CODE

(Hour)

PAGE(S)

until 04:00 PM local time 18 Nov 2009

X

A X B

C D

EX

X G F 123 - 128

129 - 135 X H 136 richard.harper@usafa.af.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

1 136

(If other than Item 7) FA7000

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

FA7000 8. ADDRESS OFFER TO

9. Sealed offers in original and 5 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and not applicable conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

RICHARD HARPER 719-333-3927

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 81

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

82 - 84

85 - 90 X K REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 91 - 92 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 93 - 94 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

95 - 121

PART II - CONTRACT CLAUSES

10 CONS - FA7000

ATTN: RICHARD HARPER

8110 INDUSTRIAL DRIVE, STE 200

USAF ACADEMY CO 80840

10 CONS - FA7000

ATTN: SHAWNA BOWSHOT

8110 INDUSTRIAL DRIVE, STE 200

USAFA CO 80840719-333-3927

719-333-6608FAX:

TEL:

719-333-9103FAX:

TEL: 719-333-4060

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

29 Sep 2009

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

FA7000-09-R-0059

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0001 30,000,000 Dollars, U.S.

Labor - Firm Fixed Price (3400)

FFP

The contractor shall provide support IAW the CAStLE Aging Structures Statement of Work (SOW) (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order.

Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. The total NTE value for this contract for FFP (3400) labor CLINs including base and option periods is $30,000,000.00. At the end of this base period, the remaining balance of the $30,000,000.00 will be established as the NTE amount of subsequent option periods.

FOB: Destination

SIGNAL CODE: A

MAX

NET AMT

UNIT UNIT PRICE MAX AMOUNT

0002 17,000,000 Dollars, Labor - FFP Level of Effort (3400)

FFP-LOE

The contractor shall provide support IAW the CAStLE Aging Structures SOW (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order. Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. The total NTE value for this contract for FFP LOE (3400) labor CLINs including base and option periods is $17,000,000.00. At the end of this base period, the remaining balance of the $17,000,000.00 will be established as the NTE amount of subsequent option periods.

MAX NET AMT

CEILING PRICE

UNIT UNIT PRICE MAX AMOUNT

0003 1,750,000 Dollars, Travel - Firm Fixed Price (3400)

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. The total NTE value for this contract for travel (3400) CLINs including base and option periods is $2,000,000.00. At the end of this base period, the remaining balance of the $2,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0004 2,000,000 Dollars, Material - Firm Fixed Price (3400)

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. The total NTE value for this contract for material (3400) CLINs including base and option periods is $5,000,000.00. At the end of this base period, the remaining balance of the $5,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0005 3,000,000 Dollars, Storage - Firm Fixed Price (3400)

Government required storage in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on storage.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The storage CLIN amounts are for estimating purposes only. The total NTE value for this contract for storage (3400) CLINs including base and option periods is $3,000,000.00. At the end of this base period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0006 3,000,000 Dollars, Transportation - Firm Fixed Price (3400)

Government required transportatoin in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on transportation.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The transportation CLIN amounts are for estimating purposes only. The total NTE value for this contract for transportation (3400) CLINs including base and option periods is $3,000,000.00. At the end of this base period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0007 8,000,000 Dollars, Labor - Firm Fixed Price (3600)

The contractor shall provide support IAW the CAStLE Aging Structures Statement of Work (SOW) (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order.

Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. The total NTE value for this contract for FFP (3600) labor CLINs including base and option periods is $8,000,000.00. At the end of this base period, the remaining balance of the $8,000,000.00 will be established as the NTE amount of subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0008 18,000,000 Dollars, Labor - FFP Level of Effort (3600)

FFP-LOE

The contractor shall provide support IAW the CAStLE Aging Structures SOW (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order. Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. The total NTE value for this contract for FFP LOE (3600) labor CLINs including base and option periods is $18,000,000.00. At the end of this base period, the remaining balance of the $18,000,000.00 will be established as the NTE amount of subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0009 730,000 Dollars, Travel - Firm Fixed Price (3600)

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. The total NTE value for this contract for travel (3600) CLINs including base and option periods is $980,000.00. At the end of this base period, the remaining balance of the $980,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0010 1,500,000 Dollars, Material - Firm Fixed Price (3600)

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. The total NTE value for this contract for material (3600) CLINs including base and option periods is $3,000,000.00. At the end of this base period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0011 10,000 Dollars, Storage - Firm Fixed Price (3600)

Government required storage in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on storage.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The storage CLIN amounts are for estimating purposes only. The total NTE value for this contract for storage (3600) CLINs including base and option periods is $10,000.00. At the end of this base period, the remaining balance of the $10,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0012 10,000 Dollars, Transportation - Firm Fixed Price (3600)

Government required transportatoin in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on transportation.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The transportation CLIN amounts are for estimating purposes only. The total NTE value for this contract for transportation (3600) CLINs including base and option periods is $10,000.00. At the end of this base period, the remaining balance of the $10,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0013 250,000 Dollars, Travel - Cost Reimbursable (3400)

COST

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. The total NTE value for this contract for travel (3400) CLINs including base and option periods is $2,000,000.00. At the end of this base period, the remaining balance of the $2,000,000.00 will be established as the NTE amount of the subsequent option periods.

MAX COST

UNIT UNIT PRICE MAX AMOUNT

0014 250,000 Dollars, Travel - Cost Reimbursable (3600)

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. The total NTE value for this contract for travel (3600) CLINs including base and option periods is $980,000.00. At the end of this base period, the remaining balance of the $980,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0015 3,000,000 Dollars, Material - Cost Reimbursable (3400)

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. The total NTE value for this contract for material (3400) CLINs including base and option periods is $5,000,000.00. At the end of this base period, the remaining balance of the $5,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

0016 1,500,000 Dollars, Material - Cost Reimbursable (3600)

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2010 through 20 February 2011 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. The total NTE value for this contract for material (3600) CLINs including base and option periods is $3,000,000.00. At the end of this base period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods

UNIT UNIT PRICE MAX AMOUNT

1001 UNDEFINED

OPTION Labor - Firm Fixed Price (3400)

FFP

The contractor shall provide support IAW the CAStLE Aging Structures Statement of Work (SOW) (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order.

Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for FFP (3400) labor CLINs including base and option periods is $30,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $30,000,000.00 will be established as the NTE amount of subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1002 UNDEFINED

OPTION Labor - FFP Level of Effort (3400)

FFP-LOE

The contractor shall provide support IAW the CAStLE Aging Structures SOW (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order. Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for FFP LOE (3400) labor CLINs including base and option periods is $17,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $17,000,000.00 will be established as the NTE amount of subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1003 UNDEFINED

OPTION Travel - Firm Fixed Price (3400)

FFP

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for travel (3400) CLINs including base and option periods is $2,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $2,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1004 UNDEFINED

OPTION Material - Firm Fixed Price (3400)

FFP

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for material (3400) CLINs including base and option periods is $5,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $5,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1005 UNDEFINED

OPTION Storage - Firm Fixed Price (3400)

FFP

Government required storage in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on storage.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The storage CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for storage (3400) CLINs including base and option periods is $3,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1006 UNDEFINED

OPTION Transportation - Firm Fixed Price (3400)

FFP

Government required transportation in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on transportation.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The transportation CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for transportation (3400) CLINs including base and option periods is $3,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1007 UNDEFINED

OPTION Labor - Firm Fixed Price (3600)

FFP

The contractor shall provide support IAW the CAStLE Aging Structures Statement of Work (SOW) (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order.

Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for FFP (3600) labor CLINs including base and option periods is $8,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $8,000,000.00 will be established as the NTE amount of subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1008 UNDEFINED

OPTION Labor - FFP Level of Effort (3600)

FFP-LOE

The contractor shall provide support IAW the CAStLE Aging Structures SOW (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order. Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for FFP LOE (3600) labor CLINs including base and option periods is $18,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $18,000,000.00 will be established as the NTE amount of subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1009 UNDEFINED

OPTION Travel - Firm Fixed Price (3600)

FFP

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for travel (3600) CLINs including base and option periods is $980,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $980,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1010 UNDEFINED

OPTION Material - Firm Fixed Price (3600)

FFP

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for material (3600) CLINs including base and option periods is $3,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1011 UNDEFINED

OPTION Storage - Firm Fixed Price (3600)

FFP

Government required storage in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on storage.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The storage CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for storage (3600) CLINs including base and option periods is $10,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $10,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1012 UNDEFINED

OPTION Transportation - Firm Fixed Price (3600)

FFP

Government required transportation in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on transportation.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The transportation CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for transportation (3600) CLINs including base and option periods is $10,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $10,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1013 UNDEFINED

OPTION Travel - Cost Reimbursable (3400)

COST

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. The total NTE value for this contract for travel (3400) CLINs including base and option periods is $2,000,000.00. At the end of this base period, the remaining balance of the $2,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1014 UNDEFINED

OPTION Travel - Cost Reimbursable (3600)

COST

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. The total NTE value for this contract for travel (3600) CLINs including base and option periods is $980,000.00. At the end of this base period, the remaining balance of the $980,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1015 UNDEFINED

OPTION Material - Cost Reimbursable (3400)

COST

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. The total NTE value for this contract for material (3400) CLINs including base and option periods is $5,000,000.00. At the end of this base period, the remaining balance of the $5,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

1016 UNDEFINED

OPTION Material - Cost Reimbursable (3600)

COST

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2011 through 20 February 2012 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. The total NTE value for this contract for material (3600) CLINs including base and option periods is $3,000,000.00. At the end of this base period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods

UNIT UNIT PRICE MAX AMOUNT

2001 UNDEFINED

OPTION Labor - Firm Fixed Price (3400)

FFP

The contractor shall provide support IAW the CAStLE Aging Structures Statement of Work (SOW) (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order.

Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for FFP (3400) labor CLINs including base and option periods is $30,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $30,000,000.00 will be established as the NTE amount of subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2002 UNDEFINED

OPTION Labor - FFP Level of Effort (3400)

FFP-LOE

The contractor shall provide support IAW the CAStLE Aging Structures SOW (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order. Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for FFP LOE (3400) labor CLINs including base and option periods is $17,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $17,000,000.00 will be established as the NTE amount of subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2003 UNDEFINED

OPTION Travel - Firm Fixed Price (3400)

FFP

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for travel (3400) CLINs including base and option periods is $2,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $2,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2004 UNDEFINED

OPTION Material - Firm Fixed Price (3400)

FFP

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for material (3400) CLINs including base and option periods is $5,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $5,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2005 UNDEFINED

OPTION Storage - Firm Fixed Price (3400)

FFP

Government required storage in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on storage.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The storage CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for storage (3400) CLINs including base and option periods is $3,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2006 UNDEFINED

OPTION Transportation - Firm Fixed Price (3400)

FFP

Government required transportation in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on transportation.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The transportation CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for transportation (3400) CLINs including base and option periods is $3,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2007 UNDEFINED

OPTION Labor - Firm Fixed Price (3600)

FFP

The contractor shall provide support IAW the CAStLE Aging Structures Statement of Work (SOW) (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order.

Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for FFP (3600) labor CLINs including base and option periods is $8,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $8,000,000.00 will be established as the NTE amount of subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2008 UNDEFINED

OPTION Labor - FFP Level of Effort (3600)

FFP-LOE

The contractor shall provide support IAW the CAStLE Aging Structures SOW (Attachment 1). Individual task orders will be issued for each project and will specifically identify the applicable labor category/categories and quantity of labor hours to be ordered under a given order. Maximum labor category pricing for all labor categories is as listed in the Labor Rate Table (Attachment 2).

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The Labor CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for FFP LOE (3600) labor CLINs including base and option periods is $18,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $18,000,000.00 will be established as the NTE amount of subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2009 UNDEFINED

OPTION Travel - Firm Fixed Price (3600)

FFP

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for travel (3600) CLINs including base and option periods is $980,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $980,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2010 UNDEFINED

OPTION Material - Firm Fixed Price (3600)

FFP

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for material (3600) CLINs including base and option periods is $3,000,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $3,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2011 UNDEFINED

OPTION Storage - Firm Fixed Price (3600)

FFP

Government required storage in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on storage.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The storage CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for storage (3600) CLINs including base and option periods is $10,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $10,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2012 UNDEFINED

OPTION Transportation - Firm Fixed Price (3600)

FFP

Government required transportation in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and reimbursement will be made IAW the SOW. No burden(s) or fee will be paid on transportation.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The transportation CLIN amounts are for estimating purposes only. Not to exceed amount will be established at the time the option is exercised. The total NTE value for this contract for transportation (3600) CLINs including base and option periods is $10,000.00. Value for this CLIN will be carried over from the balance of prior year labor CLINs of this contract. At the end of this option period, the remaining balance of the $10,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2013 UNDEFINED

OPTION Travel - Cost Reimbursable (3400)

COST

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. The total NTE value for this contract for travel (3400) CLINs including base and option periods is $2,000,000.00. At the end of this base period, the remaining balance of the $2,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2014 UNDEFINED

OPTION Travel - Cost Reimbursable (3600)

COST

Government required travel in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on travel.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The travel CLIN amounts are for estimating purposes only. The total NTE value for this contract for travel (3600) CLINs including base and option periods is $980,000.00. At the end of this base period, the remaining balance of the $980,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2015 UNDEFINED

OPTION Material - Cost Reimbursable (3400)

COST

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. The total NTE value for this contract for material (3400) CLINs including base and option periods is $5,000,000.00. At the end of this base period, the remaining balance of the $5,000,000.00 will be established as the NTE amount of the subsequent option periods.

UNIT UNIT PRICE MAX AMOUNT

2016 UNDEFINED

OPTION Material - Cost Reimbursable (3600)

COST

Government required material in support of the CAStLE Aging Structures effort IAW the SOW (Attachment 1). Funding will be included, if necessary, in the task orders and payment will be made IAW the SOW. No burden(s) or fee will be paid on material.

Partial paymemts authorized and required.

Ordering Period: 21 February 2012 through 20 February 2013 Performance of individual task orders shall continue until completion of the effort.

Note: The material CLIN amounts are for estimating purposes only. The total NTE value for this contract for material (3600) CLINs…