About this file

This document contains questions and answers from a pre-proposal site visit for a solicitation to provide operations, maintenance and support services at Melrose Air Force Range. The contractor will be responsible for nine regimes of support including facility maintenance, aerial gunnery and bombing ranges, ground training ranges, Military Operations in Urban Terrain sites, electronic and technology support, scheduling, wildland fire management, paramedic services, and situational training. The contractor must maintain all government furnished equipment and vehicles used to support range operations. Range 7 is currently incomplete and the contractor will be required to complete construction according to plans in the solicitation. The pre-proposal site visit was held on February 5, 2021 with questions due to the contracting officer within five days thereafter. A record of the site visit with anonymized questions and answers will be provided to all offerors.

View the file

Other files for this federal contract opportunity

Other files attached to Melrose Air Force Range Support Contract, newest first.
File Type Posted
FA485521R0002 - Q and A V4_2 Mar 21.pdf PDF
FA485521R00020003 Solicitation Amendment - MAFR OMS.pdf PDF
Atch 7. Past Performance Questionnaire_Rev 1_2 Mar 21.docx DOCX document
Atch 3. DD1423 Exhibit A CDRLs_Rev 1_19 Feb 21.pdf PDF
Atch 4. Staffing Matrix_Rev 1_ 19 Feb 21.XLSX XLSX spreadsheet
Atch 1. MAFR OMS PWS_Rev 1_19 Feb 21.pdf PDF
Atch 1. MAFR OMS PWS_Rev 1_19 Feb 21 TRACKED CHANGES.pdf PDF
Atch 2. Management Plan_ Rev 1_19 Feb 21 TRACKED CHANGES.pdf PDF
Atch 12. DD1423 CDRL for SB Utilization_Rev 1_ 19 Feb 21.pdf PDF
Atch 19. 52.212-2 Addendum_Rev 1_19 Feb 21 TRACKED CHANGES.pdf PDF
Atch 20. CAFB MAFR Environmental Guide_29 Jun 18.pdf PDF
FA485521R00020002 Solicitation Amendment - MAFR OMS.pdf PDF
Atch 2. Management Plan_ Rev 1_19 Feb 21.pdf PDF
Atch 18. 52.212-1 Addendum_Rev 2_19 Feb 21.pdf PDF
Atch 19. 52.212-2 Addendum_Rev 1_19 Feb 21.pdf PDF
FA485521R0002 - Q and A V3_20 Feb 21.pdf PDF
Atch 18. 52.212-1 Addendum_Rev 2_19 Feb 21 TRACKED CHANGES.pdf PDF
Atch 21. CAFB Facility Manager Handbook.pdf PDF
MAFR OMS Site Visit Minutes 5 Feb 21.pdf PDF
MAFR OMS Site Visit Information Pamphlet.pdf PDF
MAFR OMS Site Visit Itinerary - FA485521R0002.pdf PDF
FA485521R0002 - Q and A V2_9 Feb 21.pdf PDF
FA485521R0002 - Q and A V1_20 Jan 21.pdf PDF
FA485521R00020001 Solicitation Amendment - MAFR OMS.pdf PDF
Atch 18. 52.212-1 Addendum_Rev 1_20 Jan 21.pdf PDF
Atch 1. MAFR OMS PWS 16 DEC 20.pdf PDF
Atch 4. Staffing Matrix.XLSX XLSX spreadsheet
Atch 7. Past Performance Questionnaire.docx DOCX document
Atch 18. 52.212-1 Addendum.pdf PDF
Atch 19. 52.212-2 Addendum.pdf PDF
Atch 2. Management Plan.pdf PDF
Atch 3. DD1423 CDRL for Management Plan.pdf PDF
Atch 5. Price Proposal Workbook.xlsx XLSX spreadsheet
Atch 10. Small Business Participation Commitment Document.docx DOCX document
Atch 11. Data item Description for SB Utilization.pdf PDF
Atch 13. GFP.pdf PDF
Atch 14. DD254.pdf PDF
Atch 8. Sub Teaming Partner Consent Letter.pdf PDF
Atch 9. Client Authorization Letter.pdf PDF
Atch 17. Incorporated Strengths or Capability Exceedances.pdf PDF
FA485521R0002 Solicitation - MAFR OMS.pdf PDF
Atch 6. Past Performance Information Sheet.docx DOCX document
Atch 15. WD 2015-5457 Rev 13, 06 Jun 20.pdf PDF
Atch 16. CBA 2018-2021.pdf PDF
Atch 12. DD1423 CDRL for SB Utilization.pdf PDF
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Melrose Air Force Range (MAFR) Operations, Maintenance and Support (OM&S)

FA485521R0002 - Site Visit Questions and Answers

5 February 2021

Question (Q) 1: Who maintains the ARFF and Firefighting equipment?

Answer (A) 1: LRS takes care of everything except the 5-ton utility truck; facility maintenance is not required for the firefighting storage building. The contractor maintains all of the Government

Furnished Equipment (GFE) Wildland Fire equipment and all PPE whether it is contractor or

Government provided.

Q2: Is Red Horse resurfaced with existing equipment?

A2: Currently, yes. If the contractor determines that the GFE is not sufficient to maintain any of the Landing Zones (LZs), it is their responsibility to provide it IAW PWS 2.7.2

Q3: Where is the TRTG located?

A3: Side of building 3161 (interconnect, part of GECCO)

Q4: What is the generator at GECCO used for?

A4: Backup power in the event standard power fails to operate telephone and radios

Q5: Is there consideration for getting a bigger/more powerful generator to replace the GENERAC?

A5: There has been talk about it for some time, but nothing has ever been approved. This is not a cause for concern for this project as they only relate to COMM and radios.

Q6: Is MAFR scheduled for new Joint Threat Emitters (JTEs)?

A6: No, they were scheduled to get them, but it isn’t going to happen as of date.

Q7: What are the TRTGs?

A7: The two Tactical Radar Threat Generators (TRTGs) are target tracker/Gun dish emulators that were seen on the walk up to GECCO on top of the mesa. They can be moved up to 75 miles away by towing vehicles that the contractor will provide.

Q8: Does the range have any Omega and Casbah targets?

A8: No.

Q9: Is Range 7 subject to the typical TC-25-8 US Army Training Circular?

A9: Yes; AR385-63 was also mentioned when the RMO answered this question

Q10: Is the large white radar dome a “77” and what does it house?

A10: No, and it is empty currently. It is the future home of the aviation radar that is maintained by a different contract. This MAFR re-acquisition will be for operations and maintenance only.

Q11: Since Range 7 is incomplete and will be the contractor’s responsibility to complete it, can more information be provided on exactly what this will entail? Can vendors get a more comprehensive breakdown of everything that will be required?

A11: The plans for Range 7 are included in the solicitation. Vendors are encouraged to thoroughly review the solicitation attachments to view the breakdown of Range 7 requirements.