This document is a Questions and Answers (Q&A) file for the FY25 Underground Utilities Indefinite Delivery/Indefinite Quantity (IDIQ) contract at Joint Base McGuire-Dix-Lakehurst (JBMDL) in New Jersey. The Q&A covers five primary areas: permits and approvals, schedule coordination and utilities, fencing, roadway restoration, and engineering design drawings. Key details include permit requirements (noting most are not needed for this specific project), government review timelines (14-30 days for submittals), and specific technical specifications for project execution.

Notable technical requirements include temporary security fencing meeting UFC 4-022-03 and AFI 31-101 standards, roadway restoration using specific HMA mix designs, and contractor responsibilities for developing engineering drawings. The project has a 180-day Period of Performance, and the government will issue Requests for Proposal (RFPs) for specialized tasks like utility relocation or groundwater treatment if needed. The contractor must submit drawings as specified in the submittal register, including pre-construction and As-Built drawings, following Section 01 33 00 of the IDIQ Specifications for submittal standards.

View the file

Other files for this federal contract opportunity

Other files attached to FY25 Underground Utilities IDIQ, newest first.
File Type Posted
Att J-14 Underground Utilities Seed Project Questions 01 Rev 01.pdf PDF
Solicitation Amendment FA448424R00260003 SF 30.pdf PDF
Att C-2_Ordering Procedures Rev 01.pdf PDF
Att J-14 Underground Utilities IDIQ Seed Project Q and A 01.pdf PDF
Solicitation Amendment FA448424R00260002 SF 30.pdf PDF
Solicitation Amendment FA448424R00260001 SF 30.pdf PDF
Att J-13 Seed Project - Drawings Set.pdf PDF
Solicitation Amendment FA448424R00260001 SF 30.pdf PDF
Solicitation Amendment FA448424R000260001 SF 30.pdf PDF
Attch J-13 Seed Project - Repair Switchgear in Sub3 Area Reference Drawings.pdf PDF
Underground Utilties Seed Project Sign In-Sheet.pdf PDF
Att J-12_Seed Project Schedule of Material Submittals.pdf PDF
Att J-5_ Medical Statement.pdf PDF
Att J-7_Section L and M.docx DOCX document
Att J-9_Seed Project Underground Utilities Drawing Set.pdf PDF
Att J-10_Seed Project Reference Drawings (B-1817).pdf PDF
Att J-11_Seed Project Statement of Work.pdf PDF
Att J-1_Past Performance Letter and Questionnaire.docx DOCX document
Att J-3_Wage Determinations_Burlington and Ocean_Highway_3.14.25.pdf PDF
Att J-4_ Security Forces Appendix.pdf PDF
Att J-6_Anti-Terrorism Awareness Guide for Contractors.pdf PDF
Solicitation - FA448424R0026.pdf PDF
Att C-1_Statement of Work.docx DOCX document
Att C-2_Ordering Procedures.pdf PDF
Att J-2_ Environmental Compliance Statement.pdf PDF
Att J-8_Seed Project Bid Schedule.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA448424R0026

Underground Utilities Solicitation and Seed Project Questions – Part 2

1. Permits and Approvals

1.1 Can the government confirm typical average

timelines for approvals from:

-Burlington County and Ocean County Soil Conservation Districts?

-NJDEP Bureau of Water System Engineering?

-BCSCD and OCSCD permits are required for disturbances over 1 AC. This project will not have a disturbance over 1 AC so permits are not required.

Otherwise, typical time for SCD permits is approximately 30 days.

-NJDEP Water Permits are required for lines over 3,000 LF. This project is under the 3,000 LF so the permit is not required. Otherwise, typical time for NJDEP permits is approximately 90 days.

1.2 For permit submission, will preliminary design

drawings be acceptable, or must full final designs be completed prior to submission?

-As per the above, permits are not required for this project. Otherwise, permit submissions require final designs.

1.3 For submittal reviews (e.g., materials, drawings, permits), is there a maximum government review time (e.g., 14 calendar days) to maintain schedule adherence?

-Submittal reviews have a max of 30 days for very large submittals. Submittals for this project should be completed within 14 days.

2. Schedule Coordination and Utilities

2.1 In the event dewatering becomes necessary and

PFAS is detected (per Task 7), will the contractor be compensated under a new modification for groundwater treatment and disposal?

-As per section 4.7.3 of the Supplementary Specifications, the Government with issue a Request for Proposal (RFP) to treat and dispose of contaminated groundwater.

2.2 If Option Items (Tasks 2–4) regarding the fire

service line are triggered after construction begins, will the contractor be eligible for time extensions?

-This work shall be completed within the Period of Performance (POP) for the project: 180 days.

2.3 If utilities not shown on drawings require

relocation, will that work be considered a change order and eligible for equitable adjustment, or is it at the contractor’s expense?

-The Government will issue an RFP to relocate utilities not shown on the drawings (if required). The Contractor shall submit a Request for Information (RFI) for any utilities encountered that are not shown on the drawings.

3. Fencing

3.1 For temporary fencing inside the airfield, are there

specific security or construction standards required (e.g., anti-climb fencing), or is standard 6-foot chain-link with screening acceptable?

-Temporary security fencing shall meet UFC 4-022-03 and AFI 31-101 and shall include barbed wire and mesh screening. The Contractor shall also refer to details shown in Section 6 of the Supplementary specifications.

4. Roadway Restoration

4.1 For roadway restoration, are there any specific

pavement material standards (e.g., NJDOT mix designs) beyond matching “existing”?

-HMA Restoration detail is shown on sheet T-3 of the IDIQ drawing set. For bidding purposes, contractors shall assume 8” of DGA, 6” of HMA base course (19M64) and 3” of HMA surface course (12.5M64).

5. Engineering Design Drawings

5.1 The SOW indicates that the contractor must

"develop engineering drawings" for permit applications and construction.

Can the government confirm that full engineering design drawings (stamped by a licensed professional engineer, if required) are expected to be prepared and submitted by the contractor as part of the deliverables for this project?

-Yes, they should be considered as part of the deliverables for the project as indicated on the Submittal register.

-If yes, can the government clarify if there are specific design format requirements (e.g., JBMDL CAD standards, sheet size, title blocks)?

-The Contractor shall follow Section 01 33 00 of the IDIQ Specifications for submittal standards.

-Are the drawings only required for permitting purposes, or will final pre-construction drawings also be required in addition to final As-Built drawings?

-Drawings are required as shown on the submittal register. The Contractor shall submit any drawings shown on the submittal register, including As-Built drawings.