptions and Specifications
ROOFING STATEMENT OF WORK (SOW)
1.0 Project Purpose
2.0 Scope
3.0 Specific Base Construction Projects – Awarded as Task Orders (TO (s))
4.0 Specific Base Maintenance Projects – Awarded as Task Orders (TO(s))
5.0 Contractor Requirements – Management Capacity/Capability
6.0 Contractor Requirements – Self Performance Capability
7.0 Contractor Requirements – Subcontract Management
8.0 Applicable Documents
9.0 Government Furnished Information, Equipment, and Property (GFI, GFE, GFP)
10.0 Provisions on Contracting Officer’s Authority
11.0 Worksite Activities and Coordination
ROOFING STATEMENT OF WORK (SOW)
1.0 Project Purpose
The purpose of this program is to acquire commercial roof replacement, preventative maintenance, corrective repair, and inspection/testing services for United States Air Force (USAF) Active, Guard and Reserve installations, U.S. Army (USA) and U.S. Navy (USN) installations within the Contiguous United States (CONUS) including Alaska (only areas reachable by ground transportation). The program will acquire such services for existing USAF facilities on a recurring basis. The program will acquire such services for USA and USN on an as-requested basis.
Requirements execution will be divided into six geographic regions: West, Midwest, Northeast, Southwest, Southeast and Alaska (see Roofing Region Map, Attachment X, Section X of the Request For Proposal (RFP)).
2.0 Scope
2.1 The scope of this effort is to perform roof maintenance, repair and replacement (thermal and moisture protection) for low-slope (weatherproof membrane types of roof systems installed on slopes at or less than 3:12 or 14 degrees), steep slope (water-shedding types of roof coverings installed on slopes greater than 3:12 or 14 degrees), and metal (hydrostatic and hydrokinetic systems) roofing projects. Roof assemblies include all items of work included in the elemental classification of the American Society for Testing and Materials (ASTM) UNIFORMAT II B30. The thermal insulation, vapor retarder, membrane, drainage components, flashings, and details (roof edges, scuppers, parapets, curbs, drains, coping systems, shingles and roofing tiles, etc.) are included in the scope of this effort. The features of work that are part of the structural roof assembly (framing (steel, wood, etc.), structural diaphragm, decking, purlins, parapets, roof joists, beams, associated hardware and fixtures, etc.) regardless of material are in scope of this project.
2.2 The ASTM UNIFORMAT II B30 features of work incidental (in terms of dollar amount related to the direct roofing cost (labor, equipment, materials and subcontractor mark-up)) construction activities such as asbestos abatement, HVAC disconnect/movement, plaza decks, lightning protection, and walking pads, etc. which arise as a result of the roofing project are in scope of this contract. The estimated value of this incidental work should not exceed 30% of the direct roofing costs.
2.3 All roof types, systems, membranes, and services listed in UFC 3-110-03 are included.
Roof types not listed must be approved by AFCEC Roofing SME.
2.4 The Government may elect to replace a roof with a different in-scope roof type (for example: Asphalt Built-Up Roof to Metal (Hydrostatic) Membrane, etc.).
2.5 The project delivery methods shall include design-bid-build and/or design-build.
2.6 Contractor shall perform maintenance on all roof types listed in UFC 3-110-03.
3.0 Specific Base Construction Projects – Awarded as Task Orders (TO (s))
3.1 Specific roofing construction projects will be awarded at the task order level against the basic IDIQ contract on an “as needed” basis. Civil Engineering (CE) and contracting personnel will prepare design-build, design-bid-build, specifications, and related requirements documents for specific roofing projects and will solicit only those Contractors awarded IDIQ contracts in the geographic region in which the base is located.
3.2 Each requiring activity, when furnishing their individual requirements for TO competition, may include base-specific terms and conditions as well as master specifications.
3.3 TOs may be set-aside either for competition among 8(a) awardees only or may be open to all small business awardees in the region.
3.4 The Contractor shall notify the Government in writing of any conflicts between the proposed roofing system, the design documents, and the scheduling of work/workers (trades) to assure a watertight roofing installation. All of the conflict decisions shall be obtained in writing from the Government prior to the start of roofing work.
4.0 Specific Base Maintenance Projects – Awarded as Task Orders (TO(s))
4.1 Roofing Preventive Maintenance (PM) Service Calls: Roofing PM service calls are routine tasks requested by and scheduled with the Government. The scope of the PM tasks will be called out in the base TO. Typical tasks are identified on the attached Preventive Maintenance Task List (PMTL). The Contractor shall have the ability to update the BUILDER™
Sustainment Management System as required and supplied by the Government resulting from the service.
4.2 Roofing Corrective Maintenance (CM) Service Calls: During performance of PM service calls unexpected additional CM roofing work may be identified. The Contractor shall notify the Contracting Officer immediately of the required additional work. The notification will include a written statement to identify CM recommended repairs and recommend corrective action along with a firm fixed price quote indicating the projected date of completion to make the repair to include labor, material, travel, and incidental costs to accomplish the work. The Contractor shall not continue with any of the CM discovered unless the CO authorizes it in writing. Typically, the CM authorization shall be in the form of a contract modification. All CM work requirements must be determined by the CO to be fair and reasonable and within the scope of the TO and IDIQ.
5.0 Contractor Requirements – Management Capacity/Capability
5.1 The Contractor shall be required to furnish all materials, equipment, and personnel necessary to manage, and accomplish the orders issued under the contract. Throughout the life of this contract, whenever there are active TO’s (i.e., work is actively underway on-site), the Contractor shall have a project manager available during normal business hours to meet with the Contracting Officer or his/her representative at a location specified in the TO within one hour after notification. The Contractor shall also accomplish quality control management for all active projects.
5.2 Whenever there are awarded active TO’s, Contractor personnel with the following management/technical support capabilities must be available to properly manage/superintend all TO work under construction:
5.2.1 Contractor's Project Superintendent (CPS) - Provides on-site supervision of active TO's. The CPS shall visit each active project site daily, submit detailed progress reports (AF Form 3065) as required by each TO, schedule and coordinate subcontractors and material suppliers, and attend all weekly status meetings, site visit, and pre-final/final inspections. Superintendents should have a minimum of 5 years previous experience in commercial roofing.
5.2.2 Contractor's Quality Control Manager (QCM) - Provide quality control management for all active TO's and execute the Contractor’s QC plan. The QCM shall visit each active project site daily to ensure full compliance with all safety requirements, and verify that the materials and workmanship are in accordance with approved construction drawings, shop drawings, material submittals and technical specifications.
The QCM shall prepare and coordinate material submittal sheets and shop drawing submittals, prepare QC reports, schedule and coordinate testing procedures and attend all weekly status meetings, site visits, and pre-final/final inspections. The QCM shall be someone other than the CPS except in TOs which are small (<$150K) in which case the CPS may, also, serve as the QCM. QCM shall have a minimum of five years’ experience in Quality Control in commercial roofing.
5.2.3 The Contractor shall employ a CPS and/or QCM and/or job foreman for each active TO who is a certified installer of a qualified manufacturer for all roofing systems being installed. The CPS and/or QCM and/or job foreman is required on site at all times (100% of the time) when roofing work is being accomplished.
5.3 The Contractor shall be capable of performing on all roof types within the entire region.
Performance of roofing work must be accomplished by a firm (prime/sub/teaming partner) which holds a current applicator agreement for the product(s) they are installing through contract TO performance. The Contractor shall comply with the Period of Performance (PoP) established in the TOs. After notification, the Contractor must be capable of responding to emergency situations as stated in the TO and complete the emergency work by the end of the PoP. The Contractor must be capable of participating in TO level site-visits at all locations in the geographic region. Site visit procedures will be established at the task order level.
5.4 The Contractor must provide accurate progress payment estimates, accommodate a potential number of concurrent “active” projects at different bases or states, provide flexibility of staff and subcontractor pool to handle surges in work volume, meet the Government schedule, mobilizing equipment necessary to complete work in a timely and cost effective manner, provide on-time completion process submittals in a timely manner, and present a professional demeanor.
5.5 The Contractor shall participate in an annual Program Management Review (PMR) meeting with the USAF Roofing Re-Compete Program Team (Program Manager, Contracting Officer…etc.) and other stakeholders (Air Force Civil Engineering Center, Base Civil Engineers….etc.). This meeting may be accomplished virtually, via teleconference or by other electronic means. The purpose of the PMR will be to discuss Contractor performance, quality, competitiveness, and/or any other topic the Government or Contractor deem necessary to reduce costs, increase quality, or resolve issues.
5.6 The Contractor must provide to the USAF Contracting Officer an annual PMR report, in the format provided by the Government. The report must be submitted to the Government no later than 90 calendar days prior to the end of the ordering period and contain the following information:
5.6.1 Bonding Capacity: In whole dollars, provide the aggregate bonding capacity and unreleased bonding at the end of the reporting period. Also describe any increase in bonding capacity received during the reporting period.
5.6.2 Self-Performance: For all USAF projects conducted during the reporting period, list the TO number, the total cost of the materials, the total subcontractor cost and the total price TO amount.
5.6.3 Warranty Work: For the last IDIQ PoP, identify by TO project number t h e date contacted by the Government for the warranty call and the nature of the warranty call.
Describe the corrective action taken or planned if the issue was in- warranty, or explanatory comments if the issue was out of warranty.
5.6.4 Experience Modification Rate (EMR) for Workers Compensation: Provide a copy of the most current EMR statement for workers compensation from the Contractors insurance provider.
5.6.5 The Contractor must be capable of collecting, maintaining, and reporting this data to the Government for discussion at the annual PMR meetings as specified.
5.7 Throughout the period of performance The Contractor may be asked to provide to the Contracting Officer, upon 10 business days’ notice, with various additional data related to performance, quality, schedule, or other related contract elements.
5.8 The project roofing work warranty will be specified in the TO. The Contractor must be able to provide the warranty types as defined in appendix D of UFC 3-110-03. Typical included requirements are: has “no dollar limit”, covers full system water-tightness, is from the single source manufacturer, and has minimum duration of 20 years. Unless stated otherwise in the TO, all replacement roofs require a either a Five Year General Contractor Bonded Water-tightness Warranty or a combination of a standard maintenance bond (one or two years) and a manufacturer NDL to fulfill the five year obligation. The TO may waive the Bonding requirement, but if not specified, either the Bonded 5 year water-tightness warranty or a combination of a standard maintenance bond (one or two years) and a manufacturer NDL to fulfill the five year obligation is required.
5.9 The Offeror shall provide a single customer service hotline phone number that can be accessed during normal business hours, by all bases in the geographic region of the proposal, to be responsive to Government requests. The Offeror must describe how its customer service function is managed to ensure responsiveness. The Offeror must also log all calls received from AF installations and must identify the Offeror’s process for resolving AF installation concerns, and following up on unresolved requests.
6.0 Contractor Requirements – Self Performance Capability
6.1 The Contractor must be capable of self-performing in accordance with 52.219-14 -- Limitations on Subcontracting (DEVIATION 2019-O0003).
6.2 The Contractor must maintain a safety plan that, at a minimum, demonstrates the employment of standard safety processes, Occupational Safety and Health Administration (OSHA) compliance, training, and inspection for all employees and subcontractors. The Contractor shall maintain an EMR for workers compensation less than 1.0 throughout the IDIQ PoP. The Contractor may be required to produce the Safety Plan for review at any time by the Government.
6.3 The Contractor must provide and maintain manufacturer applicator agreements demonstrating the capability of providing the warranties described in the Unified Facilities Criteria (UFC).
6.4 The Contractor must have 5 years of corporate experience performing, managing and subcontracting roofing projects. The Contractor shall have recent experience (within 5 years) installing the roofing systems in the ASHRAE climate zone of the region in which they will perform work.
6.5 The Contractor shall have a roof system design capability in accordance with the design guidance in UFC 3-110-03 Roofing. The Contractor will have the capability to do roof systems design as demonstrated by including in their organization (may be a subcontractor) a Registered Roofing Consultant, Registered Professional Engineer or Registered Architect that derives his or her principal income from roofing design. A qualified architect or engineer shall design and oversee the preparation of contract documents. The Whole Building Design Guide (WBDG) Unified Facilities Guide Specifications (UFGS) and UFCs shall serve as the basis for all project specifications that the Contractor shall develop on design-build TO.
7.0 Contractor Requirements – Subcontract Management
7.1 The Contractor shall have established subcontractor relationships, have a subcontractor pre-qualification process, and maintain documentation of pre-qualification for the subcontractors used.
7.1.1 This pre-qualification process must consider the prospective subcontractors’ safety plans, quality control plans, financial capability, insurability, past performance, and applicator agreements, and must identify the minimum requirements the subcontractor must meet in each area to be determined acceptable.
7.1.2 The Contractor must maintain established criteria for determining the acceptability of the subcontractor areas described in 8.1.1.
7.1.3 This documentation may be requested by the Government and the Contractor must provide within 10 business days.
7.3 The Contractor is responsible for managing subcontractor performance. The Contractor shall be directly responsible to the Government for all work allocated to its subcontractors.
The Contractor must maintain metrics it will track on subcontractor performance, must monitor those metrics, and hold subcontractors accountable.
8.0 Applicable Documents
8.1 The Contractor shall comply with all applicable federal, state, and local statutes;
Department of Defense Instructions, Air Force Instructions, manuals, handbooks, regulations, guidance, and policy letters, including but not limited to:
- Unified Facility Criteria (UFC) 1-200-01, DoD Building Code which brings uniformity to the military use of non-government model building codes such as the International Building Code (IBC) and the International Existing Building Code (IEBC);
- UFC 1-200-02, High Performance and Sustainable Building Requirements;
- UFC 3-110-03, Roofing;
- UFC 3-110-04, Roofing Maintenance and Repair;
- AFI 32-1051, Roof Systems Management or current AF policy
- AFI 91-203, Air Force Consolidated Occupational Safety Instruction
- National Fire Protection Association (NFPA);
- American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE);
- Metal Building Manufacturers Association (MBMA);
- American Society of Civil Engineers (ASCE);
- ASTM International (formerly American Society for Testing and Materials);
- National Electrical Code (NEC);
- National Roofing Contractors Association (NRCA) Roofing Manuals to include all changes and amendments in effect on the date of issuance of each TO.
8.2 The Contractor must comply with guidance in each state issued by the State Historical Preservation Office (SHPO).
8.3 It is the Contractor’s responsibility to comply with all applicable requirements which will be called out in the TOs. Base-specific requirements will be identified in each TO. The Contractor shall obtain and maintain access to all these documents during the term of this contract.
9.0 Government Furnished Information, Equipment, and Property (GFI, GFE, GFP)
10.1 GFI, GFE, and GFP, if provided, will be specified in each TO.
10.0 Provisions on Contracting Officer’s Authority
10.1 No person other than the Air Force Installation Contracting Agency (AFICA) Contracting Officer shall have authority to modify the terms and conditions of the IDIQ contract. For specific base level roofing projects awarded on TOs against the IDIQ, the ordering contracting officer specified on that TO is the only person with the authority to modify the terms of that TO. The Contractor shall not take direction from anyone other than the Contracting Officer. In the event the Contractor effects any such changes at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof. The Contracting Officer is the only person who can obligate the government; other input taken and acted upon that change the contract (other than health/life safety concerns) in any way is done at the sole financial and legal responsibility of the Contractor.
11.0 Worksite Activities and Coordination
11.1 The Contractor shall coordinate worksite activities with all applicable Government personnel (applicable personnel will be called out in the TO) to ensure the protection of human health and the environment; the prevention of damage to property, utilities, materials, supplies, and equipment; and the avoidance of Government work interruptions.
The Contractor shall provide physical security to w o r k areas with security equipment and personnel, as required by the TO. The Contractor must comply with OSHA safety and health regulations and local safety office requirements. The Contractor is required to provide the ordering Contracting Officer copies of any OSHA report(s) submitted during the duration of the TO. For areas not covered by OSHA, the Contractor shall comply with regulations regarding safety and health and the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM385-1-1 (https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_38 5-1-1.pdf)
11.2 The Contractor shall perform work as specified at project locations. The Contractor shall be responsible for all personnel, security, supplies, equipment, and infrastructure (including, but not limited to, potable water, utility systems, sanitation, housing, dining, transportation, and medical care) when there are no facilities and services indicated as available to the Contractor in the TO.
Roofing Reapir, Replacement, and Maintenance Request for Proposal- Attachment 6
Bases by Region DRAFT FA8003-19-R-A006
Base Region* Altus AFB Southwest Arnold AFB Southeast Avon Park AFR, Southeast Barksdale AFB Southeast Beale AFB, West Buckley AFB West Cannon AFB Southwest Cape Canaveral AFS, Southeast Cape Cod AFS Northeast Cavalier AFS Midwest Cheyenne Mountain AFS West Columbus AFB Southeast Creech AFB Southwest Davis-Monthan AFB Southwest Dover AFB Northeast Dyess AFB Southwest Edwards AFB West Eglin AFB Southeast Eielson AFB Alaska Ellsworth AFB West F.E. Warren AFB West Fairchild AFB West Goodfellow AFB Southwest Grand Forks AFB Midwest Hanscom AFB Northeast Hill AFB & Test Ranges West Holloman AFB Southwest Hurlburt AFB Southeast Joint Base Andrews Northeast Joint Base Charleston Southeast Joint Base Elmendorf-Richardson Alaska Joint Base Langley Northeast Joint Base McGuire Northeast Joint Base San Antonio (includes Lackland AFB, Randolph AFB and Fort Sam Houston) Southwest
Base Region* Keesler AFB Southeast Kirtland AFB Southwest Laughlin AFB Southwest Little Rock AFB, Southeast Los Angeles AFB West Luke AFB & Ranges Southwest MacDill AFB, Southeast Malmstrom AFB West Maxwell-Gunter AFB, Southeast McConnell AFB Midwest Minot AFB Midwest Moody AFB Southeast Mountain Home AFB West Nellis AFB West New Boston AFS Northeast Offutt AFB Midwest Patrick AFB, Southeast Peterson AFB West Robins AFB Southeast Rome Labs Northeast Schriever AFB West Scott AFB Midwest Seymour-Johnson AFB Southeast Shaw AFB & Ranges Southeast Sheppard AFB Southwest Tinker AFB Southwest Tonopah Test Range West Travis AFB West Tyndall AFB, Southeast USAFA West Vance AFB Southwest Vandenberg AFB West Whiteman AFB Midwest Wright-Patterson AFB Northeast
* Please see Ordering Guide Attach. 16 for the Contractors by Region
PA
JB Andrews
NJ
NH
OH
Nellis Creech
NV Hill / Utah TTR / Little Mtn STC
UT
Buckley
Peterson Schriever
USAFA
CO
OR
Fairchild
WA
Mountain Home
ID
Malmstrom
MT
F.E. Warren
WY
Los Angeles Edwards
Vandenberg
Travis
Beale
CA
Sheppard
Dyess
Goodfellow
Laughlin JB San AntonioTX
Davis-Monthan
Luke
AZ
Holloman
Kirtland
Cannon
NM
Vance
Tinker Altus
OK
Whiteman
MO
IA
MN
Minot Grand Forks
ND
Ellsworth SD
OffuttNE
McConnell
KS
WI
Scott
IL
Hurlburt
Eglin
Tyndall
MacDill
Patrick
FL
Barksdale
LA
Columbus
Keesler
MS
Maxwell /
Gunter Annex
AL
Moody
Robins GA JB Charleston
Shaw
SC
Seymour Johnson
NC
Arnold
TN
Little Rock
AR
Hanscom
Dover
JB Langley
VA
WV
KY
ME
IN
NY
VT
MA
RI
CT
DE
MD
MI
Region 1: West Region 3: Northeast
Region 5: SoutheastRegion 4: Southwest
Region 2: Midwest
Note: Not drawn to scale. Installation locations are approximate.
Excludes Joint Bases where AF not lead Service
Wright Patterson
Rome Labs
Cheyenne Mtn AFS
Cape Canaveral
AFS
AFR = Air Force Range AFS = Air Force Station
JB = Joint Base
STC = Satellite Testing Center TR = Test Range
TTR = Test & Training Range
Tonopah TR
Avon Park
AFR
New Boston
AFS
Cape Cod
AFS
Cavalier AFS
JB McGuire
Roofing Reapir, Replacement, and Maintenance Request for Proposal- Attachment 6
Bases by Region DRAFT FA8003-19-R-A006
Region 6: Alaska
JB Elmendorf-Richardson
Eielson
PMTL B2035 225 1950 02 Details
Equipment Type: B2035 225 1950 02
Component: Roof, Low Sloped - Medium (5k sf - 10k sf, min 2 person task)
Equipment Component As Of: 10/01/2015
1 Check with Facility Manager for deficiencies. Ensure All Safety Equipment Is In Place Before Starting Job x
2 Inspect surface for wear and UV protection deterioration x
3 Inspect membrane for holes or damage x
4 Parapet Membrane Flashing: Inspect for damage/holes/deterioration; Inspect for open seams/end laps; Inspect for open upper edge; Validate membrane is properly secured and counter flashing is inplace x
5 Parapet Counter Flashing: Inspect metal counterflashing; Inspect fasteners; Inspect end/lap joints in metal x
6 Wall Membrane Flashing: Inspect membrane flashing for holes or damage; Inspect the flashing seams; Inspect the metal counter flashings for damage/holes and proper attachment x
7 Wall Counter Flashing: Inspect membrane flashing for holes or damage; Inspect the flashing seams; Inspect the metal counter flashings for damage/holes and proper attachment x
8 Surface, Membrane, Flashing: Apply mastic and fabric. Tighten/install fasteners. Apply caulk/sealant to open metal joints to prevent moisture intrusion x
9 Pipe vent: Inspect for corrosion; Inspect pipe flashing for damage/leaks; Inspect for proper air flow x
10 Roof Hatch: Inspect base flashing; Inspect metal counter flashing; Inspect fasteners; Inspect end/lap joints in metal; Inspect the gasket in hatch hood for damage/holes; Inspect hatch door mechanism to ensure proper closeage/locking x
11 Mech Equip/Exhaust Fan/Vent: Inspect exhaust vent equipment for corrosion, missing/damaged panels, ensure equipment is running properly. Ensure drain lines properly piped and supported. Ensure the equipment properly supported/flashed. Ensure metal flash x
12 Other Equip (Satelite Dish, etc): Inspect for damage; Inspect for proper support and proper membrane protection; Inspect for proper securement to support members x
13 Field Drain: Inspect flashing around drain; Inspect clamping ring for damage; Inspect bolts in clamping ring; Inspect strainer for damage; ensure drain flows freely x
14 Overflow Scupper: Inspect flashing around drain; Inspect strainer for damage; ensure drain flows freely; Inspect for proper connection to scupper box/downspout;
x
15 Drains/Scuppers: Tighten/install bolts. Clear debris. x
16 Pitch Pan: Inspect for flashing around pitch pan; Inspect pitch pan edges for damage/holes/corrosion; Inspect for integrity of filler material; Fill with pitch as necessary x
17 Coping Cap: Inspect base flashing; Inspect metal cap end/lap joints; Inspect fasteners;
Inspect for rust on metal x
18 Gutters/Downspouts: Inspect. Clear debris x
19 Fill out maintenance checklist and report defeficiencies x
Annually
Step PM Components (Task Description) Labor-hrs A
Page 1 of 1PMTL B2035 225 1950 02
4/16/2019https://cs2.eis.af.mil/sites/10758/PMTL/Module/PMTL%20Details.aspx?EID=20
| Statement of Work (SOW) |
| Section C - Descriptions and Specifications |
| ROOFING STATEMENT OF WORK (SOW) |
| 1.0 Project Purpose |
| 2.0 Scope |
| 3.0 Specific Base Construction Projects – Awarded as Task Orders (TO (s)) |
| 4.0 Specific Base Maintenance Projects – Awarded as Task Orders (TO(s)) |
| 5.0 Contractor Requirements – Management Capacity/Capability |
| 6.0 Contractor Requirements – Self Performance Capability |
| 7.0 Contractor Requirements – Subcontract Management |
| 8.0 Applicable Documents |
| 9.0 Government Furnished Information, Equipment, and Property (GFI, GFE, GFP) |
| 10.0 Provisions on Contracting Officer’s Authority |
| Roofing Region Map |
| Slide Number 1 |
| Slide Number 2 |
SOW Attachment -- Preventative Maintenance Task List (PMTL)