Questions and Answers.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- Demolition of Facilities Phase 6 Federal contract opportunity
- Solicitation number
- FA4819-20-R-1000
About this file
This document contains questions and answers regarding a solicitation for demolition services at Tyndall Air Force Base in Florida. The solicitation seeks fixed price demolition of facilities, abandonment of utility lines, and site restoration. Contractors must remove foundations entirely, secure sites after abatement, and use Pensacola Bahia grass for restoration without hydroseeding near airfields. The response due date is June 15, 2020. The contracting office provides contacts and notes that a schedule will be required after award. Environmental and safety plans are required, and an archaeologist must be onsite during excavations.
View the file
Other files for this federal contract opportunity
Show all 37
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PPIF
| Pre Proposal Inquiry Form | Solicitation No: FA481920R1000 |
| Contracting Officer Name: Melissa Sanders | Demolition of Facilities Phase 6, Tyndall AFB Florida |
| Contract Administrator Name: SrA James Sears | Quote Due Date 15 June 2020 |
Email: 325CONS.Construction@us.af.mil
| Question No. | Reference (Sect/Para/Page) | Question | Government Response |
| 1 | General Inquiry | Item 9, dewatering – we understand there is potential for shallow groundwater at the site. During excavations of the foundations, if contaminated water is encountered, how are we to price this in the demolition bid? | The Government does not have the means to provide an exact determination of where shallow groundwater will be encountered, as such we request contractors bid as if no groundwater will be encountered. If it is, then we will adjust accordingly. |
| 2 | General Inquiry | PFOA /PFOS waste is mentioned in item 11 ERP area, do any of the structures have history of usage of these contaminants? |
The information related to areas where PFOS/PFAS may be a concern on Tyndall is available through at Site Inspection Report of Fire Fighting Foam Usage at Tyndall AFB; available at the AFCEC Administrative Record website (just google AFCEC AR)
| 3 | General Inquiry | General requirements – qualified personnel. Only mentions qualified personnel - what is the expectation of the customer – Site Superintendent, SSHO and QCM? 3 separate on site personnel? | At minimum two qualified personnel will be required. One superintendent, as well as a SSHO and QCM, which both roles can be filled by one individual. |
| 4 | General Inquiry | Is there a requirement for FOD management and FOD prevention program and Flight Line Waiver? If so what is the lead time for review/approval of this document. | A Government completed document will be provided to the contractor with guidelines they will need to abide by. |
| 5 | General Inquiry | Is there an anticipation of Fence around the buildings to be demolished, if so what type of fence? | Stormwater/silt will be required for all sites, and orange construction fence for sites adjacent to the flightline where there is risk of FOD. |
| 6 | General Inquiry | Demolition of facilities includes foundations and infrastructure – please confirm that the entire foundation is to be removed and not limited to a certain depth. What is the expectation of removal of the Deep foundations on any of these structures? | For each facility, intent is to remove the entire foundation. Reference attached appendices for dimensions, if on-site conditions differ from these appendices then differing site condtions will be evaluated accordingly |
| 7 | General Inquiry | What type of grass is required for site restoration; and is sod required? | Pensacola Bahia, sod not required but cannot hydroseed near airfield only drillseed (2.2.1.n in PWS) |
| 8 | General Inquiry | What is the lead-time for dig permits? | Usually 7-10 days, conservatively 14 |
| 9 | General Inquiry | What is the expectation of the customer to secure the building after abatement waiting for demolition? | After abatement, but before demolition, contractors are expected to secure sites from pedestrians. However, note that per the Performance Work Statement (PWS) some facilities will require coordination with CES to allow certain members access around times of active work. |
| 10 | General Inquiry | Please confirm there are no historical artifacts or ecological subsurface requirements associated with the demolition work. | All sites under this requirement were reviewed by SHPO for historical and cultural sensitivity, however due to the still uncertain nature, requirements for archaelogical monitoring are incorporated into the Performance Work Statement (PWS). Contractor's will follow all guidelines for monitoring as outlined in the PWS. |
| 11 | General Inquiry | Please provide direction for disposal of e-waste | If e-waste is encountered, contractor should notify the Government and determination will be made on whether the contractor is to dispose of it or transport it to DRMO |
| 12 | General Inquiry | Utility considerations item 8, since the water, electric, and natural gas infrastructure is privatized, is the demolition contractor requirement to hire the utility owner(s), if yes what are the lead times? | Yes, contractors are required to pay a lump sum charge to the privatized utility companies to complete the work. The privatized utiliy companies are aware of these buildings needing to come down and the actual process of them cut, cap, and reitiring should not take longer than a few days per building once you've reached an agreement is reached. |
| 13 | General Inquiry | Are there specific installation access requirements to be complied with for Tyndall AFB, which include security training, OPSEC requirements? | Contractor badging takes up to two weeks after submission, and specific required information will be covered in the pre-construction meeting held after contract award. |
| 14 | General Inquiry | What other project plans are requirement of this demolition contract? Asbestos abatement plan, environmental protection plan, site access /egress security plan, hazardous materials removal and disposal plan, Accident Prevention Plan, Contractor quality control plan, Storm water Pollution Prevention Plan. | All specific submittals are called out in the PWS, OSHA safety plans, environmental permits, SWPPP for certain. If it's not listed ask specifically if it is needed |
| 15 | General Inquiry | Are we to submit a project schedule with the bid? | A project schedule is not necessary with bid, but be advised that a schedule will be required based off Appendix C, after award |
| 16 | General Inquiry | Please confirm that environmental area air monitoring to be conducted during abatement. Please note that this is in addition to OSHA personal monitoring. | Per standard abatement processes, air sampling must be performed per FDEP guidelines to ensure all dust generated by the abatement process is cleaned up. |
| 17 | General Inquiry | Various buildings are identified in the contaminated sites designated by environmental program. Upon demolition of the structure, prior to removal of the slab, soils or groundwater are potentially contaminated, can some guidance be provided how the government would like these addressed? | As stated in the PWS section 2.2.1k, work on the buildings in contaminated areas must abide by section 2.2.7 |
| 18 | General Inquiry | The PWS requires Restoration backfill to firmness equal to that soil next to the trench, please confirm? What compaction density is expected for the backfill materials, and what lift size? | Backfill should be equal in compaction to adjacent ground (PWS 2.2.1.n) |
| 19 | General Inquiry | Is a finished grade survey required by a Florida licensed Surveyor? | Yes, in accordance with UFGS (PWS 2.2.1.n) |
| 20 | General Inquiry | Is the e waste in the buildings required to be delivered to Tyndall AFB DRMO? | If e-waste is encountered, contractor should notify the Government and determination will be made on whether the contractor is to dispose of it or transport it to DRMO |
| 21 | General Inquiry | Section 2.2 states that “Facilities will be prioritized and scheduled based on dates provided by the Government, which are based on occupancy of facilities, equipment remaining in buildings, and future construction timelines.” For bidding purposes, how many mobilizations should contractors include in their pricing? | Contractors will mobilize one time on-site, it is the Government's intent that facilities will be made available so re-mobilization will not be necessary. |
| 22 | General Inquiry | Section 2.2 and 2.2.2 state that “It is a contractor responsibility to verify accuracy of all maps and drawings;” and that “The Contractor shall be solely responsible for verification and validation of existing conditions.” Since there is no site walk scheduled, how are contractors to verify accuracy? | Contractors should base bids off of attachments, after award but before work starts it is the contractor's responsibility to then verify and validate existing conditions. |
| 23 | General Inquiry | Section 2.2 – Third effort: How deep should contractors expect utility lines to be? | Utility lines are not expected to be deeper than 3-4 ft |
| 24 | General Inquiry | • The PWS (page 2 of 16) states that pavement demolition and abandoned utility lines will be paid at a unit rate (LF and SF respectively). The bid items for CLIN 28 and 29 are per job with a quantity of 1 in lieu of unit price based. Can these items be changed to the unit price basis as stated in the PWS with a budgetary quantity? There is not enough detailed information in the documents for the contractors to bid these 2 items as lump sum. | Yes, these items will be bid as SF for pavement, LF for utilities. See adjusted bid sheet, please list price for the requested SF/LF amount in lines 0029 and 0030, then list price per SF/LF in 0029a and 0030a. |
| 25 | General Inquiry | There are 2 pages with sewer markups. Page 3 (Surveyors page) shows fewer lines to be removed than the page from the Air Force. Page 3 also shows lines and manholes to be either replaced or rehabilitated. Which plan do we use to estimate the demo and remove work and do we need to bid the rehab/replace work? | The two maps provided are intended to show the lines to the best of the Government's knowledge at this time. No rehab/replace work will be included under this requirement. |
| 26 | General Inquiry | The amendment added work on Bldg 422. Will there be a revised Bid Schedule to include that building? | See revised schedule |
| 27 | General Inquiry | We have made efforts to contact the utility owners, but have so far had no luck in receiving a response. Can an allowance be provided for the utility owner’s portion, or can contacts be provided for each utility? | The below POC's were given by the utility owners for the purposes of this requirement. |
Colby Wiggings - cwiggins@gcec.com - (850) 265-3631 ext. 3017 C. Peyton Gleaton Jr. - pgleaton@gcec.com - (850) 913-3734
If any more issue is encountered reaching out to these individuals, please feel free to contact the Government via the POC's given under this solicitation.
| 28 | General Inquiry | The Performance Work Statement requires an Archaeologist to be onsite during excavations. Please confirm this requirement. | The Performance Work Statement is correct, a FL registered archaeologist must be present for ground disturbing activities. |
| 29 | General Inquiry | Is a bid bond not required on this Combined Synopsis/Solicitation? | No, a bid bond is not required |
| 30 | General Inquiry | We have gone through and done demolition and have quantities based on our interpretation of demolition "purple lines" |
Please confirm all purple lines will be removed by demolition contractor.
Are the area designated as "replace lines" - "pink areas" also part of the work?Please confirm that remove and replacement of "pink lines" is not part of the scope of work. Is there a list of the lines to be demolished as the colors are not clear in case of laterals and manholes.Please confirm all laterals coming off of purple lines are also purple.
| Specific colors in the drawings are not relevant, these were the drawings provided that best showed the infastructure to the best of CES knowledge. We have adjusted the bid schedule to provide for a maximum SF/LF to be demo'd, as well as asking for a unit price for both items. Based on timeframes to demo/construct around these areas, contractors will be instructed which lines to demo as the project progresses. If timeframes do not allow for the demolition of the total maximum square footages given in the line items, the Government shall base the amount to be removed from the contract based on the unit price given. The SF given for pavement removal will most likely still include the blue hatch shown in Appendix A Map, however more concrete information will be provided upon award for both the exact areas of pavement and utilities to be remove, and changes made accordingly. | ||
| 31 | General Inquiry | Are the sewer line re-habilitation areas also a part of scope? |
Please confirm the green lines and rehabilitation work are not part of scope. If they are part of scope please provide rehab specification.
| No rehab/replacement work is required under this project. This is just a markup of abandoned infrastructure. | ||
| 32 | General Inquiry | Recycling concrete is not specfically mentioned - would concrete structures be eligible for recycling? |
Please confirm concrete may be recycled.
| Concrete recycling is addressed in 2.2.1.e | |
| 33 | General Inquiry |
| 34 | General Inquiry |
| 35 | General Inquiry |
| 36 | General Inquiry |
| 37 | General Inquiry |
| 38 | General Inquiry |
| 39 | General Inquiry |
| 40 | General Inquiry |
| 41 | General Inquiry |
| 42 | General Inquiry |
| 43 | General Inquiry |
| 44 | General Inquiry |
| 45 | General Inquiry |
| 46 | General Inquiry |
| 47 | General Inquiry |
| 48 | General Inquiry |
| 49 | General Inquiry |
| 50 | General Inquiry |
| 51 | General Inquiry |
| 52 | General Inquiry |
| 53 | General Inquiry |
| 54 | General Inquiry |
| 55 | General Inquiry |
| 56 | General Inquiry |
| 57 | General Inquiry |
| 58 | General Inquiry |
| 59 | General Inquiry |
| 60 | General Inquiry |
| 61 | General Inquiry |
| 62 | General Inquiry |
| 63 | General Inquiry |
| 64 | General Inquiry |
| 65 | General Inquiry |
| 66 | General Inquiry |
| 67 | General Inquiry |
| 68 | General Inquiry |
| 69 | General Inquiry |
| 70 | General Inquiry |
| 71 | General Inquiry |
| 72 | General Inquiry |
| 73 | General Inquiry |
| 74 | General Inquiry |
| 75 | General Inquiry |
| 76 | General Inquiry |
| 77 | General Inquiry |
| 78 | General Inquiry |
| 79 | General Inquiry |
| 80 | General Inquiry |
| 81 | General Inquiry |
| 82 | General Inquiry |
| 83 | General Inquiry |
| 84 | General Inquiry |
| 85 | General Inquiry |
| 86 | General Inquiry |
| 87 | General Inquiry |
| 88 | General Inquiry |
| 89 | General Inquiry |
| 90 | General Inquiry |
| 91 | General Inquiry |
| 92 | General Inquiry |
| 93 | General Inquiry |
| 94 | General Inquiry |
| 95 | General Inquiry |
| 96 | General Inquiry |
| 97 | General Inquiry |
| 98 | General Inquiry |
| 99 | General Inquiry |
| 100 | General Inquiry |
| 101 | General Inquiry |
| 102 | General Inquiry |
| 103 | General Inquiry |
| 104 | General Inquiry |
| 105 | General Inquiry |
| 106 | General Inquiry |
| 107 | General Inquiry |
| 108 | General Inquiry |
| 109 | General Inquiry |
| 110 | General Inquiry |
| 111 | General Inquiry |
| 112 | General Inquiry |
| 113 | General Inquiry |
| 114 | General Inquiry |
| 115 | General Inquiry |
| 116 | General Inquiry |
| 117 | General Inquiry |
| 118 | General Inquiry |
| 119 | General Inquiry |
| 120 | General Inquiry |
| 121 | General Inquiry |
| 122 | General Inquiry |
| 123 | General Inquiry |
| 124 | General Inquiry |
| 125 | General Inquiry |
| 126 | General Inquiry |
| 127 | General Inquiry |
| 128 | General Inquiry |
| 129 | General Inquiry |
| 130 | General Inquiry |
| 131 | General Inquiry |
| 132 | General Inquiry |
| 133 | General Inquiry |
| 134 | General Inquiry |
| 135 | General Inquiry |
| 136 | General Inquiry |
| 137 | General Inquiry |
File details come from the government source that posted it. Updated .