13SubmittalSchedule_DemoProj_Atch11.doc

DOC document 140 KB Posted

Attached to
Simplified Base Engineering Requirements (SABER) Construction Services for Malmstrom AFB Federal contract opportunity
Solicitation number
FA4626-08-R-0001
Issued by
Department of the Air Force Global Strike Command

About this file

SABER Submittal Schedule

View the file

Other files for this federal contract opportunity

Other files attached to Simplified Base Engineering Requirements (SABER) Construction Services for Malmstrom AFB, newest first.
File Type Posted
Synopsis for Award B-5.doc DOC document
SABER08R0001Amend0002.doc DOC document
01 SABERSF 30 08R0001Amend0001.doc DOC document
03 Spec INDEX.DOC DOC document
04 SABER Contract Specifications.doc DOC document
02 SABER RFP 08R0001Amend0001.doc DOC document
05 SABER SOW 8 Apr 08 Atch 2.docm DOCM document
Questions and Answers.doc DOC document
SiteVisitMtgMinutes.pdf PDF
1435 00-0000-a5Atch12.zip ZIP file
12BlankEstSheets_DemoProj_atch10.pdf PDF
10HistoricalData_Atch8.xls XLS spreadsheet
06WageDetMT070001_HeavyAtch4.doc DOC document
02SABER08R0001.doc DOC document
01TOC_Solicitation.docm DOCM document
05WageDetMT070005_Building_Atch3.doc DOC document
07WageDetMT070002_Highway_Atch5.doc DOC document
04SABERSOW_24Oct07_Atch2.doc DOC document
03REVISEDSABERSPECS1FEB08Atch1.pdf PDF
1435 DrawingSet_Atch12.zip ZIP file
09PastPerformanceQuestionaire_Atch7.docm DOCM document
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 11 FA4626-08-R-0001

SUBMITTAL SCHEDULE

PROJ / W.O. #: _NZAS 00-0000________ DESC: __Construct Housing Management Office_________________________________ D.O. #: 1000_

1
2
3
4
5
6
7
8
9
10
11
SUB NO.
SUB ID. NO.
SPEC PARA. or DRWG.NO.
TYPE

OF

SUBMITTAL

DESCRIPTION OF MATERIAL
NO. OF SUB DAYS
DATE

REC FR

CONTR

DATE

TO

CECS

DATE

RET TO

LGCK

APRV’D

or

DISAPRV’D

DATE RETURNED

TO CECS

REMARKS

1
01010

22.0 Drawings &

Diskettes

Contractor Design Drawings
PTSW
2
01010

23.0

Drawings
Shop Drawings
PTSW
3
01010

24.0

Drawings
As-built Field Data

(Red Lined Drawings)

5 CD

PTFI

4
01010

24.0

Drawings & Diskettes
Final As-built
PTFP
5
01010

25.0

Manuals
O & M Manuals
5 WD
6
01010

28.0

DD 1354 Form
Transfer & Acceptance of Military Real Property Form
PTFP
7
01010

4.0

AF 103 Form
Work Clearance Request

(Dig Permit)

5 WD PTSW

NA
8
01010

6.0

Letter
D.O. Specific Quality Control Plan
PTSW
9
01010

7.0

Telephone Notification
Start/Stop Work
5 WD PTSW

Does not require a AF Form 3000

10
01010

13.0

Telephone Notification
Environmental Spills
Immediate

Does not require a AF Form 3000

11
01010

16.0

Letter
Utility Outage
7 WD

PTO

NA
12
01010

30.0

List
Itemized List of Salvage Items for Turn-in to DRMO
3 WD prior to turn-in
NA
13
01010

37.0

List
Secured Entry Area Employee List
10 CD

PTSW

14
01010

27.0 Letter

Notification

Maintenance Training for Installed Equipment
10 WD
15
01010

8.0

Notification
Notice of Final Inspection
14 CD PTCW

ACA

After contract award

BMD

Before material delivery

PTFA

Prior to final acceptance

AEO

After each occurrence

CD

Calendar days

PTFI

Prior to final inspection

AFA

After final acceptance

EWD

Each work day

PTFP

Prior to final payment

AN

Advance notification

PTCA

Prior to contract award

PTND

Prior to notice date

ANTP

After notice to proceed

PTCW

Prior to completing work

PTO

Prior to outage

AWC

After work completed

PTD

Prior to delivery

PTSW

Prior to starting work

PTDA

Prior to Delivery order Award

WD

Work days

SUBMITTAL SCHEDULE

PROJ / W.O. #: _NZAS 00-0000________ DESC: __ Construct Housing Management Office _________________________________ D.O. #: 1000_

1
2
3
4
5
6
7
8
9
10
11
SUB NO
SUB ID. NO.
SPEC PARA. or DRWG.NO.
TYPE

OF

SUBMITTAL

DESCRIPTION OF MATERIAL
NO. OF SUB DAYS
DATE

REC FR

CONTR

DATE

TO

CECS

DATE

RET TO

LGCK

APRV’D

or

DISAPRV’D

DATE RETURNED

REMARKS

Mfg Lit
Metal studs
PTSW
Mfg Lit
Insulation
PTSW
Mix Design
Concrete Mix Design
PTSW
Mix Design
Asphalt Mix Design

PTSW

Mfg Lit
Doors
PTSW
Mfg Lit
Door hardware
PTSW
Mg Lit
Thresholds
PTSW
Color Sample
Flashing & soffet
PTSW
Color Sample
Paint
PTSW
Mfg Lit
Roof Shingles
PTSW
Mfg lit
Air conditioning unit
PTSW
Mfg Lit
Heating unit
PTSW
Mfg Lit
Electrical Panels
PTSW
Mfg Lit
Conduit

PTSW

Mfg Lit
Breakers
PTSW
Mfg Lit
Light fixtures
PTSW
Mfg Lit
Water Heater

PTSW

Mfg Lit
Duct
PTSW
Mfg Lit
Mechanical vents
PTSW

SUBMITTAL SCHEDULE

PROJ / W.O. #: _NZAS 00-0000________ DESC: __ Construct Housing Management Office _________________________________ D.O. #: 1000_

1
2
3
4
5
6
7
8
9
10
11
SUB NO.
SUB ID. NO.
SPEC PARA. or DRWG.NO.
TYPE

OF

SUBMITTAL

DESCRIPTION OF MATERIAL
NO. OF SUB DAYS
DATE

REC FR

CONTR

DATE

TO

CECS

DATE

RET TO

LGCK

APRV’D

or

DISAPRV’D

DATE RETURNED

REMARKS

Mfg Lit
Brick Veneer
PTSW
Mfg Lit
Transformer
PTSW
Mfg Lit
Cable Tray
PTSW
Mfg Lit
Structural Steel
PTSW
Mfg Lit
CMU Block
PTSW
Mfg Lit
Carpet
PTSW
Mfg Lit
Floor Tile
PTSW
Mfg Lit
Gypsum board
PTSW
Mfg Lit
Windows
PTSW
Mfg Lit
Water Closets
PTSW
Mfg Lit
Sinks
PTSW
Mfg Lit
Cabinets
PTSW
Mfg Lit
Ceiling system and tile
PTSW
Mfg Lit
Skylight

PTSW

Mfg Lit
Pipe
PTSW

MALMSTROM FORM 124, OCT 92 PREVIOUS EDITION WILL BE USED

Submittal Schedule_Demo Proj_Atch 11