2-3_13R0102-0002_Atch_1_SPECS_Section_32_12_10_BITUMINOUS_TACK_ _PRIME_COATS_08_APR_13.pdf
PDF 45 KB Posted
- Attached to
- Demolition of Base Buildings
- Solicitation number
- FA4427-13-R-0102
About this file
13R0102-0002 Atch 1 Specs Section 32 12 10 Bituminous Tack Prime Coats
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IDC FACILITY DEMOLITION
Travis AFB, CA
08 APR 2013
SECTION 32 12 10 Page 1
SECTION 32 12 10
BITUMINOUS TACK AND PRIME COATS
01/98
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION
OFFICIALS (AASHTO)
AASHTO T 40 (2002) Sampling Bituminous Materials
ASTM INTERNATIONAL (ASTM)
ASTM D 140 (2001) Sampling Bituminous Materials
ASTM D 2995 (1999) Determining Application Rate of
Bituminous Distributors
ASTM D 977 (2003) Emulsified Asphalt
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL
PROCEDURES:
SD-06 Test Reports
Sampling and Testing
Copies of all test results for bituminous materials, within 24 hours of completion of tests. Certified copies of the manufacturer's test reports indicating compliance with applicable specified requirements, not less than 30 days before the material is required in the work.
1.3 PLANT, EQUIPMENT, MACHINES AND TOOLS
1.3.1 General Requirements
Plant, equipment, machines and tools used in the work shall be subject to approval and shall be maintained in a satisfactory working condition at all times.
1.3.2 Bituminous Distributor
The distributor shall have pneumatic tires of such size and number to prevent rutting, shoving or otherwise damaging the base surface or other
SECTION 32 12 10 Page 2 layers in the pavement structure. The distributor shall be designed and equipped to spray the bituminous material in a uniform coverage at the specified temperature, at readily determined and controlled rates with an allowable variation from the specified rate of not more than plus or minus 5 percent, and at variable widths. Distributor equipment shall include a separate power unit for the bitumen pump, full-circulation spray bars, tachometer, pressure gauges, volume-measuring devices, adequate heaters for heating of materials to the proper application temperature, a thermometer for reading the temperature of tank contents, and a hand hose attachment suitable for applying bituminous material manually to areas inaccessible to the distributor. The distributor shall be equipped to circulate and agitate the bituminous material during the heating process.
1.3.3 Power Brooms and Power Blowers
Power brooms and power blowers shall be suitable for cleaning the surfaces to which the bituminous coat is to be applied.
1.4 WEATHER LIMITATIONS
Bituminous coat shall be applied only when the surface to receive the bituminous coat is dry. Bituminous coat shall be applied only when the atmospheric temperature in the shade is 50 degrees F or above and when the temperature has not been below 35 degrees F for the 12 hours prior to application.
PART 2 PRODUCTS
2.1 TACK COAT
Emulsified asphalt shall conform to ASTM D 977 or Grade SS-1h or CSS-1h.
2.2 PRIME COAT
Emulsified asphalt shall conform to ASTM D 977 or ASTM D 2397 or, Grade SS-1, SS-1h, CSS-1, or CSS-1h.
PART 3 EXECUTION
3.1 PREPARATION OF SURFACE
Immediately before applying the bituminous coat, all loose material, dirt, clay, or other objectionable material shall be removed from the surface to be treated. The surface shall be dry and clean at the time of treatment.
3.2 APPLICATION RATE
The exact quantities within the range specified, which may be varied to suit field conditions, will be determined by the Contracting Officer.
3.2.1 Tack Coat
Bituminous material for the tack coat shall be applied in quantities of not less than 0.05 gallon nor more than 0.15 gallon per square yard of pavement surface.
SECTION 32 12 10 Page 3
3.2.2 Prime Coat
Bituminous material for the prime coat shall be applied in quantities of not less than 0.15 gallon nor more than 0.40 gallon per square yard of pavement surface.
3.3 APPLICATION TEMPERATURE
3.3.1 Viscosity Relationship
Asphalt application temperature shall provide an application viscosity between 10 and 60 seconds, Saybolt Furol, or between 20 and 120 centistokes, kinematic. The temperature viscosity relation shall be furnished to the Contracting Officer.
3.3.2 Temperature Ranges
The viscosity requirements shall determine the application temperature to be used. The following is a normal range of application temperatures:
Emulsions
SS-1 70-160 degrees F SS-1h 70-160 degrees F CSS-1 70-160 degrees F CSS-1h 70-160 degrees F
*These temperature ranges exceed the flash point of the material and care should be taken in their heating.
3.4 APPLICATION
3.4.1 General
Following preparation and subsequent inspection of the surface, the bituminous coat shall be applied at the specified rate with uniform distribution over the surface to be treated. All areas and spots missed by the distributor shall be properly treated with the hand spray. Until the succeeding layer of pavement is placed, the surface shall be maintained by protecting the surface against damage and by repairing deficient areas at no additional cost to the Government. If required, clean dry sand shall be spread to effectively blot up any excess bituminous material. No smoking, fires, or flames other than those from the heaters that are a part of the equipment shall be permitted within 25 feet of heating, distributing, and transferring operations of bituminous material other than bituminous emulsions. All traffic, except for paving equipment used in constructing the surfacing, shall be prevented from using the underlying material, whether primed or not, until the surfacing is completed. The bituminous coat shall conform to all requirements as described herein.
3.4.2 Prime Coat
The prime coat will be required if it will be at least seven days before a the surfacing (Asphalt cement hot mix concrete)layer is constructed on the underlying (base course, etc)compacted material. The type of liquid asphalt and application rate will be as specified herein. The Contractor
SECTION 32 12 10 Page 4 shall protect the underlying from any damage (water, traffic, etc.) until the surfacing is placed. If the Contractor places the surfacing within seven days, the choice of protection measures or actions to be taken is at the Contractor's option. Damage to the underlying material caused by lack of, or inadequate, protection shall be repaired recompacted or replaced by approved methods at no additional cost to the Government. If the Contractor options to use the prime coat, it shall be applied as soon as possible after consolidation of the underlying material. To obtain uniform application of the prime coat on the surface treated at the junction of previous and subsequent applications, building paper shall be spread on the surface for a sufficient distance back from the ends of each application to start and stop the prime coat on the paper. Immediately after application, the building paper shall be removed and destroyed.
3.4.3 Tack Coat
Tack coat shall be applied between lifts of asphalt placed, at the discretion of the Contracting Officer.
3.5 CURING PERIOD
Following application of the bituminous material and prior to application of the succeeding layer of pavement, the bituminous coat shall be allowed to cure and to obtain evaporation of any volatiles or moisture. Prime coat shall be allowed to cure without being disturbed for a period of at least 48 hours or longer, as may be necessary to attain penetration into the treated course.
3.6 FIELD QUALITY CONTROL
Samples of the bituminous material shall be tested for compliance with the applicable specified requirements. A sample shall be obtained and tested by the Contractor as directed, under the supervision of the Contracting Officer. The sample may be retained and tested by the Government at no cost to the Contractor.
3.7 SAMPLING AND TESTING
Sampling and testing shall be performed by an approved commercial testing laboratory or by facilities furnished by the Contractor. No work requiring testing will be permitted until the facilities have been inspected and approved.
3.7.1 Sampling
The samples of bituminous material, unless otherwise specified, shall be in accordance with ASTM D 140 or AASHTO T 40. Sources from which bituminous materials are to be obtained shall be selected and notification furnished the Contracting Officer within 15 days after the award of the contract.
3.7.2 Calibration Test
The Contractor shall furnish all equipment, materials, and labor necessary to calibrate the bituminous distributor. Calibration shall be made with the approved job material and prior to applying the bituminous coat material to the prepared surface. Calibration of the bituminous
SECTION 32 12 10 Page 5 distributor shall be in accordance with ASTM D 2995.
3.7.3 Trial Applications
Before providing the complete bituminous coat, three lengths of at least 100 feet for the full width of the distributor bar shall be applied to evaluate the amount of bituminous material that can be satisfactorily applied.
3.7.3.1 Tack Coat Trial Application Rate
Unless otherwise authorized, the trial application rate of bituminous tack coat materials shall be applied in the amount of 0.05 gallons per square yard. Other trial applications shall be made using various amounts of material as may be deemed necessary.
3.7.3. 2 Prime Coat Trial Application Rate
Unless otherwise authorized, the trial application rate of bituminous materials shall be applied in the amount of 0.25 gallon per square yard.
Other trial applications shall be made using various amounts of material as may be deemed necessary.
3.7.4 Sampling and Testing During Construction
Quality control sampling and testing shall be performed as required in paragraph FIELD QUALITY CONTROL.
-- End of Section --
File details come from the government source that posted it. Updated .