Q & A #2

View the file

Other files for this federal contract opportunity

Other files attached to Replace UST Spill Buckets, newest first.
File Type Posted
Q&A_4.pdf PDF
Amendment_4_--_FA462619RA015.pdf PDF
Attch_10_Sections_L&M_Replace_UST_Spill_Buckets_-_Revised_23_Sep_19.pdf PDF
Summary_of_Changes_-_Amendment_4.pdf PDF
Q&A_3_-_FA462619RA015.pdf PDF
Amendment_03_-_FA462619RA015.pdf PDF
Summary_of_Changes_-_Amendment_3.pdf PDF
Attch_10_Sections_L&M_Replace_UST_Spill_Buckets_-_Revised_13_Sep_19.pdf PDF
Q&A_1.pdf PDF
Summary_of_Changes_-_Amendment_2.pdf PDF
Attch_10_Sections_L&M_Replace_UST_Spill_Buckets_-_Revised_5_Sep_19.pdf PDF
Amendment_02_--_FA462619RA015.pdf PDF
Attch_1,_Technical_Specification_Revised_9-3-19.pdf PDF
Attch_4,_Spill_Buckets_Drawing_Revised_9-3-19.pdf PDF
Attch_2,_Submittal_Schedule_Revised_9-3-19.pdf PDF
Summary_of_Changes_-_Amendment_1.pdf PDF
Amendment_01_--_FA462619RA015.pdf PDF
Attch_9_Subcontractor_Consent.doc DOC document
Attch_4_Spill_Bucket_Drawing_Revised_8-6-19.pdf PDF
Attch_10_Sections_L&M_Replace_UST_Spill_Buckets.pdf PDF
Attch_8_Past_Performance_Questionaire.docx DOCX document
Attch_3_Schedule_of_Drawings.pdf PDF
Solicitation_-_FA462619RA015.pdf PDF
Attch_2_Submittal_Schedule.pdf PDF
Attch_6_Installation_Perimeter_Access_Ctrl.pdf PDF
Attch_5_Special_Contract_Requirements.pdf PDF
Attch_11_Wage_Determinations_UST_Spill_Buckets.pdf PDF
Attch_1_Technical_Specification_Revised_8-22-19.pdf PDF
Attch_7_Bid_Schedule_Repl_UST_Spill_Buckets.xls XLS spreadsheet
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4626-19-R-A015: Replace UST Spill Buckets

Questions and Answers:

Q6: Reference Attachment 10, pg. 10, Section M, Part 1, Subfactor 1: This paragraph states that the Site Superintendent must have 3 years experience “in each of the identified past performance sub-factors (1 and 2)”. We find no sub-factor 1 or 2 identified in Factor 3. Please clarify which are the (sub-factors 1 and 2) referenced in Factor 3 (Past Performance) that the Site Superintendent must demonstrate experience with.

A6: Attachment 10, pg. 10, Section M, Part 1, Subfactor 1 has been edited to read:

Subfactor 1: Site Superintendent Qualifications and Experience

Offeror must submit resume for site superintendent that shows a minimum of 3 years of experience installing, repairing and removing USTs.

ACCEPTABLE – Offeror has provided a full, structured and detailed resume for the project's site superintendent along with all corresponding qualifications and experience.

UNACCEPTABLE – Offeror has not provided a detailed resume for the project's site superintendent along with all required certifications and experience.

Reference: Amendment 03

Q7: Reference Attachment 10, Pg. 10, Section M Subfactor 2: Clarify if the prime contractor is required to have the (UST) License if they will not install the spill buckets. Will it be acceptable for the installing subcontractor to have the UST License in lieu of the prime contractor?

A7: At least part of the offeror’s team (prime or sub) must be licensed by the Department of Environmental Quality (DEQ) to install, repair and remove USTs in the state of Montana.