Atch 13-Site Visit Question Answers Document-27 May 25.pdf
PDF 381 KB Posted
- Solicitation number
- FA480325B0011
About this file
This document is a comprehensive Questions and Answers (Q&A) file for a federal contract opportunity to repair Well 3 and Well 5 with SCADA automation at Shaw Air Force Base. The 94-page document contains detailed responses to 105 technical and procedural questions from potential contractors, covering aspects such as electrical systems, network configurations, software licensing, installation requirements, equipment specifications, and project constraints.
Key technical details include requirements for Allen Bradley PLC upgrades, fiber network connections, transformer specifications, software versions (Studio 5000 version 33 or higher), and compliance with NIST 800-53 and 800-82 for Industrial Control Systems. The project is a design-build contract with phased implementation, requiring contractor-furnished equipment and software. Notable requirements include developing SCADA system screens, configuring network switches, installing monitors, and ensuring system compatibility. The government will provide a PC and static IP addresses, while the contractor is responsible for most technical implementation, with government oversight and witness during final commissioning.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA480325B0011
VLSB 24-0019
REPAIR WELL 3 AND WELL 5 WITH SCADA AUTOMATION SITE VISIT
QUESTIONS AND ANSWERS
QUESTION 1. Well 4 utilizes 480VAC VFDs, served by step-up transformers from the building 208 service. What is the service voltage at Wells 3 and 5? If not 480V, should the VFDs match the service size or will the step up transformer need to be provided by the contractor?
ANSWER: Well 3 Main Transformer is a 12.47KV to 208V – However there is already a 208V to 480V 112KVA dry transformer installed Feeding the existing 480V VFD. This 112KVA can remain if it meets the design needs.
Well 5 12.47KV to 208V Transformer – Design Build see SOW for requirements. Contractor will need to provide a dry type transformer for the 480V VFD.
QUESTION 2. The scope requires connection to an existing fiber network. Does base comms manage this network and will the well system be on a vLan or physically isolated for security?
ANSWER: The existing fiber network is on a vLan controlled by the comm squadron.
QUESTION 3. The scope includes the replacement of Well 3 effluent pump but not Well 5.
Please confirm if Well 5 effluent pump will require replacement and associated horsepower?
ANSWER:
See SOW Well 3 pump will not be replaced.
See SOW Well 5 pump will not be replaced.
QUESTION 4. SCADA Software Version - Can the Government confirm if a specific version of Studio 5000 is required or if the contractor can select the latest compatible release?
ANSWER: Current version is 33. The contractor can select the latest compatible version greater or equal to version 33.
QUESTION 5. Managed Switch Alternative - Is there a pre-approved list of acceptable alternatives for the Cisco switch in case it becomes unavailable?
ANSWER: No current list is available. The contractor will be required to submit and receive approved from Shaw.
QUESTION 6. IP Address Assignment - Will the Government provide static IP addresses for all new SCADA equipment or should the contractor coordinate for network configuration?
ANSWER: The Govt will provide the static IP address for the new managed switches after award at the 35% design submittal.
QUESTION 7. Control Logic Review - Can the Government clarify if the control narratives and ladder logic must be approved before physical installation?
ANSWER: Yes- As part of the design build the control narratives and ladder logic must be approved prior the physical installation.
QUESTION 8. Pump Flow Range Confirmation - For soda ash pumps (300-600 GPD), can flow range be finalized based on water pH analysis after NTP?
ANSWER: The soda ash pumps needs to have the ability to pump up to 600 GPD. The flow rate can be reduced based on the pH analysis after the NTP. The system needs to have the ability to adjust the pump speed based on the online analyzers results.
QUESTION 9. Pump Skid Match - Should skids for chemical feed pumps be fabricated to match Well 4's spec exactly or is field adjustment allowed?
ANSWER: The skid should match Well’s 4 spec and any difference shall be called out in the design and must be approved by the Govt.
QUESTION 10. Monitor Procurement - Is the Government providing the 65" and 55" monitors, or is procurement by the contractor?
ANSWER: Contractor to provide and install the monitors and accessory equipment to have a functioning display.
QUESTION 11. Alarm System Integration - Can the Government confirm whether cellular dial-out capabilities need integration into a base-wide notification platform?
ANSWER: This system will have it’s own dial-out capability separate from the COIN network. The system will only have the ability to dial out. It cannot receive any wireless control inputs. This shall be included in the FAT where the contractor shall prove the system cannot be controlled from a wireless remote. The contractor shall be required to provide this in the design and it must be approved by the Govt.
QUESTION 12. Design Review Delays - Will delays in Government review beyond the 21 calendar days for each design phase result in an extension to the PoP?
ANSWER: Any delay solely caused by the government will result in a Period of Performance extension.
QUESTION 13. Submission Standards - Are there submission templates or standards for DD1354 and Functional Acceptance Tests?
ANSWER:
FAT-
1. Introduction
This FAT document outlines the procedures and criteria for testing the upgrade of an Allen Bradley PLC controlling a well automation system. The purpose of this FAT is to verify that the upgraded system meets the specified requirements and functions correctly before deployment to the field.
2. System Description
• System Name: [Well Automation System Name/ID]
• PLC Model (Old): [Original PLC Model Number]
• PLC Model (New): [Upgraded PLC Model Number]
• Software Version: [PLC Programming Software Version]
• Key Functionality: [Briefly describe the core functions of the well automation system, e.g., pump control, valve control, data acquisition, alarm handling]
3. Test Environment
• Location: [Location of the FAT, e.g., Integrator's facility]
• Hardware:
o PLC: [Specify the exact model and revision of the upgraded PLC] o HMI: [Specify the HMI model and software version, if applicable] o I/O Modules: [List all I/O modules used in the test setup] o Network Devices: [List any network switches, routers, etc.] o Simulated Well Equipment: [Describe any simulated equipment used for testing, e.g., simulated pump, valves, sensors]
• Software:
o PLC Programming Software: [Specify the software version used to program the
PLC]
o HMI Development Software: [Specify the HMI development software version, if applicable]
• Test Data: [Describe the test data that will be used, e.g., simulated sensor readings, setpoints]
4. Test Cases
Test Case
ID
Description Test Steps Expected Result Pass/Fail Criteria
FAT-
Verify successful PLC startup
Power on the system.
PLC enters RUN mode without errors.
PLC must enter RUN mode within [time limit] and no fault codes should be present.
Test Case
ID
Description Test Steps Expected Result Pass/Fail Criteria
FAT-
Verify pump control functionality
Issue commands to start and stop the pump.
Pump starts and stops according to the commands.
Pump status should match the commanded state within [time limit].
FAT-
Verify valve control functionality
Issue commands to open and close valves.
Valves open and close according to the commands.
Valve status should match the commanded state within [time limit].
FAT-
Verify alarm handling
Simulate alarm conditions.
Alarms are triggered and displayed correctly on the HMI.
Alarms should be triggered within [time limit] and displayed correctly on the HMI.
Acknowledge functionality should be tested.
FAT-
Verify data acquisition
Monitor sensor readings.
Sensor readings are accurate and consistent.
Sensor readings should be within the specified accuracy range.
FAT-
Verify communication with HMI
Send and receive data between the PLC and HMI.
Data is exchanged correctly between the PLC and HMI.
Data should be displayed correctly on the HMI and control actions from the HMI should be reflected in the PLC.
FAT-
Verify historical data logging
Log data for a specified period.
Data is logged correctly and can be retrieved.
Logged data should be accurate and retrievable.
(Add more test cases as needed to cover all critical functionalities.)
5. Acceptance Criteria
• All test cases must pass.
• The system must meet all specified performance requirements.
• All documentation must be complete and accurate.
6. Test Schedule
• Start Date: [Date]
• End Date: [Date]
7. Roles and Responsibilities
• Test Lead: [Name and Contact Information]
• Client Representative: [Name and Contact Information]
• System Integrator: [Name and Contact Information]
8. Test Deliverables
• FAT Test Plan
• FAT Test Report (including pass/fail results for each test case)
• Updated System Documentation
9. Sign-off
____________________________ Date: _____________ 20 CES
____________________________ Date: _____________ System Integrator
This template provides a starting point for your FAT. Remember to tailor it to the specific requirements of your well automation system and the scope of the PLC upgrade. Include specific tag names, setpoints, and tolerances where applicable. Consider adding tests for error handling, recovery procedures, and security features as needed. Ensure clear communication and collaboration between all stakeholders throughout the FAT process.
QUESTION 14. Demolition Drawing Clarification - Is there a demolition drawing that indicates boundaries for conduit and cabinets to be removed?
ANSWER: Design Build- Contractor shall meet the SOW requirements.
QUESTION 15. Hazmat Survey - Are there any existing hazardous materials surveys available for areas with equipment demolition?
ANSWER: See SOW
QUESTION 16. Software Licenses - Is the Government providing the software licenses for Studio 5000 or should these be included in the contractor's cost?
ANSWER: See SOW contractor is providing the software.
QUESTION 17. Site Access - Will escort-free access to Well locations be available throughout the construction schedule?
ANSWER: Yes. However, the contractor will have to coordinate any outage with 20CE.
The only area that will require an escort is in the EMCS shop control room.
QUESTION 18. Stripper Tank Level Sensor Setup - Can the Government confirm if a radar level sensor is acceptable in place of an ultrasonic sensor at the stripper tower tank, especially considering condensation or foam conditions?
ANSWER: See updated SOW – Only radar will be allowed.
QUESTION 19. HMI Rescale Functionality - Should the contractor develop custom HMI functionality for setting the high-high and low-low-water level marks during commissioning, or will standard Allen Bradley modules be provided?
ANSWER: See SOW the contractor will be required to provide this function. The Govt will not be providing standard AB modules.
QUESTION 20. Heat Tracing Requirements - Is there a preferred specification or model for the heat tracing system required for the stripper level sensor pipe?
ANSWER: No preferred
QUESTION 21. Electrical Cabinet Demolition Scope - Can the Government confirm whether any of the conduit or cabling attached to the cabinets to be demolished can be removed entirely or must be capped and left in place?
ANSWER:
See updated SOW attachment 01
QUESTION 22. Fiber Line Protection During Demo - What precautions or Government-provided procedures must be followed to protect the fiber line that is to remain during cabinet demolition?
ANSWER: The fiber is currently working. The contractor is reasonable for any damage to the fiber or other equipment during the project inside the work area.
QUESTION 23. PC Workstation Power and Data Requirements - Will the Government provide the necessary power and data connections at the designated Allen Bradley PC workstation location, or should the contractor include this infrastructure?
ANSWER: The PC workstation does have a 120V outlet that can be used. The contractor will have to provide the data connections infructuous.
QUESTION 24. Main Motor Supply Voltage Confirmation - Can the Government confirm the voltage and phase supply for the new main well motor VFD to ensure compatibility during design?
ANSWER:
See SOW attachment 01 480V at Well 3
See SOW attachment 01 208V currently at Well 5 Will be 480V.
QUESTION 25. Sample Table Specifications - Are there specific dimensions or material requirements for the drop-down sample table to be installed at Well 3?
ANSWER: See Attachment 01
QUESTION 26. Preferred HMI Display Theme - Does the Government require the gray background theme shown in the example graphic to be used consistently across all HMI displays for each well and tower?
ANSWER: Design Build- Contractor shall meet the SOW requirements.
QUESTION 27. Permit Requirements - Can the Government confirm if all permits listed (NPDES, SWPPP, FAA, etc.) are required for this scope? Are any pre-approvals in place?
QUESTION 28. Utility Coordination Timeline - For AF Form 103 submission, what is the current average turnaround time for approval?
ANSWER: Avg 2 weeks
QUESTION 29. Environmental Inspections - Will any EPA or SC DHEC inspections be scheduled during or post-construction?
ANSWER: (DHEC) DES follows the EPA rules. No EPA inspections required.
QUESTION 30. Concrete Washout Area - Is there a pre-approved on-base location for temporary washout facilities?
ANSWER: The Base will approve a temporary washout location within the job site. The will be responsible to restore the temporary washout area at the end of the job.
QUESTION 31. SCADA Panel Compatibility - Will the existing fiber backhaul or SCADA panel support the new analyzers, or is an upgrade required?
ANSWER: It is the contractors reasonability to ensure the any installed equipment will provide a functioning SCADA system.
QUESTION 32. DD1354 Point of Contact - Is a specific point of contact already designated for the review and signature of the interim/final DD1354 forms?
ANSWER: Real property -Christopher Hirak
QUESTION 33. Confined Space Entry Plan - Can the Government provide a sample confined space program template to align our submittal with base requirements?
ANSWER: This SOW should not require the contractor to enter a confined space.
QUESTION 34. On-Base Waste Disposal - Is there an authorized on-base transfer station available for non-hazardous demolition waste?
ANSWER: No. The contractor shall remove all waste of the Base.
QUESTION 35. Security Screening for Subs - Are there any additional security screenings (e.g., background checks) required beyond base access requests for subcontractor personnel?
ANSWER: All workers will require approved background checks to work on the base.
QUESTION 36. SCADA Access Protocols - Will the Government provide a specific list of required login access levels and SCADA user roles for each site (Well 3, Well 5, Tower, WIFM)?
ANSWER: Login access levels will be decided at the 65% design level.
QUESTION 37. Use of Government Fiber Network - Is there any restriction on the contractor extending or modifying existing Shaw AFB fiber infrastructure to support SCADA communications?
ANSWER: The contractor can extend the existing fiber if required. This shall be called out in the design.
QUESTION 38. Construction Schedule Constraints - Are there any anticipated base-level utility outages or training activities that will limit access or power availability during the 429/477-day performance windows?
ANSWER: No there are no anticipated base-level utility outages or training activities that will limit access or power availability during the 429/477-day performance windows.
QUESTION 39. Permitting Responsibility - Will the Government assist in obtaining Shaw AFB-specific permits, such as dig, outage, or crane permits, or must the contractor directly coordinate all of these?
ANSWER: The contractor will directly coordinate with the base on the permits.
QUESTION 40. Buy American Act Requirements - Are there any known waivers or exceptions in place that permit the use of foreign-made analyzers or components for SCADA hardware?
ANSWER: No known waivers or exceptions.
QUESTION 41. Security Clearance Requirements - Do any of the contractor or subcontractor personnel require background investigations beyond the standard base access process?
ANSWER: No.
QUESTION 42. Preconstruction Conference Scope - Will subcontractors or key technical personnel be required to attend the preconstruction conference mentioned in FAR 52.236-26?
ANSWER: Yes. The Subs can call in. The GC, PM and superintendent needs to be there in person.
QUESTION 43. Access to As-Built Documentation Will the Government provide existing as-built drawings and SCADA integration documentation for Well 3 and Well 5 before the design phase?
ANSWER: After the award the government will provide the provide existing asbuilts.
QUESTION 44. Interface with Existing Systems - Can the Government confirm whether the contractor must also ensure compatibility with the EMCS (Energy Management Control System)?
ANSWER: This SCADA system will be separate from the EMCS. The contractor will not be required to work with Harris Controls.
QUESTION 45. Liquidated Damages Clarification - In the case of phased delivery or substantial completion milestones, how will the $410.32/day liquidated damages be assessed?
ANSWER: When considering assessing liquidated damages, the Government will not factor phase delivery or substantial completion milestones. Per FAR clause 52.211-12, the government will consider assessing Liquidated Damages against the Contractor in the amount of $410.32 each calendar day in the event it has been determined the Contractor is at fault without acceptable reason for failure to complete the work within the specified time mutually agreed upon in the contract.
QUESTION 46. Design Submittal Turnaround - What is the maximum expected review time for design submissions before it is considered a schedule-impacting delay under FAR clauses?
ANSWER: Anytime past the number of calendar days specified in the Statement of Work for reviews is considered a schedule-impacting delay.
QUESTION 47. Pricing Sheet - Chemical Analyzer Count & Spec - How many total chemical analyzers are required (Chlorine, Fluoride, Phosphate, pH)? Are specific makes/models preferred?
QUESTION 48. Pricing Sheet - TV Display Requirements - What specifications are required for the 65" and 55" monitors (e.g., wall mount vs. stand, outdoor vs. indoor)? Will HDMI input suffice?
ANSWER: The monitor shall be mounted on the wall in an indoor area. HDMI input will be allowed.
QUESTION 49. Pricing Sheet - Studio 5000 Licensing - Does the Government provide Studio 5000 licenses, or should these be included in the material cost? Which version is required?
ANSWER: See Questions 4 and 16.
QUESTION 50. Pricing Sheet - FactoryTalk Software Scope - Is FactoryTalk being used strictly for alarming/HMI or for full SCADA integration? Is a site-wide license required?
ANSWER: See the SOW. “The contractor shall provide all management, tools, supplies, equipment, labor, and applicable licenses and permits necessary to complete the requirements within.”
QUESTION 51. Pricing Sheet - Allen Bradley VFD Specs - What is the horsepower, voltage, and phase requirement for the VFD(s)? Will they be mounted indoors or outdoors?
ANSWER: See SOW and attachment 01
QUESTION 52. Pricing Sheet - Labor Hour Guidance - Is there a standard labor rate or labor category to be used in the 'Avg. Rate ($/hr)' field?
ANSWER: There is not a standard labor rate or category used.
QUESTION 53. Pricing Sheet - Material Delivery - Should material costs include shipping to Shaw AFB, or is there a designated staging area for government receipt?
ANSWER: There is not a designated staging area for government receipt. It is the contractor’s responsibility for all logistics required for material shipment to the final preferred destination.
QUESTION 54. Pricing Sheet - Line Item Quantities - Can the Government confirm quantities for each item (e.g., eyewash stations, TVs, software installations) if left blank in the pricing sheet?
ANSWER: Design/ Build - Contractor responsible for quantities based on the SOW and any code requirements.
QUESTION 55. Pricing Sheet - Panel & Cabinet Hardware - Will additional line items for control panel enclosures or conduit runs be provided, or should they be embedded in other cost lines?
ANSWER: The contractor is allowed to add line items in the blank excel file and this is preferred over embedding the cost in other lines.
QUESTION 56. Paint Scope Clarification - Is the contractor responsible for priming and painting newly installed supports, piping, or equipment enclosures, even if not itemized in the bid sheet?
ANSWER: Per the SOW “All work shall be done in strict accordance with this Statement of Work and subject to the terms and conditions of the contract and in accordance with (UFC) Unified Facilities Criteria, Unified Facilities Guide Specifications (UFGS), the International Building Code (IBC), International plumbing code (IPC), South Carolina Department of Health and Environmental Control (SCDHEC), National Electrical Code (NEC), National Electrical Safety Code (NESC), National Fire Protection Association (NFPA), EPA 402-K-01-001 (2008), South Carolina Department of Transportation (SCDOT), South Carolina Department of Health and Environmental Control (SCDHEC) Shaw Air Force Base Design and Construction Standards, Change 2, 21 Aug 2018 and all other applicable codes.”
QUESTION 57. Paint Type & Spec Confirmation - Are there base-approved paint types or color standards for equipment, enclosures, or supports at Shaw AFB?
ANSWER:
Design Build- Contractor shall meet the SOW requirements and follow the UFC’s and Shaw design standards.
QUESTION 58. Restoration of Disturbed Finishes - Should any wall/ceiling/floor finishes disturbed during demo or installation be restored with matching paint? Is full-room repainting required?
ANSWER: Corner to Corner if any section of the wall is damaged.
QUESTION 59. Generator Backup Clarification - Does the project require permanent or temporary generator backup for the SCADA systems, VFDs, or control panels? Or is a UPS system sufficient for all redundancy needs?
ANSWER: UPS is sufficient.
QUESTION 60. HVAC System Requirements - Will this project require HVAC upgrades or new ventilation within the well enclosures or chemical rooms? If so, are specific models or sizing constraints provided?
ANSWER: This is a design/ build project. If there is a code requirement or a new heat load that will require the contractor to install or upgrade the HVAC system, the contractor should plan for it.
QUESTION 61. HVAC Monitoring Integration - If existing HVAC systems are in place, must they be integrated into the SCADA/EMCS system?
ANSWER: This is a design/ build project. If there is a code requirement for the existing HVAC systems to be integrated into the SCADA system the contractor should plan for it.
QUESTION 62. Condensate Handling & Drainage - If HVAC equipment is to be installed, where should condensate drainage be routed for compliance with base standards?
ANSWER: Closest drain that does not cause a tripping hazard.
QUESTION 63. Fire Sprinkler Applicability - Will any areas of this project (e.g., new electrical cabinets, analyzer skids, or workspaces) require fire sprinkler system design and installation per UFC 3-600-01 and NFPA 13?
ANSWER: No.
QUESTION 64. Confirmation of Government-Furnished Equipment - Can the Government confirm that no equipment (e.g., analyzers, pumps, software licenses, monitors) will be furnished as GFE for this project? All materials are assumed to be Contractor-Furnished and Contractor- Installed.
ANSWER: Per the SOW. The government will furnish a PC. The contractor is responsible for installing the necessary software and configuring it for SCADA system access and control.
QUESTION 65. Submittal Review Turnaround - Can the Government confirm the number of calendar days allotted for submittal reviews at each stage (e.g., 35%, 65%, 95%)? Will delays in review affect the PoP?
ANSWER: See SOW and question 12
QUESTION 66. Fiber Line Routing Clarification - Will existing ductbanks or raceways be available for use to route new SCADA fiber, or should the contractor trench new conduit paths?
ANSWER: All fiber is already installed at each Well location. No new trench should be required in this project.
QUESTION 67. Responsibility for Network Configuration - Is the Government responsible for assigning IP addresses and configuring SCADA network switches, or should the contractor preconfigure and coordinate settings with base IT?
ANSWER: See SOW Contractor will reuse the automated logic IP for the new switches IP address.
QUESTION 68. Tower Alarm Integration Detail - What format (digital, analog, MODBUS, etc.)
should tower high/low level alarm signals be delivered in for base-wide alerting?
ANSWER: This is a design/ build project. The contractor shall provide what is required in the SOW.
QUESTION 69. Site Access & Escort Requirements - Will contractor personnel need daily escorts, or will recurring access badges be provided for cleared staff after initial base approval?
ANSWER: Only area that will require an escort is in the EMCS shop control room.
QUESTION 70. Demolition Waste Disposal Location - Is there an on-base waste transfer station for demo materials, or must all waste be hauled offsite? Any restrictions on disposal timing or haul routes?
ANSWER: All waste shall be hauled offsite. Disposal timing shall be completed during working hours 0800 to 1600.
QUESTION 71. Security Classification of SCADA Data - Will the SCADA system or any collected data be considered sensitive or classified, requiring encryption or secured communication channels?
ANSWER: This is a design bid build. Per the SOW “All work shall be done in strict accordance with this Statement of Work and subject to the terms and conditions of the contract and in accordance with (UFC) Unified Facilities Criteria, Unified Facilities Guide Specifications (UFGS), the International Building Code (IBC), International plumbing code (IPC), South Carolina Department of Health and Environmental Control (SCDHEC), National Electrical Code (NEC), National Electrical Safety Code (NESC), National Fire Protection Association (NFPA), EPA 402-K-01-001 (2008), South Carolina Department of Transportation (SCDOT), South Carolina Department of Health and Environmental Control (SCDHEC) Shaw Air Force Base Design and Construction Standards, Change 2, 21 Aug 2018 and all other applicable codes.”
QUESTION 72. Integration to EMCS/BAS - Is this SCADA upgrade expected to tie into an existing Energy Management Control System (EMCS) or is it a fully isolated system?
ANSWER: The system currently has COMMS and fiber connections to each well. The contractor shall per the SOW provide a working system.
QUESTION 73. System Acceptance Criteria - Will the Government conduct a single final inspection, or is phased acceptance (e.g., Well 3, then Well 5, then Tower) expected for system commissioning?
ANSWER: Phased.
QUESTION 74. Spare Parts and Training - Is the contractor required to provide spare parts or operator training as part of closeout? If so, what deliverables are expected?
QUESTION 75. Commissioning Witness and Government Involvement - Will Government personnel be required to witness final commissioning, or is the contractor solely responsible for validating system performance before final DD1354 submission? Are there specific test procedures or forms (e.g., checklist or FAT) to be used during this phase?
ANSWER: The Govt will be required to witness the final commissioning. See FAT example.
QUESTION 76. General Conditions - Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
ANSWER: The SSHO and QC can be a shared role. Superintendent can’t not be a shared role.
QUESTION 77. General Conditions - Are there any phasing requirements?
ANSWER: Contractor will be required to coordinate well outages with 20CES. Two week notice required before outage.
QUESTION 78. General Conditions - If the building remains occupied, how many people will be in the building?
ANSWER: 5
QUESTION 79. General Conditions - Are there any temporary heating/cooling requirements?
QUESTION 80. General Conditions - Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
ANSWER: Yes, the Period of Performance end date can be extended if it has been determined long lead time due to markets conditions impact material/equipment deliveries. The contractor must provide proof the material was ordered and the delivery time.
QUESTION 81. General Conditions - Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions.
ANSWER: No
QUESTION 82. General Conditions - Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation.
ANSWER: See SOW.
QUESTION 83. General Conditions - Please provide the contact information for the building controls contractor.
ANSWER: This information is not relevant. There is not active controls contractor contract.
QUESTION 84. General Conditions - Please provide the contact information for the building fire alarm company.
ANSWER: Not relevant.
QUESTION 85. General Conditions - Please provide the site visit attendee sign-in sheet.
ANSWER: No, The Contracting Officer has made the decision NOT to provide site visit sign in sheet.
QUESTION 86. General Conditions - Is this project tax exempt?
ANSWER: The Contracting Squadron does not have the authority to tax exempt this requirement. The Contractor is responsible for any tax requirements that may or may not apply to this requirement.
QUESTION 87. Per Federal Information Security Management Act (FISMA) 2002, FISMA 2014, and Department of Defense (DoD) policies and having recently completed SCADA projects within the MCEN, do you likewise require compliance with NIST 800-53 and 800-82 for Industrial Control Systems or will you be implementing those in the future?
ANSWER: Yes the system shall be required to comply with NIST 800-53 and 800-82 for Industrial Control Systems
QUESTION 88. If the above compliance is required, have you assessed the system as low security risk?
ANSWER: Yes
QUESTION 89. Can you provide a network drawing showing where the Shaw AFB Network between the Wells and the Operations/Controls area?
ANSWER: See attachment 01
QUESTION 90. Can you provide a clearer drawing of Atch_2_- _Shaw_AFB_Well_Utility_Controls_Schematic.pdf? Some sheets of the drawing are not readable.
ANSWER: See word doc. SCADA QA answer
QUESTION 91. What is the space available for the Folding Table next to the sampling station?
ANSWER: Design Build- Contractor shall meet the SOW requirements. Attachment 01 has an example of the table.
QUESTION 92. Can you provide an I/O list? The wiring diagrams are too blurry.
ANSWER: See Q 89.
QUESTION 93. Please provide all technical documentation.
QUESTION 94. What is the specified manufacturer for equipment, or is it up to contractor proposal?
QUESTION 95. How many flow meters need to be replaced and what is the specification?
QUESTION 96. Missing information - “Shall have a plant system-based layout (See attachment 01 for example)” what is the attachment 01?
ANSWER: Follow up with 20 CONS Attachment 01 has this information and is apart of the contract.
QUESTION 97. How many Gold 3656 pumps are there in Well 3, which ones will be replaced, and what are their technical specifications?
ANSWER: See Updated SOW. This will not be replaced.
QUESTION 98. Does the tank have the mechanical provision for mounting the new ultrasonic sensor, or should it be installed on the same pipeline where the 3 existing level sensors are installed?
ANSWER: See SOW Design Build contractor providing a new 4’’ clear PVC pipe that the sensor will be mounted to.
QUESTION 99. What are the tank specifications and mechanical capability to install an overflow sensor and level sensor?
QUESTION 100. What is the network communication (fiber optic, ethernet) between the tanks and Building 251?
ANSWER: Fiber optic from the well buildings to the B251 EMCS
QUESTION 101. What version of STUDIO 5000 and FactoryTalk are required and what license type?
ANSWER: See QA04
QUESTION 102. Is the contractor required to provide the server, if so, what are the specifications?
QUESTION 103. What is the preferred SCADA software?
QUESTION 104. What is the total number of screens to be developed for the SCADA system?
QUESTION 105. What timeframe for warranty and technical support is required from the contractor?
ANSWER: See updated SOW
***No other questions were provided for this requirement***