0-7_FA4427-13R0102_Atch_1_SPECS_Section_02_65_00.doc
DOC document 145 KB Posted
- Attached to
- Demolition of Base Buildings Federal contract opportunity
- Solicitation number
- FA4427-13-R-0102
About this file
Specifications
View the file
Other files for this federal contract opportunity
Show all 36
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IDC FACILITY DEMOLITION
FA4427-13-R-0102
30 JAN 2013
USACE / NAVFAC / AFCESA / NASA UFGS-02 65 00 (February 2010) Preparing Activity: USACE Superseding UFGS-02 65 00 (August 2008)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated July 2010
SECTION 02 65 00
UNDERGROUND STORAGE TANK REMOVAL
02/10 NOTE: This guide specification covers the requirements for removal and disposal of underground, nonhardened tanks and piping used to store petroleum products, waste oils or hazardous wastes in accordance with Federal, State, and local regulations.
Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.
Remove information and requirements not required in respective project, whether or not brackets are present.
Comments and suggestions on this guide specification are welcome and should be directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.
Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).
PART 1 GENERAL
NOTE: Show the following information on the project drawings:
(1) Overall installation plan which identifies and locates tanks and equipment; borrow, disposal, and stockpile areas; temporary containment areas; special security areas; shoring and special support requirements; and access routes.
(2) Individual as-built site plans of tank locations which identify site features such as buildings, roads, utilities, topography, trees and shrubs, surface condition, etc. If as-built drawings are not available, a site investigation and site plans are required to show the general location of existing tanks and site features. Detail drawings to include dimensions, sections, elevations, slopes and size of excavations and temporary containment areas. Provide, as part of the Tank Closure Report, a detailed map showing exact location of the tank prior to removal.
(3) Limits of pavement removal, fence removal, and the location of ancillary equipment to be removed.
Hardened tanks are deep buried tanks as would be found with some missile facilities. Note this in the contract as they require deeper excavations and possibly substantial demolition of concrete.
Tanks will not be abandoned in place unless a waiver is granted in accordance with state or local requirements, LEE HQ U.S. Air Force for Air Force Projects, and HQUSACE policy dated 31 July 1990, for Formerly Used Defense Sites. Waivers will be obtained prior to advertising the closure project. Exceptions will be granted when requested in writing on a case by case basis. Absence of contamination must still be verified prior to closure and prior to obtaining a waiver.
Incorporate installation, state and local requirements into this specification, including the necessary approval processes, licensing, or having their representative on site during removal operations. In many cases, the state or local jurisdiction has final authority on approval of the Work Plan. While states often enforce petroleum tank removal regulations, counties and cities are sometimes delegated authority.
Petroleum sludge and contaminated media are often considered "special wastes" and are subject to regulations enforced by the State Fire Marshals Office, local agencies, etc. Some states have adopted federal rules for management of petroleum waste.
State requirements usually involve testing, analysis, and a report. The review by the state may require additional testing or other work, and may take several months; therefore, the designer is forewarned to investigate these requirements in advance. Areas most likely to be impacted are waste and tank disposal, tank cleaning, residue and soil sampling and analysis, contaminated soil disposal or remediation, reporting, and requirements for a clean closure.
Petroleum sites which are known to have extensive soil contamination or where groundwater contamination is a possibility, should have a Corrective Action Plan under Subtitle I of RCRA and applicable state and local regulations; refer to EM 1110-1-4006, Removal of Underground Storage Tanks (USTs).
For sites where the tank contained a hazardous waste, remediation should occur under the RCRA Corrective Action requirements of 40 CFR 264, 40 CFR 265, and applicable state requirements.
Coordinate with the customer regarding possible designer's discussions with the regulators, and the existence of unique requirements. Some MACOMS require the Installation Project/Program Manager to either be responsible for all coordination or be included on all contacts with the regulators. For projects not on an active installation discuss requirements with the regulators and omit references to the installation and the Installation Environmental Coordinator.
Include the applicable state and local regulatory references where appropriate in the body of the specification. It is recommended that the specifier refer to DoD "Policy and Guidelines for Acquisitions Involving Environmental Sampling or Testing (November 2007) The following specifications must be used in conjunction with this section:
SECTION 00 22 13 SUPPLEMENTARY INSTRUCTIONS TO BIDDERS
SECTION 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
Section 01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR CONTAMINATED SITES
SECTION 01 32 01.00 10 PROJECT SCHEDULE
[SECTION 01 32 16.00 20 CONSTRUCTION PROGRESS DOCUMENTATION] or
[SECTION 01 32 17.00 20 NETWORK ANALYSIS SCHEDULES (NAS)]
SECTION 01 45 00.00 10 QUALITY CONTROL
SECTION 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL
Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
1.1 UNIT PRICES (Not Used)
NOTE: This paragraph will be deleted if the work is in one lump-sum contract price. If it is retained and more detail is needed, items of consideration may include: excavation, contaminated soil, clean backfill required, non-hazardous sludge, pumpable liquids, analytical (PCB & asbestos), analytical (contaminated water), remove piping, and remainder of work. Coordinate this paragraph with the bidding schedule.
1.2 REFERENCES
NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title.
Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates.
References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process.
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN PETROLEUM INSTITUTE (API)
API PUBL 1628S
(1996) A Guide to the Assessment and Remediation of Underground Petroleum Releases
API RP 1604
(1996; R 2001) Closure of Underground Petroleum Storage Tanks
API RP 2003
(2008; 7th Ed) Protection Against Ignitions Arising out of Static, Lightning, and Stray Currents
API RP 2219
(2005) Safe Operation of Vacuum Trucks in Petroleum Service
API STD 2217A
(2005; R 2009) Guidelines for Safe Work in Inert Confined Spaces in the Petroleum and Petrochemical Industries API Std 2015 (2001) Safe Entry and Cleaning of Petroleum Storage Tanks
ASTM INTERNATIONAL (ASTM)
ASTM D 1556
(2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method
ASTM D 1557
(2009) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)
ASTM D 2167
(2008) Density and Unit Weight of Soil in Place by the Rubber Balloon Method
ASTM D 2487
(2006e1) Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D 4397
(2009) Standard Specification for Polyethylene Sheeting for Construction, Industrial, and Agricultural Applications
ASTM D 6938
(2008a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-1-4006
(1998) Engineering and Design -- Removal of Underground Storage Tanks (USTs)
EM 200-1-1
(1994) Environmental Quality -- Validation of Analytical Chemistry Laboratories
EM 200-1-3
(2001) Engineering and Design -- Requirements for the Preparation of Sampling and Analysis Plans
EM 200-1-6
(1997) Environmental Quality -- Chemical Quality Assurance for HTRW Projects
EM 200-1-7
(2001) Environmental Quality - Performance Evaluation (PE) Program
EM 385-1-1
(2008) Safety and Health Requirements Manual
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 530-R-97-007
(1997) Best Management Practices (BMPs) for Soils Treatment Technologies;, Suggested Operational Guidelines to Prevent Cross-Media Transfer of Contaminants During Cleanup Activities
EPA 600/4-79/020
(1983) Methods for Chemical Analysis of Water and Wastes
EPA SW-846
(Third Edition; Update IV) Test Methods for Evaluating Solid Waste: Physical/Chemical Methods
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910
Occupational Safety and Health Standards
40 CFR 261
Identification and Listing of Hazardous Waste
40 CFR 262
Standards Applicable to Generators of Hazardous Waste
40 CFR 264
Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 265
Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 266
Standards for the Management of Specific Hazardous Wastes and Specific Types of Hazardous Waste Management Facilities
40 CFR 268
Land Disposal Restrictions
40 CFR 279
Standards for the Management of Used Oil
40 CFR 280
Technical Standards and Corrective Action Requirements for Owners and Operators of Underground Storage Tanks (UST)
CA STATE WATER RESOURCES CONTROL BOARD
23 CCR Division 3 Chapter 16 Underground Tank Regulations
1.3 SYSTEM DESCRIPTION
NOTE: 40 CFR 280, RCRA Subtitle I closures are primarily performed on petroleum or chemical product tanks and require a minimum of 30 days notice prior to a change in service or closure.
The RCRA Subtitle C tank closures fit into three categories:
a. Hazardous waste accumulation tanks as per 40 CFR 262.34(a)(1)(ii). These tanks store hazardous waste for less than 90 days.
b. Tanks storing hazardous waste over 90 days without a permit (illegal storage).
c. Part B permitted storage tanks.
The Installation Environmental Coordinator should decide who is responsible for contacting the Implementing Agency. Accomplish Subtitle C tank closures in accordance with the closure plans previously prepared and approved, and other applicable regulatory standards including the Land Ban 40 CFR 268 requirements.
The work consists of removal, decontamination and disposal of two 10,000 gallon underground storage tanks and associated piping and ancillary equipment, including but not limited to dewatering , disposal of contaminated soil, laboratory testing, providing reports which are required by regulatory agencies, and backfilling.. The tanks were used for storing JP8 fuel and were taken out of service in SEP 2006. Residue remaining in the tank is considered a hazardous waste. Existing native soils are predominantly clay. Groundwater [has been encountered within 5 to 10 feet of the surface.
1.4 SUBMITTALS
NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. Submittals should be kept to the minimum required for adequate quality control.
A 揋?following a submittal item indicates that the submittal requires Government approval. Some submittals are already marked with a 揋? Only delete an existing揋?if the submittal item is not complex and can be reviewed through the Contractor抯Quality Control system. Only add a 揋?if the submittal is sufficiently important or complex in context of the project.
For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects.
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects.
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
SD-01 Preconstruction Submittals Work Plan.
Site safety and health plan Excavation and material handling plan Field sampling and laboratory testing plan[G] Tank and piping removal and disposal plan[G] Spill and discharge control plan[G] Qualifications Laboratory Services State licensed hazardous waste transporter[G] SD-06 Test Reports Laboratory and field testing reports[G] Backfill Material[G].
Tank Contents Verification[G].
Contaminated Water Disposal[G].
Soil Examination, Testing, and Analysis[G].
Backfilling Tank Closure Report[G].
SD-11 Closeout Submittals Building permit, inspection permits, and other permits Results of excavation Tank disposal paperwork;[G] Contaminated soil disposal paperwork;[G] Contaminated water disposal paperwork;[G] Identification of tanks removed and disposed of;[G] Salvage Rights Starting and ending dates of reporting period Tank Closure Report;[G] Cumulative quantities of soil excavated
1.5 QUALITY ASSURANCE
1.5.1 Qualifications
NOTE: Require certification for tank removals whenever work will be performed under a jurisdiction requiring certification.
The laboratory validation process for underground storage tank projects is addressed in EM 1110-1-4006 Removal of Underground Storage Tanks, dated 30 September 1998; EM 200-1-1 Validation of Analytical Chemistry Laboratories, dated 1 July 1994; and EM 200-1-7, dated 01 February 2001. Include this information in Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL.
Substantiate a minimum of 2 years of tank removal experience, including subcontractors and personnel employed on the project, and certification by the State of California for tank removal work. Experience shall include removal, transportation, and disposal of underground tanks and associated piping, in conformance with the following:
a. API RP 1604
b. 40 CFR 280, State and local regulations and procedures.
c. Applicable safety rules and regulations.
d. Use of equipment and procedures for testing and vapor-freeing tanks.
e. Handling and disposal of types of wastes encountered in underground tank and pipe removal including disposal of underground tanks and associated piping.
f. Excavation, testing, and disposal of petroleum contaminated soils, liquids, and sludge.
g. Project titles, dates performed, owner's names, points of contact for each project with current contact phone numbers.
1.5.2 Laboratory Services
NOTE: The following paragraph contains tailoring options for NASA, Air Force/Navy, and Army. Select the appropriate tailoring for your project under the view window.
Submit documentation for laboratory services in accordance with State of California certification requirements [EM 1110-1-4006, EM 200-1-1, EM 200-1-3, EM 200-1-6 and EM 200-1-7].
1.5.3 Support Staff
Identify all staff involved for the various components, including personnel collecting and shipping samples, and detail staff member's qualifications.
1.5.4 Preconstruction Conference and Work Plan
Prior to the commencement of work, a preconstruction conference will be scheduled by the Contracting Officer. Prepare and submit a comprehensive Work Plan within 30 days of contract award. The work plan shall conform to the requirements of this specification, API RP 1604, API Std 2015, API RP 2003, API STD 2217A and API RP 2219. Allow 14 days in the schedule for the Government's review and approval. No adjustment for time or money will be made for re-submittals required as a result of noncompliance. No work at the site is allowed, with the exception of site inspections and mobilization, until the Work Plan is approved. As a minimum, include the following in the Work Plan:
1.5.4.1 Site Safety and Health Plan
Furnish detailed safety, health, and accident prevention provisions and develop a Site Safety and Health Plan (SSHP). Incorporate the requirements of 29 CFR 1910 and EM 385-1-1 into the SSHP. Include current training certification statement for personnel prior to entry into the work site. Do not commence work until the SSHP is approved by the Contracting Officer. As a minimum, include the following:
a. Health and safety organization, including discussion of distribution of functions and responsibilities.
b. Organization and components of the SSHP.
c. Physical and chemical site hazard identification.
d. Basic toxicology and toxicity information.
e. Discussion of the EZ and CRZ.
f. Protective clothing.
g. Respiratory protection.
h. Air quality monitoring.
i. Personnel exposure guidelines.
j. Decontamination procedures.
k. Basic first aid review.
l. Emergency response and contingency plan.
m. Site entry and exit procedures.
n. Sampling procedures.
1.5.4.2 Excavation and Material Handling Plan
Describe methods, means, equipment, sequence of operations and schedule to be employed in excavation, transport, handling, borrowing source and stockpiling of soil during underground tank removal. Include shoring requirements. Fifteen days before beginning tank removal work, submit to the Contracting Officer, for approval, a material handling plan that describes phases of dealing with the contaminated soil and water as it relates to the proposed tank[s] and piping removal, including methods of excavating, a material handling plan for the contaminated material, soil testing requirements, and water pumping and collection requirements.
1.5.4.3 Field Sampling and Laboratory Testing Plan
Submit a detailed Sampling and Analysis Plan in accordance with Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL.
Describe field sampling methods and quality control procedures. Identify laboratory and laboratory methods to be used for contamination testing. Include sample reports showing sample identification for location, date, time, sample method, contamination level, name of individual sampler, identification of laboratory, and quality control procedures.
1.5.4.4 Tank and Piping Removal and Disposal Plan
Describe methods, means, sequence of operations, and schedule to be employed in the testing, pumping, cleaning, de-vaporizing, inspecting, cutting and removal, and disposal of underground storage tanks and piping. Include methods to be employed for product, sludge, vapor, and pumpable liquid removal; purging and inerting; and storage methods proposed for control of surface water. Also address the following:
a. Treatment Options
b. Identification of waste, tank and contaminated soil transporters and means of transport.
c. Disposal and alternate facilities, disposal or remediation.
d. Decontamination procedures and coordination with SSHP.
1.5.4.5 Spill and Discharge Control Plan
Develop a comprehensive spill and discharge control plan. Consider and provide contingency measures for potential spills and discharges from handling and transportation of contaminated soils and water. A possible source of guidance for assessment and remediation is API PUBL 1628S.
1.5.4.6 Site Safety And Health Officer
Identify an individual to serve as the Site Safety and Health Officer (SSHO) to report problems and concerns regarding health and safety to the Contracting Officer. Provide documentation that the SSHO possesses working knowledge of local and Federal occupational safety and health regulations, and provide training, in accordance with 29 CFR 1910 to Contractor employees in air monitoring practices and techniques. The SSHO shall remain onsite to provide day to day industrial hygiene support, including air monitoring, training, and daily site safety inspections. The SSHO may be assigned other duties, such as project foreman or quality control manager.
1.5.5 Permits and Licenses
As required or as directed by the Contracting Officer, obtain local, state, or federal permits and licenses that directly impact the Contractor's ability to perform the work prior to commencing removal operations.
1.5.6 Statutes and Regulations
Perform tank closures, removal, and disposal in accordance with 40 CFR 280, 40 CFR 262, 40 CFR 264, and 40 CFR 265 as well as the applicable local, State of California, and Federal regulations.
1.6 PROJECT/SITE CONDITIONS
NOTE: Include any pertinent information regarding the former uses of the area as a gas station or waste oil storage facility, any results of chemical analyses done on contents and/or soils, leak testing results, and any hazardous material that has been stored there, if it has been removed and any unusual site features that may be helpful to the bidders. Refer to EM 1110-1-4006 for more information.
If waste oil tanks were included in the Installation Part B Permit, include that information in this paragraph.
Coordinate with state/local regulators, and EM 1110-1-4006 for information regarding designation of non-contaminated waste oil or petroleum wastes as special wastes.
Edit the specification to reflect the implementing Agency (IA) requirements regarding Treatment, Storage, and Disposal (TSD) facilities.
Notify the Installation Environmental Coordinator (IEC) and the Contracting Officer 14 days prior to tank removal. The Contractor is responsible for contacting the Implementation Agency (IA) in accordance with the applicable reporting requirements.
PART 2 PRODUCTS
2.1 BACKFILL MATERIAL
NOTE: Part or all of this paragraph may be deleted if the subject is addressed in other sections. Refer to EM 1110-1-4006 for special compaction requirements such as under pavements.
Obtain backfill material from [the location indicated on the drawings] [offsite]. Classify backfill in accordance with ASTM D 2487 as GW, GP, GM, GC, SW, SP, SM, SC, MH, CL, or CH and free from roots and other organic matter, trash, debris, snow, ice or frozen materials. Secure and submit approved soil classification test results, including the chain-of-custody records,.prior to bringing offsite materials onsite. The testing frequency for backfill material is 1 per 1000 cubic yards or a minimum of 1 test. Use non-contaminated material removed from the excavation for backfill in accordance with Paragraph BACKFILLING.
2.2 PLASTIC SHEETING
Provide plastic sheeting conforming to ASTM D 4397.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Furnish labor, materials, necessary permits, laboratory tests, and reports and equipment to remove and dispose of products remaining in the underground tanks; clean and vapor free the underground tanks and connecting piping.
3.1.1 Safety Guidelines
Comply with personnel safety guidelines in accordance with federal, state and local regulations.
3.1.2 Exclusion Zone (EZ) And Contamination Reduction Zone (CRZ) Do not permit personnel, not directly involved with the project, to enter work zones, called the EZ and CRZ. The EZ is an area around the tank a minimum of 10 feet from the limits of the tank excavation. At the perimeter of the EZ, establish a CRZ. Clean equipment and personnel within the CRZ, as stated in the paragraph titled "Personnel and Equipment Decontamination." Locate the Contractor's site office, parking area, and other support facilities outside the EZ and CRZ. Clearly mark and post boundaries of the EZ and CRZ. Include a site map, outlining the extent of work zones and location of support facilities, in the SSHP.
3.1.3 Onsite Training
Prior to starting onsite work, conduct a health and safety training class directed by the SSHO [CIH] to discuss the implementation of the SSHP. Notify the Contracting Officer 24 hours prior to beginning the training class.
3.1.4 Personnel Protection
Furnish appropriate personal safety equipment and protective clothing to personnel and ensure that safety equipment and protective clothing is kept clean and well maintained. Furnish three clean sets of personal protective equipment and clothing for use by the Contracting Officer or official visitors as required for entry into the EZ.
3.1.5 Respiratory Protection Program
Fully employ respiratory protection program, addressing respirator usage and training, in accordance with 29 CFR 1910 and EM 385-1-1.
3.1.6 Decontamination
Decontaminate or properly dispose of personal protective equipment and clothing worn in contaminated areas at the end of the work day. The SSHO [CIH] is responsible for ensuring that personal protective clothing and equipment are decontaminated before being reissued.
3.1.7 Emergency Response and First Aid Equipment
a. Prior to commencement of work, thoroughly review emergency response and contingency plan in accordance with 29 CFR 1910. In an emergency, take action to remove or minimize the cause of the emergency, alert the Contracting Officer, and institute necessary measures to prevent repetition of the emergency. Equip site-support vehicles with route maps providing directions to the medical treatment facility.
b. Provide appropriate emergency first aid equipment for treatment of exposure to site physical and chemical hazards. Provide and post a list of emergency phone numbers and points of contact for fire, hospital, police, ambulance, and other necessary contacts. Provide and post a route map detailing the directions to the nearest medical facility.
c. Notify the Contracting Officer of any unforeseen hazard or condition which becomes evident during work.
3.1.8 Burning and Explosives
Use of explosives or burning debris is not allowed. Do not permit ignition sources in the EZ and CRZ.
3.1.9 Protection of Existing Structures and Utilities
Take all necessary precautions to avoid damage to existing structures, their appurtenances, monitoring wells, or utilities that may be affected by work activities. Repair any damage to utilities, monitoring wells resulting from the Contractor's operations at no expense to the Government. Coordinate with the installation to locate underground utilities prior to beginning construction. Do not disturb utilities encountered which were not previously shown or otherwise located without approval from the Contracting Officer.
3.1.10 Shoring
Provide shoring FOR CONTAMINATED SITES.
3.2 TANK CONTENTS VERIFICATION
Conduct sampling and analysis in accordance with the approved Sampling and Analysis Plan. Submit reports, including the chain-of-custody records.
3.2.1 Sampling
NOTE: If the contents have been properly characterized or already removed and disposed, delete the non-applicable portions of the specification.
The designer will detail the sampling requirements (number of samples and analytical methodology) based on the state/local regulations and EM 1110-1-4006 (i.e. tank contents, contaminated water, pumpable liquids and sludge, stockpiled soils, and in situ soils).
If the Government is to perform sampling and analyses, specify what data will be available from the Government. This will enable the Contractor to ascertain if additional analysis will be required by the TSD facility and should be reflected in the bid.
See EM 200-1-3, Requirements for Preparation Sampling and Analysis Plans, for additional information.
Sample tank , pumpable liquids, tank coatings and sludge. If the data is not adequate, additional sampling and analysis to the extent required by the approved facility receiving the material is the responsibility of the Contractor. Meeting all regulatory requirements, including the preparation of hazardous materials and waste for transportation, is the responsibility of the Contractor.
3.2.2 Analysis
NOTE: The designer will consult the state/local regulations and EM 1110-1-4006 for assistance in determining the appropriate analytical parameters for tank contents samples. Analytical protocol will also be based on historical records of tank usage and/or tank contents testing and defined in Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL. Ensure that the Contractor addresses the specific laboratory preparation and analytical methods to be employed, especially variations in fuel related analyses.
Contractor shall test tank contents for the parameters listed herein. Include total petroleum hydrocarbons (TPH) [benzene, ethylbenzene, toluene and xylene in the analysis.
3.2.3 Characterization
NOTE: Regarding "in a special manner", some states require that petroleum contaminated soils (special wastes) be disposed of in specially designated landfills.
Refer to EM 1110-1-4006 for additional information.
Prior to removing any of the tank contents, characterize the contents to determine the type of required disposal based on local, state, and Federal disposal regulations. Characterize tank product, pumpable liquids, and sludge] in accordance with 40 CFR 261 and 40 CFR 279. Submit the waste contents determination and accompanying test results for each phase present in the tank to the Contracting Officer. The Contractor is responsible for any additional requirements identified by the disposal facility. Do not remove the tank contents until approval is given by the Contracting Officer.
3.3 CLEARING, GRUBBING AND REMOVALS
NOTE: If underground storage tank removal is part of a larger project which contains Section 31 11 00 CLEARING AND GRUBBING, use it instead of this paragraph. Otherwise edit this paragraph as needed.
Perform clearing and grubbing as required and directed by the Contracting Officer. Saw cut concrete or asphalt pavement at the limits of removal and break, remove and dispose of the resulting debris off Government Property.
3.4 TOPSOIL (Not Used)
NOTE: If underground storage tank removal is part of a larger project which contains Section 31 00 00 EARTHWORK, use it for topsoil requirements instead of this paragraph. Otherwise edit this paragraph as needed.
3.5 PREPARATIONS FOR EXCAVATION
Before excavating, remove residual liquids trapped in the product lines and remove all product from the tank. Purge and vent the tank in accordance with API RP 1604, and as specified herein.
3.5.1 Removal of Product, Pumpable Liquids, and Sludge
NOTE: See EM 1110-1-4006 for the analytical parameters required for recyclability, reusability and disposal consistent with characterization of tank contents.
If the Defense Re-utilization and Marketing Office (DRMO) is unwilling to take the wastes, delete reference to delivery inside the installation. Early in the design stage coordinate with the DRMO to ensure their capabilities are used to the maximum benefit of the Government and on approved containers that might be available or required by the DRMO. The bid documents must have a letter of waste acceptance attached thereto to be considered a responsive bid. Coordinate with the state regulatory personnel. Other options are addressed in EM 1110-1-4006.
Petroleum contaminated water disposal is addressed in EM 1110-1-4006.
TSD facilities appropriate to accept the wastes generated by this project may be identified. If an analysis is available, bid acceptance may be subject to the bidders having a signed letter of acceptance from a permitted TSD attached to the bid; otherwise the bid should be declared nonresponsive.
Contain and store tank product, pumpable liquids, and sludge onsite, prior to disposal. Treat contaminated water as specified. Analyze and segregate tank product, pumpable liquids, and sludge to recover reusable products prior to being transported to the treatment, storage and disposal (TSD) facility. Use of Government facilities for permanent storage or disposal of the wastes is prohibited. Temporary storage on Government facilities will be allowed only until testing is complete, manifests are complete, and transportation is arranged. The Contractor is responsible for obtaining all required permits. Usable product shall be the property of the Contractor. Provide approved containers, vehicles, equipment, labor, signs, labels, placards and manifests and associated land disposal restriction notices and notifications, necessary for accomplishment of the work, including materials necessary for cleaning up spills that could occur from tank removal operations.
3.5.2 Contaminated Water Disposal
3.5.2.1 Sampling, Analysis, and Containment
NOTE: The designer will detail the analytical parameters for contaminated water and treated effluent, treated onsite or offsite, according to the state regulations, the requirements of the recycler and/or TSD facility, and EM 1110-1-4006. Sampling and analysis are to be conducted for parameters consistent with characterization of tank contents.
Sample and analyze contaminated water both prior to and after treatment. Analyze contaminated water produced from excavation operations and tank pumping treated onsite, for pH; benzene, ethylbenzene, toluene, and xylene (BETX); total lead; oil and grease; total petroleum hydrocarbons (TPH). Provide approved containers, vehicles, equipment, labor, signs, labels, placards and manifests and associated land disposal notices and notifications, necessary for accomplishment of the work.
3.5.2.2 Treatment
If contaminated water is to be treated onsite, specify the proposed treatment in the Work Plan and submit for approval, including the chain-of-custody records. Install temporary storage and treatment equipment in the general vicinity of the tanks at a location approved by the Contracting Officer. Sample and analyze treated effluent and secure approval of results by the Contracting Officer before discharge to the sanitary sewer. Treat and discharge effluent in accordance with the discharge permit.
3.6 PURGING AND INERTING
NOTE: Coordinate explosive limits with health effects, especially for BTEX (benzene, toluene, ethylbenzene, xylene) containing mixtures. Coordinate with EM 1110-1-4006, health and safety specialists or industrial hygienists.
After the tank and piping contents have been removed, but prior to excavation beyond the top of the tank, disconnect all the piping except the piping needed to purge or inert the tank. Purge flammable and toxic vapors from the tank or make the tank inert in accordance with API RP 1604, with the exception that filling with water is not permitted and, if dry ice is employed, use a minimum of 3 pounds per 100 gallons of tank volume. Continuously monitor the tank atmosphere for combustible vapors if the tank is purged, or continuously monitor for oxygen, if the tank is inerted.
3.7 EXCAVATION
NOTE: Some states may require the use of VOC emission suppression protocols during excavation, stockpiling, and transportation operations for VOC contaminated soil. The designer may need to include requirements for submittals of VOC suppression products (polyethylene sheeting, foam, or liquid VOC suppressants) and use field demonstrations to show there are no interferences from the suppression technology used with field screening devices. Approval from state/local regulators may be required prior to usage of these products and the designer should specify accordingly.
Mark all excavation areas, as well as work near roadways.
3.7.1 Exploratory Trenches
Excavate exploratory trenches as necessary to determine the tank location, limits and the location of ancillary equipment. Upon commencing exploratory excavation, utilize organic vapor analyzer/flame ionization device (OVA/FID) equipment to obtain readings for [total petroleum hydrocarbons (TPH), and benzene, tolulene, ethylbenzene, and xylene (BTX), and toxicity characteristic leaching procedure (TCLP). If BTEX indicates gasoline, then provide TCLP.
3.7.2 Tank Excavation
NOTE: Acceptable levels of contaminations are dependent on regulations applicable to the location where tanks and piping are being removed; therefore, verify acceptable levels.
For some locations, such as a contaminated site scheduled for site remediation, it may be permissible to use contaminated soil materials for backfill in tank and piping excavations. Get approval from local regulating authority before using contaminated soil materials.
If contaminated soil materials are approved for backfill, retain first bracketed sentence and delete the second and third bracketed sentences.
a. Provide Contracting Officer with written documentation, no later than 30 days before work begins, that proper State or local authorities have been notified. Notify the Contracting Officer at least 48 hours prior to start of tank removal work. Stage operations to minimize the time that tank excavation is open and the time that contaminated soil is exposed to the weather. Provide protection measures around the excavation area to prevent water runoff and to contain the soil within the excavation area.
b. Perform excavation around the perimeter of the tank to limit the amount of potentially petroleum contaminated soil that could be mixed with previously uncontaminated soil. Segregate petroleum contaminated soil in separate stockpiles.
c. Maintain an excavation around the tank of sufficient size to allow workers ample room to complete the work, but also protect the workers from sliding or cave-ins. Install sheeting, bracing, or shoring in the absence of adequate side slopes if there is a need for workers to enter the excavated area. Divert surface water to prevent direct entry into the excavation.
d. Dewatering of the excavation may require a discharge permit by the State and shall be limited to allow adequate access to the tank and piping, to assure a safe excavation, and to ensure that compaction and moisture requirements are met during backfilling. Dewatering may result in the production of petroleum contaminated water and/or free product. Recover free product from the groundwater only as part of necessary dewatering.
e. Collect and test water generated by dewatering during excavation required for removal of tanks or piping, surface water collected in open excavation, or water used for washing equipment or existing concrete or bituminous surfaces, in accordance with EPA 530-R-97-007, EPA 600/4-79/020, EPA SW-846 and state or locally required analyses.
3.7.3 Temporary Containment of Excavated Soil
Provide temporary containment area near the excavated area. Cover containment area with 30 mil polyethylene sheeting. Place excavated soil on the impervious barrier and cover with 6 mil polyethylene sheeting. Provide straw bale berm around the outer limits of the containment area and cover with polyethylene sheets. Secure edges of sheets to keep the polyethylene sheeting in place.
3.7.4 Piping Excavation
Perform excavation as necessary to remove tank piping and ancillary equipment in accordance with paragraphs: Shoring, Tank Excavation, and Open Excavations.
3.7.5 Open Excavations
NOTE: The time that tank excavations are left open depends on a variety of factors, a major one being the capability of the Contractor's lab to provide analyses within the specified turnaround time. Since short turnaround time adds cost, carefully evaluate the need for short turnarounds to avoid unnecessary costs.
If the excavation cannot be left open, it should be lined with a geomembrane and backfilled. This will aid excavation if test results reveal further contamination. However, placing a geomembrane in the excavation prior to backfilling may interfere with future in-situ remediation (e.g. soil vapor extraction, bioventing, etc.) and should only be allowed after careful consideration.
Secure open excavations and stockpile areas while awaiting confirmation test results from the soil beneath the tank. Backfill the excavation as soon as possible after tank and contaminated soil removals have been completed and confirmation samples have been taken. Divert surface water around excavations to prevent water from directly entering into the excavation.
3.7.6 Hidden Structures
During excavation activities, if asphalt pavement, concrete slabs, or other hidden structures are encountered, remove and wash with high pressure water cleaning equipment. Remove and dispose of the pavement, concrete, and other structures as specified in Section 02 41 00 DEMOLITION.
3.7.7 Stockpiles
NOTE: Soils characterized or contaminated by a listed hazardous waste and not excluded by 40 CFR 261.4(b)(10) cannot be stockpiled unless the area has been designated by the state RCRA office as a corrective action management unit (CAMU); stockpiling of hazardous waste soil constitutes storage in a waste pile and requires a RCRA permit; placing hazardous waste contaminated soil onto plastic still constitutes a waste pile; therefore, except as stated above, all hazardous waste soils must be placed into containers such as drums, roll-offs or dumpsters.
If analytical tests have not been taken before editing of this specification, historical data may be used to assume whether a tank contained petroleum waste only or hazardous waste, until analytical test results are in and contents are verified. If the historical information indicates that a tank did not contain hazardous waste (as defined by the state), and there is no reason to believe the tank ever contained hazardous waste, the soil may be stockpiled until analytical test results required of the Contractor are received. If at that time the results indicate the presence of hazardous waste, the contaminated soil must be managed according to RCRA: no stockpiles unless they are designated CAMUs. If historical data indicates the presence of hazardous waste, or if there is no historical data, the specification should be edited to assume that the contaminated soil is hazardous and should be containerized.
Uncontaminated excavated soil and petroleum contaminated soil, that is not a state-regulated hazardous waste, shall be stockpiled and used for backfill in the tank excavation prior to using borrow material. Separately stockpile uncontaminated soil from the contaminated soil, a safe distance away from, but adjacent to, the excavation. Place allowable stockpiles of contaminated soil on an impermeable geomembrane a minimum of 3 layers, each 6 mils thick, covered with a 6 mils sheet of geomembrane . Place the geomembrane to prevent the stockpiled soil from coming into contact with surface water run-off. Locate the geomembrane cover to prevent rain or surface water from coming into contact with the contaminated soil, as well as limit the escape of the volatile constituents in the stockpile.
3.7.8 Acceptable Levels of Contamination
NOTE: Acceptable levels of contamination are dependent on regulations applicable to the location where tanks and piping are being removed. Specifier shall verify acceptable levels.
For some locations such as a contaminated site scheduled for site remediation, it may be permissible to use contaminated soil materials for backfill in tank and piping excavations. Specifier shall get approval from local regulating authority before using contaminated soil materials.
If contaminated soil materials are approved for backfill, delete paragraph.
Take further samples and test soils with OVA/FID readings for TPH and for BTEX and for Napthalene in accordance with the permit to remove USTs, and for toxicity characteristic leaching procedure (TCLP) for lead if leaded gasoline was stored in or near the underground tank being removed. For stockpiled soils, provide a minimum of one composite sample as 4:1 for every 50 cubic yards for TPH, BTEX, Naphalene and TCLP. Or provide a discrete sample for every 20 cubic yards. Soils that contain 1 ppm or more TPH, 5 ppb or more BTEX and Napthalene or have TCLP reading of 1 ppm lead or virgin petroleum products are considered contaminated materials. Soils which are less than the above may be used as clean fill. Furnish results to the Solano County inspector who will approve to backfill or not. Furnish results to the Contracting Officer within 24 hours after the results are obtained.
3.8 REMOVAL OF PIPING, ANCILLARY EQUIPMENT, AND TANK
NOTE: Consult the state regulators to determine how the state views tank and ancillary equipment transportation, disposal and salvage rights, and what state requirements for cleaning are applicable. Depending on tank material and contents, permits and manifests and other documentation may be required.
3.8.1 Piping and Ancillary Equipment
Disconnect all piping and ancillary equipment from the tank. Remove the piping completely. Cap all tank ancillary equipment and piping connections, except those connections necessary to inert the tank within the excavation zone. Clean the piping exterior and ancillary equipment to remove all soil and inspect for signs of corrosion and leakage. Ensure no spillage of the piping contents occurs, as specified in the Work Plan, and as required in paragraph SPILLS. If the soil under and around the tank pad is contaminated, remove the tank pad and dispose of offsite at an approved hazardous waste facility.
3.8.2 Tank
Remove the tank from the excavation and clean the exterior to remove all soil and inspect for signs of corrosion, structural damage, or leakage. Use only non-sparking type materials or equipment which comes into contact with the tank, or in the vicinity of the excavation such as shovels, slings and tools. After removal from the excavation, place the tank on a level surface at an approved location and secure it with wood blocks to prevent movement.
3.8.3 Contaminated Soil, Tank and Piping Excavation Examination NOTE: Determine the appropriate field-screening instruments for health and safety monitoring; methods should be based on historical records of tank contents testing and age of release; refer to EM 1110-1-4006 for selection. Consider the use of immunoassay field kits to save time and money. Separate immunoassay field kits sensitive to the light and heavy fuel fractions are available; these kits will not be used as real time health and safety monitoring devices.
Include the Coordinator's Name, Office, and Phone Number.
If contamination is expected, the state may request to be present onsite to oversee contaminated soil excavation and supervise sampling efforts. The designer's or Environmental Coordinator's experience at the site or similar sites may provide a basis for estimating the amount of contaminated soil.
If USACE labs are expected to perform analysis, coordinate with them early on to verify they have the adequate resources to accomplish the work.
a. After the tank has been removed from the ground, examine and test the adjacent and underlying soil for any evidence of leakage. Visually inspect the soil for staining after removal of all obviously contaminated soil, then screen for the presence of volatile and/or semi-volatile contamination using a real time vapor monitoring instrument or immunoassay field kits.
b. If tank is 20 feet or less in length, take two samples. Take each sample 2 feet from each end of the tank and 2 feet below the bottom of the excavation. If groundwater is encountered, follow the instruction from the permit to remove USTs for sampling.
c. If the tank is greater than 20 feet, take three samples. Take two samples 2 feet from each end of the tank and 2 feet below the bottom of the excavation. Take a third sample from the middle of the tank area and 2 feet below the bottom of the excavation. If groundwater is encountered, follow the instruction from the permit to remove USTs for sampling.
d. Analyze samples for TPH, BTEX, Napthalene and TCLP. Perform sampling and analysis conforming to standards specified above for stockpiled soils. Soils that contain 1 ppm or more TPH, 5 ppb or more BTEX and Napthalene, or have TCLP reading of 1 ppm of lead or virgin petroleum products are considered contaminated materials. Soils which are less than the above may be used as clean fill. Furnish results to the Solano County inspector who will approve to backfill or not. Furnish results to the Contracting Officer within 24 hours after the results are obtained. Along with the results furnish a sketch showing underground tank, sampling location, and extent of excavations.
e. Transport offsite for disposal uncontaminated soil or petroleum contaminated soil not regulated by the state as hazardous waste. Stockpile contaminated soil or suspected contaminated soil, or, if the site is a RCRA-designated CAMU, containerized until further disposition.
f. The Contracting Officer will determine the extent of the contaminated soil to be removed from each site per site. Report any evidence indicating that the amount of contaminated soil may exceed the individual site limit specified, to the Contracting Officer the same day it is discovered. If minimal additional excavation is required, the Contracting Officer may allow the Contractor to proceed. If extensive contamination is encountered, sample the excavation and backfill in accordance with paragraph BACKFILLING.
g. After the known contaminated soil is removed, sample and analyze the excavation.
3.8.4 Testing Along Piping
NOTE: Testing requirements are dependent on regulations applicable to the locations where tanks and piping are being removed. Verify number of tests required and required location for tests.
For every 20 linear feet of product delivery piping, take one soil sample and analyze for TPH, BTEX, and TCLP. Conform sampling and analysis of soil materials to EPA standards specified above.
3.9 TANK CLEANING
NOTE: 1. For tanks larger than 15,120 liters (4,000 gallons) or for projects that have tanks, some of which are smaller or larger than 15,120 liters (4,000 gallons), select the first optional…