This document is a Summary of Work (Section 01 11 00) for a HVAC repair project at Building 1907A on Joint Base McGuire/Dix/Lakehurst. The project involves comprehensive HVAC system upgrades and replacement, specifically focusing on the SIPR room's cooling infrastructure. Key work elements include removing existing mini-split air conditioning units, installing new 32 kW Liebert units with copper piping, installing a new 35-ton Trane stand-alone low ambient temperature chiller with specific manufacturer requirements, constructing a new concrete equipment slab, installing surface mounted bollards, and adding a new chiller pump in the mechanical room.
The project requires extensive electrical work, including installing new branch circuit breakers, disconnect switches, and wiring for the Liebert computer cooling unit and chiller. Additional requirements include installing a glycol feeder, insulating all piping, sealing penetrations, connecting the new chiller to the backup generator, implementing a comprehensive control system using JACE 9000 and Niagara framework, and providing detailed monitoring and alarm capabilities. The period of performance is 365 days, and the contract will be awarded using a Best Value Tradeoff process, with past performance weighted more heavily than price. The contractor must provide a preliminary project schedule, minimize facility disruption, and submit As-Built/Record drawings upon project completion.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 11 00 - 1
PTFL 22-1012 BLDG 1907A
DIVISION 1
GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PROJECT 22-1012 B1907A
REPAIR HVAC AT NCC
PERIOD OF PERFORMANCE ____365___ DAYS
PART 1 GENERAL
1. DESCRIPTION OF SERVICES. The work consists of furnishing all labor, materials, equipment, transportation, fuel, supervision, and permits required for the HVAC repair at BLDG 1907A, on Joint Base McGuire/Dix/Lakehurst. The project shall replace the existing mini-split air conditioning units in the SIPR room. The project shall comply with all MACC IDIQ requirements. The work includes but is not limited to:
NOTE: Contractor to coordinate access into SIPR with user. Notification shall be given two weeks in advance.
1.1 The removal of two (2) mini-split units and their respective outdoor condenser units. Remove and dispose of all piping, wiring, and disconnect switches associated with the existing mini-split units and outdoor A/C units for the SIPR room.
1.2 All unused conduits and abandon material found shall be removed.
1.3 Install new chilled water 32 kW Liebert units. Install new copper piping. New unit shall be in the same chilled water loop. Existing Liebert units are connected to the centralized chiller water plant in B1908.
1.4 Install a new heat exchanger in the mezzanine of B1908 Mechanical room.
1.5 Install a new 460 208v/60hz/3-phase 35-ton Trane stand-alone extreme low ambient temperature chiller.
The chiller will serve as a redundant and as an emergency system. The chiller shall receive the following from the manufacture: a disconnect switch, single point power connection, BACNet Interface, insulation for high humidity/low evap temp, neoprene vibration isolator, soft start capability, and freeze protection.
1.5.1 Contractor shall install one (1) 6” thick slab for new chiller, using 4000 PSI air-entrained concrete.
carefully sawcut 2” deep, chip out concrete 2” thick, and scarify the concrete surface to ¼” amplitude. Apply a concrete bonding agent to the scarified surface and install the reinforced concrete slab for new HVAC equipment, slope top surface away from building. The contractor shall verify the necessary concrete slab size for the equipment to be installed. Location shall be along the wall of the existing outdoor unit. Concrete slab shall be at least 6” larger than equipment footprint.
1.5.2 Install four (4) surface mounted bollards.
1.6 Install a new chiller pump in the Mechanical room of B1907A. The pump shall have isolation valves.
1.6.1 Contractor shall install new copper piping to connect to all Liebert system loop. Piping will be required to penetrate through CMU wall. Piping shall be supported properly and shall have all the necessary components to make a working system (strainers, isolation valves, air vent, air separator, 01 11 00 - 2 and etc.).
1.6.2 Install new temperature and pressure gauges
1.6.3 Contractor shall submit shop drawing of the system.
1.6.4 The emergency backup system shall be tested, adjusted and balance.
1.7 Contractor shall install a glycol feeder in the system.
1.8 All piping shall be insulated with 2” fiberglass insulation with all service jackets. Exterior piping shall receive metal jacketing.
1.9 All penetration shall be properly sealed and fireproofed.
1.10 The new chiller shall be connected to the building backup generator to allow continue operation during electrical outages. The chilled water loop shall have automatic change-over valves to isolate the NCC.
Automatic change-over valves shall be connected to the backup generator panel.
1.11 All mechanical system and piping shall be identified and labeled.
1.12 Provide the required electrical service to the new HVAC equipment. Label and identify the branch circuit breakers in the respective panels. Refer to electrical section for detail.
1.13 Contractor shall provide temporary cooling for the server room if necessary. Server room are to maintain a temperature range of 64°F - 80°F and a relative humidity of 40%-50%.
CONTOLS
1.14 The contractor shall provide and install JACE 9000 running on Niagara 4.4 or later if no existing
Controls or Jace installed. Contractor shall submit a shop drawing of the controls.
1.15 Control and monitoring should include the following:
(a) All Liebert Units
(b) Backup chiller
(c) Pumps
(d) Supply and return water temperature of heat exchanger
(e) Indoor temperature sensor
(f) Supply and return temperature of heat exchanger
1.16 Contractor shall provide and install all BACnet compatible equipment controller (MS/TP) to integrate with JACE front end. All controllers shall be the same manufacture.
1.17 Integration of field control networks using the Niagara Framework Engineering Tool. Must be fully programmable using the Niagara Framework Engineering Tool. Trending using Niagara History service and Niagara Trend log objects – contractor to provide trending for each device.
1.18 Unrestricted interoperability license and a Niagara Compatibility Statement (NiCS) that follows the Tridium Open NiCS Specification. Note that this will result in the following entries in the license file:
(a) accept.station.in="*"
(b) accept.station.out="*"
(c) accept.wb.in="*"
01 11 00 - 3
(d) accept.wb.out="*"
1.19 Scheduling – contractor to provide global and individual scheduling.
1.20 Alarm Generation and routing – contractor to provide high and low temperature and humidity alarm, boiler alarm and chiller alarm. Alarm will be routed to the JBMDL N4 Supervisor.
1.21 Configuration of integrated field control system using the Niagara Framework. Engineering Tool when supported by the field control system.
1.22 One port compatible with the field control system to be integrated. Embedded operating system.
1.23 Provide access to field control network data and supervisory functions via web interface and support a minimum of 16 simultaneous users
1.24 Provide government/end user full access to the controller to include platform and station access/passphrase.
1.25 Provide Graphical displays consisting of all mechanical equipment for the Liebert system
1.26 Provide and install CAT 6A network cable from JACE to the facility network switch, set up 1 port with government provided IP address. Second port will be set up with default IP address for service access.
1.27 Contractor to coordinate with government to send JACE station to the main supervisor. IP address, username and password will be provided on site after the JACE for each building is completed and accepted.
1.28 IP addresses and Ethernet MAC addresses as applicable for each piece of Control Hardware.
ELECTRICAL WORK
A. Chiller:
1. Provide a 3P-225A(min) branch circuit breaker in place of 3P-100A Temporary Chiller branch circuit breaker in existing 1907 RED Panel, 400A, 208V, 3phase Eaton Power Panel in B1907A Mechanical Room. Alternatively, provide the above 3P-225A branch circuit breaker in existing space in place of any spare breaker in the Power panel. The kAIC of 3P- 225A Branch circuit breaker shall be same as that of the panel. Consult Eaton for recommended breaker type.
2. Provide wiring between the power panel and single-point power connection factory installed NEC disconnect switch on-board of chiller. Wiring shall be 3-2 4/0, #4G; 2-1/2” C. Conduit shall be EMT indoors, GRS and weather-tight metallic flexible for outdoors and PVC Schedule 40 for underground applications. Provide trenching, backfill, sand cushion, warning tape and restoration of paved areas as required. Core drill though walls as required including fireproofing wall penetrations.
B. Liebert Computer Cooling Unit:
1. Provide a 3P-40A(min) branch circuit breaker in place of an existing spare branch circuit breaker or existing space in existing PP-1 1907 RED Panel, 100A, 208V, 3phase Eaton Power Panel or in existing 1907 RED Panel, 400A, 208V, 3phase Eaton Power Panel B1907A Mechanical Room.
The kAIC Branch circuit breaker shall be same as that of the panel. Consult Eaton for recommended breaker type.
2. Provide a wall-mounted enclosed 3P-40A non-fused NEC disconnect switch for the Liebert unit
01 11 00 - 4
3. Provide wiring between the power panel NEC disconnect and from there to the Liebert unit. Wiring shall be 3#8, #12G; 2” C. Conduit shall be EMT indoors and metallic flexible conduit for equipment connection. Core drill though walls as required including fireproofing wall penetrations.
C. General:
1. All work shall conform to Electrical IDIQ Technical specifications.
2. Provide grounding/bonding as per NEC requirements
3. Provide all labelling and revised panel directories. All loads shall have labels indicating the source of power: Power Panel designation, location of panel and branch/feeder circuit breaker in the power panel.
4. Conduct all tests and submit records of test data as required.
D. Electrical shutdowns:
1. All shutdowns shall be conducted on off-duty hours (Saturdays, Sundays, or from 1700H to 0600H on weekdays) and at the convenience of the Government.
2. The contractor shall give a 2-week notice (minimum) to the Government prior to any shutdown.
2. LOCATION: The work is located at JBMDL (Dix campus) as indicated on the project plans and described in the project documents.
3. All interior treatments shall be in accordance with the current guidance in the installation facility standards (IFS) unless otherwise specified in the scope of work.
4. Interpretation of Drawings and Specifications:
4.1 It shall be understood that specifications and drawings are complementary and are to be taken together for a complete interpretation of the work. Anything mentioned in the specifications and not shown on the drawings or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of a difference between the drawings and specifications, the specifications shall govern. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall promptly be submitted to the CO who shall, in consultation with CE, promptly render a decision in writing. Normally, the items of higher standard shall govern. See FAR 52.236-21.
4.2 No exclusions from, or limitations in, the language used in the drawings or specifications shall be interpreted as meaning that the appurtenances or accessories necessary to complete a required system or item of equipment are to be omitted.
4.3 The drawings of necessity utilize symbols and schematic diagrams to indicate various items of work. Neither of these have any dimensional significance nor do they delineate every item required for the intended installations. The work shall be installed, in accordance with the diagrammatic intent expressed on the electrical and mechanical drawings, and in conformity with the dimensions indicated on final architectural and structural working drawings and on equipment shop drawings.
4.4 No interpretation shall be made from the limitations of symbols and diagrams that any elements necessary for complete work are excluded.
4.5 Certain details appear on the drawings which are specific with regard to the dimensioning and positioning of the work. These details are intended only for the purpose of establishing general
01 11 00 - 5 feasibility. They do not prevent field coordination for the indicated work.
4.6 Information as to the general construction of a facility shall be derived from existing structural and architectural drawings and specifications only as available at the Base Civil Engineering print room.
4.7 The use of words in the singular shall not be considered as limiting where other indications denote that more than one item is referred to.
5. The Contractor shall maintain overall cleanliness of the site at the end of each work day. This daily cleanup will not relieve the Contractor from responsibility of the final cleanup before acceptance of all work. After completion of all activities, the Contractor shall be required to clean the area being worked on by removing all dirt, trash, and debris resulting from their work and shall restore the area to its original state of cleanliness. The Contractor shall dispose of all debris at an off post site.
Federal, State and Local laws and regulations regarding hauling and disposal shall apply.
6. Proper, adequate and proficient supervision shall be provided by the Contractor throughout all phases of the work.
7. Work performed under this contract could be accomplished on both well-traveled and semi traveled streets and major roads, throughout the base, to include training areas, and in or around buildings and other training and base facilities.
8. The Contractor is obligated to verify all measurements and specification requirements during an on-site visit prior to providing his proposal for the work. The Contractor accepts responsibility for any issues that arise due to his lack of attendance at site visits or choosing to not conduct the site visit prior to providing a proposal for the work.
9. Fire Prevention. The Contractor's operations shall comply with all requirements of the Installation Fire Prevention Standards, Air Force, Army and Navy Regulations as applicable, most current issue of the National Fire Codes, and the Fire Department which is Authority Having Jurisdiction (AHJ).
Open flame, hot work requires prior approval of the Fire Department of AHJ.
10. It shall be the Contractor's responsibility to follow the manufacturer's recommendations and upgrade all construction in accordance with the applicable regulation. Any part of construction not performed in accordance with the applicable regulation shall be repaired or replaced by the Contractor at no additional cost to the Government.
11. Any inspection for this work by any DOD personnel shall not in any way be interpreted as waiving the Government’s requirement that the work product(s) be fit for its intended purpose. Government inspections do not in any way constitute acceptance of work quality or fitness until the final acceptance inspection is made.
12. Contractor shall attend Pre-Bid, Pre-Construction and monthly project meetings as required or determined to be necessary by the specifications or Contracting Officer
13. TASK ORDER AWARD: BEST VALUE TRADEOFF PROCESS: This project will be awarded based on the Best Value Tradeoff criteria. The evaluation factors in the tradeoff decision are past performance and price. Past performance is weighted more important than price. Award will be made to the responsible offeror whose proposal conforms to all solicitation requirements and provides the best value to the Government. The proposal selected shall meet the project requirements and shall include a proposed preliminary project schedule that shows an understanding of the requirements to complete the project in the allotted time. The Contractor’s proposal shall include the following in sufficient detail:
01 11 00 - 6
PRELIMINARY PROJECT SCHEDULE: Preliminary project schedule showing the main actions required to perform the work. Contractor shall use the AF IMT 3064 Project Progress Schedule Form.
The project schedule shall show the work is to be done in an occupied facility and minimize impact to users of the facility. Schedule shall show the associated duration for each main task. Schedule shall show that the time requirements of the SOW are met. The schedule shall also show the submissions of updated schedules (look ahead schedules) every 30 days.
PRICE: The offeror’s price proposal and price breakdown will be evaluated for reasonableness, balance, and total price. Contractor is to provide a full breakdown of the cost.
14. At the conclusion of the work and prior to final payment, Contractor shall provide As-Built/Record drawings for all work performed in accordance with the project specifications and respective scope(s) of work.
END OF SECTION 01 11 00