2-5_13R0102-0002_Atch_1_SPECS_Section_32_92_19_SEEDING_08_APR_13.pdf

PDF 52 KB Posted

Attached to
Demolition of Base Buildings
Solicitation number
FA4427-13-R-0102
Issued by

About this file

13R0102-0002 Atch 1 Specs Section 32 92 19 Seediing

View the file

Other files

File Type Posted
Questions__ _Answers__2-15_May_13.pdf PDF
1-0_13R0102-0002_Amendment_2_DEMO_IDC.pdf PDF
2-6_13R0102-0002_Atch_1_Task_Description_30_Apr_13.pdf PDF
1-2_13R0102-0002_Fill-In_Section_B_thru_K.doc DOC document
1-1_13R0102-0002_DEMO_Conformed_Solicitation.pdf PDF
2-4_13R0102-0002_Atch_1_SPECS_Section_32_12_16_HOT-MIX_ASPHALT_(HMA)_FOR_ROADS_08_APR_13.pdf PDF
2-1_13R0102-0002_Atch_1_SPECS_Section_02_82_33.13_20 _REMOVAL_CONTROL_AND_DISPOSAL_OF_PAINT_WITH_LEAD_08_APR_13.pdf PDF
1-3_13R0102-0002_Atch_1_SPECS_COVER_and_INDEX_08_APR_13.pdf PDF
2-3_13R0102-0002_Atch_1_SPECS_Section_32_12_10_BITUMINOUS_TACK_ _PRIME_COATS_08_APR_13.pdf PDF
1-6_13R0102-0002_Atch_1_SPECS_01_56_00_para_3.14.2_Attachment_1_Temporary_Staging_of_Contaminated_Soil.pdf PDF
1-7_13R0102-0002_Atch_1_SPECS_Section_02_41_00_DEMOLITION_08_APR_13.pdf PDF
2-7_13R0102-0002_Atch_3_Wage_Determination_Applicability.pdf PDF
1-8_13R0102-0002_Atch_1_SPECS_Section_02_61_13 _EXCAVATION_AND_HANDLING_OF_CONTAMINATED_MATERIAL_08_APR_13.pdf PDF
1-6_13R0102-0002_Atch_1_SPECS_01_56_00_para_3.14.2_Attachment_2_MAP.pdf PDF
1-9_13R0102-0002_Atch_1_SPECS_Section_02_65_00 _UNDERGROUND_STORAGE_TANK_REMOVAL_08_APR_13.pdf PDF
1-6_13R0102-0002_Atch_1_SPECS_Section_01_56_00 _ENVIRONMENTAL_GENERAL_REQUIREMENTS_08_APR_13.pdf PDF
1-5_13R0102-0002_Atch_1_SPECS_Section_01_33_00 _SUBMITAL_PROCEDURES_08_APR_13.pdf PDF
2-0_13R0102-0002_Atch_1_SPECS_Section_02_82_16.00_20 _ENGINEERING_CONTROL_OF_ASBESTOS_CONTAINING_MATERIALS_08_APR_13.pdf PDF
2-2_13R0102-0002_Atch_1_SPECS_Section_03_30_00 _CAST-IN-PLACE_CONCRETE_08_APR_13.pdf PDF
1-4_13R0102-0002_Atch_1_SPECS_Section_01000_GENERAL_REQUIREMENTS_08_APR_13.pdf PDF
2-8_13R0102-0002_Questions__ _Answers_1_dated_06_May_13.pdf PDF
Demo-_Amendment_01-14_Mar_13.pdf PDF
Demo-SV-PPConference-12Mar13.pdf PDF
0-0_FA4427-13R0102_DEMO_IDC_SOLICITATION.pdf PDF
0-5_FA4427-13R0102_Atch_1_SPECS_Section_01_56_00.doc DOC document
1-0_FA4427-13R0102_Atch_3_Wage_Determination_Applicability.doc DOC document
0-4_FA4427-13R0102_Atch_1_SPECS_Section_01_33_00.doc DOC document
0-8_FA4427-13R0102_Atch_1_SPECS_02_82_16.00_20.doc DOC document
0-7_FA4427-13R0102_Atch_1_SPECS_Section_02_65_00.doc DOC document
0-9_FA4427-13R0102_Atch_1_SPECS_02_82_33.13_20.doc DOC document
1-2_FA4427-13R0102_Atch_6_Subcontractor_Consent_Form.doc DOC document
0-1_FA4427-13R0102_FILL_IN_Section_B_thru_K.doc DOC document
1-1_FA4427-13R0102_Atch_5_Past_Perf_Ltr-Questionnaire.doc DOC document
0-3_FA4427-13R0102_Atch_1_SPECS_SECT_01000_-_GENERAL_REQUIREMENTS_30_JAN_13.doc DOC document
0-2_FA4427-13R0102_Atch_1_SPECS_COVER_and_INDEX.doc DOC document
0-6_FA4427-13R0102_Atch_1_SPECS_Section_02_41_00.doc DOC document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IDC FACILITY DEMOLITION

Travis AFB, CA

08 APR 2013

SECTION 32 92 19, Page 1

SECTION 32 92 19

SEEDING

10/06

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D 4427 (2007) Peat Samples by Laboratory Testing

ASTM D 4972 (2001; R 2007) pH of Soils

U.S. DEPARTMENT OF AGRICULTURE (USDA)

AMS Seed Act (1940; R 1988; R 1998) Federal Seed Act

DOA SSIR 42 (1996) Soil Survey Investigation Report

No. 42, Soil Survey Laboratory Methods Manual, Version 3.0

1.2 DEFINITIONS

1.2.1 Stand of Turf

95 percent ground cover of the established species.

1.3 RELATED REQUIREMENTS

Section 31 00 00 EARTHWORK applies to this section for pesticide use and plant establishment requirements, with additions and modifications herein.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Wood cellulose fiber mulch

Fertilizer

Include physical characteristics, and recommendations.

SD-06 Test Reports

Topsoil composition tests (reports and recommendations).

SECTION 32 92 19, Page 2

SD-07 Certificates

State certification and approval for seed

1.5 DELIVERY, STORAGE, AND HANDLING

1.5.1 Delivery

1.5.1.1 Seed Protection

Protect from drying out and from contamination during delivery, on-site storage, and handling.

1.5.1.2 Fertilizer Gypsum Sulfur Iron and Lime Delivery

Deliver to the site in original, unopened containers bearing manufacturer's chemical analysis, name, trade name, trademark, and indication of conformance to state and federal laws. Instead of containers, fertilizer gypsum sulphur iron and lime may be furnished in bulk with certificate indicating the above information.

1.5.2 Storage

1.5.2.1 Seed, Fertilizer Gypsum Sulfur Iron and Lime Storage

Store in cool, dry locations away from contaminants.

1.5.2.2 Topsoil

Prior to stockpiling topsoil, treat growing vegetation with application of appropriate specified non-selective herbicide. Clear and grub existing vegetation three to four weeks prior to stockpiling topsoil.

1.5.2.3 Handling

Do not drop or dump materials from vehicles.

1.6 TIME RESTRICTIONS AND PLANTING CONDITIONS

1.6.1 Restrictions

Do not plant when the ground is muddy, or when air temperature exceeds 90 degrees Fahrenheit.

1.7 TIME LIMITATIONS

1.7.1 Seed

Apply seed within twenty four hours after seed bed preparation.

PART 2 PRODUCTS

2.1 SEED

2.1.1 Classification

SECTION 32 92 19, Page 3

Provide State-certified seed of the latest season's crop delivered in original sealed packages, bearing producer's guaranteed analysis for percentages of mixtures, purity, germination, weedseed content, and inert material. Label in conformance with AMS Seed Act and applicable state seed laws. Wet, moldy, or otherwise damaged seed will be rejected. Field mixes will be acceptable when field mix is performed on site in the presence of the Contracting Officer .

2.1.2 Seed Purity

Min. Min. Percent Max.

Common Percent Germination Percent Name Pure Seed and Hard Seed Weed Seed

65% Perennial Rye 99 90 .01 20% Creeping Fescue 99 90 .01 15% Kentucky Bluegrass 99 85 .01

2.2 TOPSOIL

2.2.1 On-Site Topsoil

Surface soil stripped and stockpiled on site and modified as necessary to meet the requirements specified for topsoil in paragraph entitled "Composition." When available topsoil shall be existing surface soil stripped and stockpiled on-site in accordance with Section 31 00 00

EARTHWORK.

2.2.2 Off-Site Topsoil

Conform to requirements specified in paragraph entitled "Composition."

Additional topsoil shall be furnished by the Contractor.

2.2.3 Composition

Containing from 5 to 10 percent organic matter as determined by the topsoil composition tests of the Organic Carbon, 6A, Chemical Analysis Method described in DOA SSIR 42. Maximum particle size, 3/4 inch, with maximum 3 percent retained on 1/4 inch screen. The pH shall be tested in accordance with ASTM D 4972. Topsoil shall be free of sticks, stones, roots, and other debris and objectionable materials. Other components shall conform to the following limits:

Silt 25-50 percent Clay 4 to 12 percent Sand 20-35 percent pH 5.5 to 7.0 Soluble Salts 600 ppm maximum

2.3 SOIL CONDITIONERS

Add conditioners to topsoil as required to bring into compliance with "composition" standard for topsoil as specified herein.

2.3.1 Peat

SECTION 32 92 19, Page 4

Natural product of peat moss derived from a freshwater site and conforming to ASTM D 4427. Shred and granulate peat to pass a 1/2 inch mesh screen and condition in storage pile for minimum 6 months after excavation.

2.3.2 Sand

Clean and free of materials harmful to plants.

2.3.3 Perlite

Horticultural grade.

2.3.4 Composted Derivatives

Ground bark, nitrolized sawdust, humus or other green wood waste material free of stones, sticks, and soil stabilized with nitrogen and having the following properties:

2.3.4.1 Particle Size

Minimum percent by weight passing:

No. 4 mesh screen 95 No. 8 mesh screen 80

2.3.4.2 Nitrogen Content

Minimum percent based on dry weight:

Fir Sawdust 0.7 Fir or Pine Bark 1.0

2.3.5 Gypsum

Coarsely ground gypsum comprised of calcium sulfate dihydrate 61 percent, calcium 22 percent, sulfur 17 percent; minimum 96 percent passing through 20 mesh screen, 100 percent passing thru 16 mesh screen.

2.3.6 Calcined Clay

Calcined clay shall be granular particles produced from montmorillonite clay calcined to a minimum temperature of 1200 degrees F. Gradation: A minimum 90 percent shall pass a No. 8 sieve; a minimum 99 percent shall be retained on a No. 60 sieve; and a maximum 2 percent shall pass a No. 100 sieve. Bulk density: A maximum 40 pounds per cubic foot.

2.4 FERTILIZER

2.4.1 Granular Fertilizer

Provide at the rate detailed in the soils report. Fertilizer shall be controlled release commercial grade, free flowing, uniform in composition, and consist of a nitrogen-phosphorus-potassium ratio. The fertilizer shall be derived from sulpher coated urea, urea formaldehyde, plastic or polymer coated pills, or isobutylenediurea (IBDU). Fertilizer shall be balanced

SECTION 32 92 19, Page 5 with the inclusion of trace minerals and mirco-nutrients.

2.4.2 Hydroseeding Fertilizer

Provide at the rate detailed in the soils report. Controlled release fertilizer, to use with hydroseeding and composed of pills coated with plastic resin to provide a continuous release of nutrients for at least 6 months.

2.5 MULCH

Mulch shall be free from noxious weeds, mold, and other deleterious materials.

2.5.1 Straw

Stalks from oats, wheat, rye, barley, or rice. Furnish in air-dry condition and of proper consistency for placing with commercial mulch blowing equipment. Straw shall contain no fertile seed.

2.5.2 Hay

Air-dry condition and of proper consistency for placing with commercial mulch blowing equipment. Hay shall be sterile, containing no fertile seed.

2.5.3 Wood Cellulose Fiber Mulch

Use recovered materials of either paper-based (100 percent) or wood-based (100 percent) hydraulic mulch. Processed to contain no growth or germination-inhibiting factors and dyed an appropriate color to facilitate visual metering of materials application. Composition on air-dry weight basis: 9 to 15 percent moisture, pH range from 5.5 to 8.2. Use with hydraulic application of grass seed and fertilizer.

2.6 WATER

Source of water shall be approved by Contracting Officer and of suitable quality for irrigation, containing no elements toxic to plant life.

PART 3 EXECUTION

3.1 PREPARATION

3.1.1 EXTENT OF WORK

Provide soil preparation (including soil conditioners as required), fertilizing, seeding, and surface topdressing of all newly graded finished earth surfaces, unless indicated otherwise, and at all areas inside or outside the limits of construction that are disturbed by the Contractor's operations.

3.1.1.1 Topsoil

Provide 4 inches of off-site topsoil to meet indicated finish grade. After areas have been brought to indicated finish grade, incorporate soil amendments into soil a minimum depth of 4 inches by disking, harrowing, SECTION 32 92 19, Page 6 tilling or other method approved by the Contracting Officer. Remove debris and stones larger than 3/4 inch in any dimension remaining on the surface after finish grading. Correct irregularities in finish surfaces to eliminate depressions. Protect finished topsoil areas from damage by vehicular or pedestrian traffic.

3.1.1.2 Soil Conditioner Application Rates

Apply soil conditioners at rates as determined by laboratory soil analysis of the soils at the job site.

3.1.1.3 Fertilizer Application Rates

Apply fertilizer at rates as determined by laboratory soil analysis of the soils at the job site.

3.2 SEEDING

3.2.1 Seed Application Seasons and Conditions

Immediately before seeding, restore soil to proper grade. Do not seed when ground is muddy or in an unsatisfactory condition for seeding. If special conditions exist that may warrant a variance in the above seeding dates or conditions, submit a written request to the Contracting Officer stating the special conditions and proposed variance. Apply seed within twenty four hours after seedbed preparation. Sow seed by approved sowing equipment. Sow one-half the seed in one direction, and sow remainder at right angles to the first sowing.

3.2.2 Seed Application Method

Seeding method shall be hydroseeding.

3.2.2.1 Hydroseeding

First, mix water and fiber. Wood cellulose fiber, paper fiber, or recycled paper shall be applied as part of the hydroseeding operation. Fiber shall be added at 1,000 pounds, dry weight, per acre. Then add and mix seed and fertilizer to produce a homogeneous slurry. Seed shall be mixed to ensure broadcasting at the rate of 18.5pounds per 1000 square feet. When hydraulically sprayed on the ground, material shall form a blotter like cover impregnated uniformly with grass seed. Spread with one application with no second application of mulch.

3.2.3 Mulching

3.2.3.1 Hay or Straw Mulch

Hay or straw mulch shall be spread uniformly at the rate of 2 tons per acre. Mulch shall be spread by hand, blower-type mulch spreader, or other approved method. Mulching shall be started on the windward side of relatively flat areas or on the upper part of steep slopes, and continued uniformly until the area is covered. The mulch shall not be bunched or clumped. Sunlight shall not be completely excluded from penetrating to the ground surface. All areas installed with seed shall be mulched on the same day as the seeding. Mulch shall be anchored immediately following

SECTION 32 92 19, Page 7 spreading.

3.2.4 Watering

Start watering areas seeded as required by temperature and wind conditions. Apply water at a rate sufficient to insure thorough wetting of soil to a depth of 2 inches without run off. During the germination process, seed is to be kept actively growing and not allowed to dry out.

3.3 PROTECTION OF TURF AREAS

Immediately after turfing, protect area against traffic and other use.

3.4 RESTORATION

Restore to original condition existing turf areas which have been damaged during turf installation operations at the Contractor's expense. Keep clean at all times at least one paved pedestrian access route and one paved vehicular access route to each building. Clean other paving when work in adjacent areas is complete.