Attch 07 AF 3052 Construction Cost Estimate.xls
XLS spreadsheet 54 KB Posted
- Attached to
- Multiple Award Construction Contract (MACC) at Langley AFB/Ft Eustis AB, VA Federal contract opportunity
- Solicitation number
- FA4800-11-R-0002
About this file
Attachment 07 AF 3052 Construction Cost Estimate
View the file
Other files for this federal contract opportunity
Show all 50
Multiple Award Construction Contract (MACC) at Langley AFB/Ft Eustis AB, VA has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Discription of Work Solicitation No.: FA4800-11-R-0002 Attachment 07
AF Form 3052
| C O N S T R U C T I O N C O S T E S T I M A T E B R E A K D O W N | |||||||||||
| CONTRACTOR: | ADDRESS | ||||||||||
| CONTRACT FOR: | PROPOSED TOTAL PRICE | ||||||||||
| PURCHASE REQUEST No. | PROJ No. | WORK LOCATION | |||||||||
| MATERIAL COST | L A B O R C O S T | ||||||||||
| Line No. | Item | Unit | Qty. | Unit | Total | Man hour | Avg. Rate | Total | Other Direct Cost | Line Total | MEANS REFERENCE |
| 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| 3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 4 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 6 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 7 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 8 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 9 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 11 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| 12 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Sub-Total | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||||
| 4.5% Tax | $ - 0 | $ - 0 | |||||||||
| Labor Burden 25% | $ - 0 | $ - 0 | |||||||||
| TOTAL | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
&LAF Form 3052, JAN 88&RSheet &P of &N
SUMMARY SHEET
| SUMMARY SHEET | ||||||
| PROJ No. | ||||||
| TOTAL MATERIAL COSTS | $ - 0 | (1) | ||||
| TOTAL LABOR COSTS | $ - 0 | (2) | ||||
| TOTAL OTHER DIRECT COSTS | $ - 0 | (3) | ||||
| TOTAL DIRECT COSTS | $ - 0 | (4) | ||||
| FIELD OVERHEAD ____% | 0% | $ - 0 | (5) | |||
| SUBTOTAL | $ - 0 | (6) | ||||
| PROFIT ____ % | % | $ - 0 | (7) | |||
| SUBTOTAL | $ - 0 | (8) | ||||
| HOME OFFICE G&A ____% | % | $ - 0 | (9) | |||
| SUBTOTAL | $ - 0 | (10) | ||||
| BOND ____ % | % | $ - 0 | (11) | |||
| TOTAL PRICE | $ - 0 | (12) | ||||
| Markups: | ||||||
| Subcontracted labor & material: | $ - 0 | |||||
| General & Administrative: | $ - 0 | |||||
| Total Markups: | $ - 0 | |||||
| Grand Total Price: | $ - 0 | |||||
| BY: | ||||||
| Company Name | Signature | |||||
| Title | Date | |||||
| INSTRUCTIONS | ||||||
| (1) - (3) | Transfer the totals from the face of the AF Form 3052. (1) - (3) include sales tax and labor burden. | |||||
| (4) | Total of Lines (1) thru (3) | |||||
| (5) | Enter the actual field overhead percentage experienced. This may not be an arbitrary figure. | |||||
| Rate is applied to Line (4). | ||||||
| (6) | Subtotal cost of Lines (4) and (5). | |||||
| (7) | Enter the percentage of profit requested. Rate is applied to Line (6). | |||||
| (8) | Subtotal cost of lines (6) and (7). | |||||
| (9) | Enter the actual Home Office General and Administrative rate experienced. These expenses | |||||
| relate to the indirect costs associated with the operation of the company's office. This may not | ||||||
| be an arbitrary figure. Rate is applied to Line (6). | ||||||
| (10) | Total of Lines (8) and (9). Per DoD pricing policies, profit is not applied to G&A. | |||||
| (11) | Enter actual bond rate. Proof of additional bonding may be required. Rate is applied to Line (10). | |||||
| (12) | Total of Lines (10) and (11). | |||||
| BE PREPARED TO SUBSTANTIATE ALL COSTS AND RATES |