Attachment 1- Statement of Need MUNS Carpet.pdf
PDF 358 KB Posted
- Attached to
- B1319 Carpet, Asbestos, Furniture
- Solicitation number
- FA468625QS001
About this file
This is a Statement of Need (SON) from the Department of the Air Force, 9th Reconnaissance Wing at Beale Air Force Base, California, dated August 1, 2025, for carpet replacement, asbestos abatement, and furniture moving services at Building 1319. The contractor must replace existing carpet with new 24"x24" carpet tiles and cove base in all carpeted areas except those with existing tiles, concrete, and restrooms, covering approximately 307 square yards with 720 linear feet of 4" cove base material. Room 7 requires only carpet removal and asbestos abatement without reinstallation. Specific carpet material options are provided from manufacturers including J+J Flooring Group, Interface Americas, Mohawk, Mannington, Tarkett, Milliken, and Bentley Mills, with mandatory compliance to Air Force Carpet II Ordering Guide procedures through Tier I contractors.
The scope includes comprehensive asbestos abatement with removal of asbestos-containing materials (ACM) from all carpeted office areas, concrete subfloor preparation, and proper disposal per applicable federal and state regulations including 29 CFR Parts 1910.1001 and 1926.1101. The contractor must submit an asbestos abatement plan, obtain required certifications, provide air clearance sample results, and notify the U.S. EPA at least 10 business days before work begins. Additionally, the contractor is responsible for moving and storing all furniture and equipment from the approximately 2,760 square foot work area, with storage units placed in designated parking areas. Work must be performed between 0700-1600 hours, Monday through Friday, during specific available periods: July 29-August 8, August 26-September 5, September 30-October 17, November 11-28, December 23-January 23, and February 17-March 6, while observing all federal holidays.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS 9TH RECONNAISSANCE WING (ACC)
BEALE AIR FORCE BASE, CALIFORNIA
1 August 2025
MEMORANDUM FOR 9 CONS
FROM: 9 CES/CEOER
SUBJECT: B1319 Replace Carpet, Asbestos Abatement, Furniture Move - Statement of Need
(SON)
A. General Scope. The Contractor shall furnish all supervision, labor, tools, equipment, materials, operations, incidentals, and deliverables as required to do the following at building
1319:
Carpet and Cove Base
• Replace the existing carpet with new carpet tiles and cove base in all existing carpeted areas except for areas with existing tiles and concrete and restrooms. See attached floor plan for areas that require carpet replacement.
• Room 7: This room only requires carpet removal and asbestos abatement. Do not install carpet in this room. Ensure all debris, glue, etc. are removed and cleaned to bare concrete.
• Compliance is mandatory to follow ordering procedures outlined in the Air Force Carpet
II Ordering Guide. Per the guide, Contractors are required to contact the Tier I
Contractors for material quotes and orders. NOTE: Contractor mark-up/profits are not allowable on items purchase via Tier I contracts.
Carpet Selection 24”x24” Carpet Tile
Carpet Material J+J Flooring Group: Knit 2711, Boucle 3081 Collection
Interface Americas: After Dark 105704 Night Flight
Collection
Mohawk: BT437 Shaded Lines Tile Page 4, 979 Pencil Lead
Mannington: Acorn 84334 Entwined Collection
Tarkett: Cedar Deck 36205 Fabricate Collection
Milliken: Empire DES174 City Proper Collection
Bentley Mills: Backstage 8BC200AA1K 4GS-T
Square Yards 307
Cove Base Material 4” size
Linear Feet 720
Number of Corners None
Furniture Removal and Storage
1. Due to the installation of the new carpet in building 1319, the Contractor is responsible for moving furniture to a storage area that will not affect furniture/office equipment from inclement temperatures and weather, and then back into the office once the carpet installation is complete. The Contractor shall move all furniture (tables, filing cabinets, chairs, paper shredders, etc.) and all items on the walls in all office areas and rooms with old carpet. The combined area is approximately 2,760 sq ft. All furniture shall be placed in their original positions. Any fixed/immovable items shall be covered/protected by the
Contractor to avoid asbestos containing material (ACM) exposure.
2. The government (user) shall remove all personal items, wall items, and any government issued items/workstation electronics (phones, monitors, laptops, etc.) as well. Any fixed/immovable items shall be covered/protected by the Contractor to avoid ACM exposure.
3. Storage. The Contractor must provide a storage solution and placement for the furniture, as agreed by the user. Storage units (and refuse bins) shall be placed in the parking area outside the building or as designated by the user. The user shall ensure these areas agreed upon are cleared of obstructions.
4. The period of performance is highly dependent on the timeline of carpet installation and asbestos abatement.
Asbestos Abatement and Submittals
• Remove ACM in all offices and rooms with existing carpet except for areas with existing tiles and concrete.
• Prep concrete subfloor to ensure ACM is removed and new carpet tiles adhere to it.
Grinding may be required if the underlying material is not easily removed.
• Submit an Asbestos Abatement plan with applicable asbestos worker/abatement certifications.
• Remove all debris/waste/ACM materials identified in the asbestos report and dispose per abatement plan.
• Asbestos air clearance sample results, performed under direct supervision of a third-party
California-certified asbestos consultant.
• Submit to the United States Environmental Protection Agency (U.S. EPA) written
NESHAP notification of regulated asbestos renovation activities, at least 10 business days before starting renovation or demolition work. A signed copy of the notification form shall be submitted to U.S. EPA at the address below:
US EPA Pacific Southwest, Region 9
75 Hawthorne St.
San Francisco, CA 94105
There is no fee associated with submitting an Asbestos Notification Form to U.S. EPA.
Contractor shall submit a copy of the notification submittal to 9 CES/CEIE
(Environmental) Air Quality/Toxics Program Manager, Susan Stewart, at susan.stewart.7@us.af.mil.
• Submit a hazardous waste manifest to 9 CES/CEIE Environmental Manager, Eric Maresh, at eric.maresh.3@us.af.mil.
• The Contractor shall also adhere and comply with the following:
o All applicable Federal, State, and local regulations prior to and during commencement of work to include 29 CFR Part 1910.1001, 29 CFR Part 1926.1101, 40 CFR Part 763, subpart E, 15 USC Chapter 53, and 40 CFR Part 61, subpart M, prescribe requirements for identifying, monitoring, removal and disposal of asbestos containing materials (ACM), notifying building occupants of potential asbestos-related hazards, and acquiring specialized asbestos-related training.
o State regulations Cal OSHA Construction Safety Orders—(Title 8 CCR, Ch 4, Subchapter 4, Article 4, Section 1529) and Environmental Health Standards for
Management of Hazardous Waste—(Title 22 CCR, Social Security, Division 4.5
B. Access. The Contractor Manager or alternate shall complete an entry authorization list
(EAL) for access to Beale Air Force Base. The request shall be submitted within two (2) weeks of delivery to Pass and Registration via the Government Point of Contact (POC) identified in the inspect and accept information section of the contract. All contractor vehicles must enter the base via Wheatland Gate and shall be subject to inspection. All contractor personnel must obtain base passes or be listed on the Entry Access List (EAL) throughout duration of work performance.
Any persons in the EAL are required to bring two (2) forms of identification or REAL ID to access the base.
mailto:susan.stewart.7@us.af.mil mailto:eric.maresh.3@us.af.mil https://www.dir.ca.gov/Title8/1529.html https://www.dir.ca.gov/Title8/1529.html https://govt.westlaw.com/calregs/Browse/Home/California/CaliforniaCodeofRegulations?guid=I81CB6A705B6111EC9451000D3A7C4BC3&originationContext=documenttoc&transitionType=Default&contextData=(sc.Default)&bhcp=1
C. Hours of Operation. All work shall be accomplished between the hours of 0700-1600, Monday through Friday. Below are the available dates the Contractors can work due to mission requirements and operations/training:
• 29 July - 8 August
• 26 August - 5 September
• 30 September - 17 October
• 11 November - 28 November
• 23 December - 23 January
• 17 February - 6 March
D. Federal Holidays. ACC follows the established Federal Government schedule for holidays provided during each work year. The holidays recognized by the Federal Government are:
New Years Day 1 January
Martin Luther King Day 3rd Monday in January
Washington’s Birthday 3rd Monday in February
Memorial Day Last Monday in May
Juneteenth 19 June
Independence Day 4 July
Labor Day 1st Monday in September
Columbus Day 2nd Monday in October
Veterans Day 11 November
Thanksgiving Day 4th Thursday in November
Christmas Day 25 December
If these Holidays fall on Saturday, the preceding Friday will be observed. If these Holidays fall on Sunday, the following Monday will be observed.
Any other day designated by Federal Statute
Any other day designated by Executive Order
Any other day designated by the President’s Proclamation
Down-days. (i.e., Family Day) declared by the AETC Commander are considered duty days and are not included in the definition of a holiday.
E. Administrative Days. The Wing Commander may order a base closure due to weather or other unforeseen circumstances. Contractor employees shall not report to work if the base is closed, but work shall be accomplished as soon as possible after reopening the base.
F. Work Items. The Contractor shall comply with all applicable Federal, State, and local NEC construction standards. Current Air Force Occupational Safety and Health (AFOSH) standards and COVID-19 safety regulations also apply.
The Contractor shall comply with IAW all NFPA, AFI, UFC and ETL standards for fire safety.
All waste material is to be removed off base by the contractor. The Contractor will practice good housekeeping during the project.
WARREN R. CINCO, CIV, USAF
Planner/Manager
| 2025-08-01T10:37:11-0700 | |
| CINCO.WARREN.RIONDA.1254153113 |
File details come from the government source that posted it. Updated .