Attachment 2 FA4626-19-R-A015
AF Form 66
02: 000510_AC01_00_90-
Replace UST Spill Buckets Submittal Schedule (15
SS-1 of 2
SCHEDULE OF MATERIALS SUBMITTALS
Project Number
NZAS 19-6009
Project Title:
Replace UST Spill Buckets
Solicitation/Contract No.
FA4626-19-R-A015
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR
LI
N E
N U
M
BE
R
ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL
Number of Copies Required
E Q
U
IR
D
SU
B M
IS
SI
O N
D
AT
(B Y
C O
N T
R
AC
TO
R
D
AT
E R
E C
E
IV
E D
I
CO
T
R
AC
T
IN
G
E
T O
C
IV
IL
G
IN
E E
R
T U
R N
S U
SP
E
SE
BM
IT
TA
L N
U M
B E
S
DATE CONTRACTOR NOTIFIED
T
R
AC
T O
SU
B
M
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
REMARKS
CE
R
TI
FI
CA
T
IO
N
O F
CO
M
PL
IA
N C
SH
P D
R
AW
IN
G
S
SA
M
PL
E
S
CO
LO
R S
E
LE
C T
IO
M
AN
U
FA
CT
U
R E
'S
C
O M
M E
N D
AT
I
O N
S
M
AN
U
FA
CT
U
R E
W
AR
R
AN
T
CA
AL
O
G D
AT
A
O
PE
R
AT
ST
R
U C
T
IO
N S
N O
T
IF
IC
AT
H
APPROVED
DIS-
DIVISION 01-GENERAL REQUIREMENTS
1 01 00 00 3.8.1 Work Notification/ Weekly Schedule 1 Tues
PSW
Shall be submitted EVERY Tuesday of the week prior to the scheduled work week
2 01 00 00 3.13.2 Quality Control Plan 4 10-days
ANTP
3 01 00 00 3.16.1 As-Built Field Data 1 3-days
AFI
4 01 00 00 3.16.5 As-Built Contract Drawings/AutoCad 3 PTFP
5 01 00 00 3.22 Work Clearance Request (AF Form 103) 4
6 01 00 00 3.25 Nuclear Densometers 1
7 01 00 00 3.3.1 Schedule of Material Submittals 4
8 01 00 00 1.5 Missile Field Entry Authority List (EAL) 1 21-days
PSW
9 01 36 00 1.2 Environmental Permits 1 5-days
10 01 36 00 1.7 Hazardous Materials (Attachment 5) 1 30-days
11 01 36 00 1.11.6 Waste Management Plan (Attachment 1) 1
PTFA
12 01 36 00 1.12.5 Recycled Material Use Report (Attachment 4) 1
PTFA
13 01 36 00 Monthly Report of Solid Waste Disposal and Diversion (Attachment 5) 1 Monthly
DIVISION 03 - CONCRETE
14 03 30 00 1.3 - Cast in place concrete - Product Data 4 PSW
15 03 30 00 2.3 - Mix Design 4 15-days
16 03 30 00 2.4.3 - Grout 4
17 03 30 00 2.8 - Fasteners - Product Data 4
DIVISION 7 - THERMAL and MOISTURE PROTECTION 28 07 90 00 1.3 Joint Sealers Product Data 4 15-days
29 07 90 00 1.3 Joint Sealers Installation Instructions
4 15-days
Attachment 2 FA4626-19-R-A015
AF Form 66
02: 000510_AC01_00_90-
Replace UST Spill Buckets Submittal Schedule (15
SS-2 of 2
SCHEDULE OF MATERIALS SUBMITTALS
Project Number
NZAS 19-6009
Project Title:
Replace UST Spill Buckets
Solicitation/Contract No.
FA4626-19-R-A015
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR
LI
E
N U
M
BE
ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL
Number of Copies Required
Q
U
IR
B M
IS
SI
O N
D
(B
C O
N T
R
AC
TO
R
D
AT
E R
E C
E
IV
E D
I
T
R
AC
T
E
T O
C
IV
IL
G
IN
E E
R
T U
R N
S U
SP
E
SE
BM
IT
TA
L N
U M
B E
S
DATE CONTRACTOR NOTIFIED
T
R
AC
T
SU
B
M
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
REMARKS
CE
R
TI
FI
CA
T
IO
N
O F
CO
M
PL
IA
N C
SH
P D
R
AW
IN
G
S
SA
M
PL
E
S
CO
LO
R S
E
LE
C T
M
AN
U
FA
CT
U
R E
C
O M
M E
N D
AT
I
O N
S
M
AN
U
FA
CT
U
R E
W
AR
R
AN
CA
AL
O
G D
AT
A
O
PE
R
AT
ST
R
U C
T
IO
N S
N O
T
IF
IC
AT
H
DIS-
DIVISION 31 - EARTHWORK
30 31 00 00 1.4 Test Reports 4 ATT
31 03 00 00 2.3 Filter Fabric 4 10-days
DIVISION 33 – SPILL BUCKET, DROP TUBE, & VAVLE
32 33 52 10 1.3 Contractor Qualifications 4 10-days
PSW
33 33 52 10 1.3 Personnel License 4 10-days
PSW
34 33 52 10 2.2 Spill Bucket 4 10-days
PSW
35 33 52 10 2.3 Overfill Prevention Valve 4 10-days
PSW
36 33 52 10 2.4 Stainless Steel Pipe 4 10-days
PSW
37 33 52 10 2.5 Piping Components 4 10-days
PSW
38 33 52 10 2.6 Rigid Polyethylene Pipe, clip angles, bolts, nuts, & washers. 4 4 10-days
D - Days PBC - Prior to Beginning Construction PFI - Prior to Final Inspection
AFI - After Final Inspection PTFP- Prior to Final Payment PPC - Prior to Project Completion
ANTP - After Notice to Proceed PSW - Prior to Start Work PT - Prior to Testing
ATT - After Test is Taken PTFA - Prior to Final Acceptance SRO- After Each Occurrence