Solicitation Amendment FA448424R00260001 SF 30.pdf

PDF 1 MB Posted

Attached to
FY25 Underground Utilities IDIQ Federal contract opportunity
Solicitation number
FA448424R0026
Issued by
Department of the Air Force Air Mobility Command

About this file

This document is a Standard Form 30 (SF 30) Amendment of Solicitation/Modification of Contract for the FY25 Underground Utilities IDIQ contract at Joint Base McGuire-Dix-Lakehurst (JB MDL) in New Jersey. The amendment, numbered 0001 and effective 22 Apr 2025, adds Attachment J-13 Seed Project - Drawings Set.pdf to the list of attachments. The solicitation covers infrastructure repair and construction services including water, sanitary sewer, and stormwater systems; lift stations; water wells; water and sewer treatment plant improvements; horizontal and vertical concrete work; asphalt paving; excavation; and related civil engineering tasks. The amendment does not change the solicitation's receipt date and requires offerors to acknowledge the amendment prior to the specified submission deadline.

View the file

Other files for this federal contract opportunity

Other files attached to FY25 Underground Utilities IDIQ, newest first.
File Type Posted
Att J-15 Underground Utilities Seed Project Questions 02.pdf PDF
Att J-14 Underground Utilities Seed Project Questions 01 Rev 01.pdf PDF
Solicitation Amendment FA448424R00260003 SF 30.pdf PDF
Att J-14 Underground Utilities IDIQ Seed Project Q and A 01.pdf PDF
Att C-2_Ordering Procedures Rev 01.pdf PDF
Solicitation Amendment FA448424R00260002 SF 30.pdf PDF
Att J-13 Seed Project - Drawings Set.pdf PDF
Solicitation Amendment FA448424R00260001 SF 30.pdf PDF
Solicitation Amendment FA448424R000260001 SF 30.pdf PDF
Underground Utilties Seed Project Sign In-Sheet.pdf PDF
Attch J-13 Seed Project - Repair Switchgear in Sub3 Area Reference Drawings.pdf PDF
Att J-1_Past Performance Letter and Questionnaire.docx DOCX document
Att J-3_Wage Determinations_Burlington and Ocean_Highway_3.14.25.pdf PDF
Att J-4_ Security Forces Appendix.pdf PDF
Att J-6_Anti-Terrorism Awareness Guide for Contractors.pdf PDF
Att J-5_ Medical Statement.pdf PDF
Att J-7_Section L and M.docx DOCX document
Att J-9_Seed Project Underground Utilities Drawing Set.pdf PDF
Att J-10_Seed Project Reference Drawings (B-1817).pdf PDF
Att J-11_Seed Project Statement of Work.pdf PDF
Att J-12_Seed Project Schedule of Material Submittals.pdf PDF
Solicitation - FA448424R0026.pdf PDF
Att C-1_Statement of Work.docx DOCX document
Att C-2_Ordering Procedures.pdf PDF
Att J-2_ Environmental Compliance Statement.pdf PDF
Att J-8_Seed Project Bid Schedule.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section J - List of Attachments

Header Miscellaneous Text (Modified):

C-1 Statement of Work

C-2 Ordering Procedures

J-1 Past Performance Letter & Questionnaire

J-2 Environmental Compliance Statement

J-3 Wage Determinations

J-4 Security Forces Appendix

J-5 Medical Statement

J-6 Anti-Terrorism Awareness Guide

J-7 Sections L&M

J-8 Seed Project Bid Schedule

J-9 Seed Project Underground Utilities Drawing Set

J-10 Seed Project Reference Drawings

J-11 Seed Project Statement of Work

J-12 Seed Project Schedule of Material Submittals

J-13 Seed Project - Drawings Set.pdf

FA448424R00260001

SUMMARY OF CHANGES
List of Attachments
IDCode: J
Page: 1
Pages: 2
AmendNo: 0001
EffDate: 22 Apr 2025
ReqNo:
ProjNo: 001
IssCode: FA4484
AdmCode:
IssuedBy: FA4484 87 CONS PK

BLDG 2402 CP 609 754 2413, 2402 VANDENBERG AVE

JBMDL, NJ 08641

UNITED STATES

Sean Burney, Email: sean.burney.1@us.af.mil Telephone: 609-754-4861 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA448424R0026
SolDate: 04 Apr 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of this amendment is add Att J-13 Seed Project - Drawings Set.pdf.
ContNameTitle:
CoNameTitle: DANA M. WRIGHT
ContDate:
CODate: 22 Apr 2025

File details come from the government source that posted it. Updated .