This document is a Request for Information (RFI) response for the Hurlburt Field HVAC Multiple Award Construction Contract (MACC) solicitation FA441725R0017. The RFI covers detailed questions and answers regarding a specific SEED Project involving replacement of CRAC units in a server room, with responses addressing technical, logistical, and administrative aspects of the potential contract. Key project details include replacing two existing CRAC units in a server room, with specific requirements around equipment removal, controls systems, electrical connections, and site access.
The RFI provides comprehensive guidance for potential contractors, including requirements for temporary cooling, control point specifications, existing equipment details, and site logistics. Notably, the project requires small businesses located within a 300-mile radius of Hurlburt Field, Florida, with the government intending to select approximately five contractors. The contract will have a five-year ordering period, with individual task orders estimated between $1,000 and $3,000,000, and a total anticipated ceiling cost of $5,000,000 per contract. Contractors must have a current NIST SP 800-171 assessment and be registered in the System for Award Management (SAM).
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation: FA441725R0017 - Hurlburt Field HVAC MACC Question
No.
Section
QUESTION
1.
Base Access
Would it be possible to have a yearly badge done since we already have a 5-year MACC contract with Hurlburt? This would truly be helpful by not having to go to the visitor every time there's a site visit.
A: Yes, Contractors winning an award under the MACC will provide an “Base Access List” to 1 SOCONS with a list of personnel that will work on the contract. Updates to be submitted when personnel are added or removed.
Those listed will receive an annual pass for Hurlburt.
2.
PM/QCM/Safety
a) In executing this project, can one superintendent fulfill the supervision, safety, and QAQC roles? Or is the contractor required to provide both a separate full-time Superintendent and full-time Quality Control Manager?
b) Are contractors required to issue a contract specific QA/QC Plan?
c) Are contractors required to issue a contract specific Safety Plan?
d) Is a full-time Site Safety and Health Officer required? If full time
SSHO required, can either the Superintendent or QCM dual hat this role or must it be a stand-alone role?
A: A single person, superintendent or other, may fill multiple roles as long as they have the qualifications and credentials to perform that position.
3.
Funding
Does this Seed Project currently have funding?
A: Yes, the Seed Project has funding.
4. Tax Exempt Is this project tax exempt? A: No, not tax exempt
5.
Acceptance
Period Question Withdrawn
6.
Attachment 5
a) The July 10 update on SAM.gov states, “Past/Present Performance Questionnaire - Attachment 5 updated”; however, it appears that an update to Attachment 5 has not been posted. Please confirm if Attachment 5 as presently posted is the correct version.
A: The current version of Attachment 5 is correct and posted
b) How many Past Performance examples are required at minimum/maximum?
A: No minimum amount. However, if you do provide Past Performance examples/information (See section L - 4.1 Volume II (a) - Past Performance) – limit to 20 pgs.
7.
L.2.1.4.3 Cost or Pricing Related
Data
This section states that all cost and/or pricing data shall ONLY be addressed in the Cost/Price Proposal Volume. However, Volume I Technical Proposal, Subfactor 1, requests a Price Proposal for the SEED Project and the Fifty Division Cost Estimate Worksheet. Should these items only be included in Volume III or should they also be included in Volume I? A: The referenced paragraph at L.2.1.4.3 has been updated. See Solicitation Amendment 0002 for details.
8.
Section L, 3.1.1.3.2
Reasonableness;
3.1.1.3.3
Materially Unbalanced
Pricing
Please clarify if the offeror is to provide a narrative response to these sections or if these elements are determined based on the provided Price Proposal and Fifty Division Cost Estimate Worksheet.
A: IAW Sect. L 3.1.1.1, contractors shall provide a Scope of Work Narrative that effectively and sufficiently summarizes, explains and documents the preliminary design to address the offers technical approach and critical path. A separate narrative addressing reasonableness and/or pricing is not required;
however, as the paragraph states, the burden of proof for credibility of proposed cost/prices rests with the offeror.
9.
L.3.1.1.3.4 Cost/ Price Information
This section states, "3.1.1.3.4 Cost/Price Information: Data beyond that required by this instruction shall not be submitted, unless the Offeror considers it essential to document or support their cost/price position.
Additionally, although adequate price competition is expected, if only one offer is received in response to this solicitation the responding Offeror will be required to provide certified cost or pricing data in accordance with Table 15- 2, at FAR 15.408 and DFARS Clause 252.215-7009."
Please confirm that certified cost or pricing data is not required with the offeror's initial proposal and only would be required upon request in the event of only one offer being received by the Government. This would include all requirements related to the following clauses:
• 52.215-10 Price Reduction for Defective Certified Cost or Pricing Data. Aug
• 52.215-12 Subcontractor Certified Cost or Pricing Data. Jun 2020
• 252.215-7997 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications-Section 890 Pilot Program. (DEVIATION 2024-O0007) (Feb 2024) Deviation 2024-O0007 (Feb 2024)
• 52.215-20 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data. (Alternate II) Nov 2021 Alternate II Oct
• 252.215-7010 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data. (DEVIATION 2024-O0007) (May 2024) Deviation 2024-O0007 (Feb 2024)
• 252.215-7009 Proposal Adequacy Checklist. Mar 2023
A: Certified cost or pricing data is NOT required
10.
SAM.gov;
252.204-7020
NIST SP 800-171
DoD Assessment
Requirements
The contract listing on SAM.gov includes this statement: "Additionally, the contractors responsibility determination to be made includes having all prospective contractors having a current NIST SP 800-71 assessment in the Procurement Integrated Enterprise Environment (PIEE). A contractor search in the Supplier Performance Risk System will be made to verify each contractor’s assessment has been completed, and the security requirements are either fully met or identifies a work plan to implement the remaining security requirements." Is there an assessment level or score that is required?
A: The highest score is 110. A contractor must have a complete self-assessment current within 3 years. If a contractor does not have a 110 score, they must have a plan with a realistic date to improve score.
11.
252.204-7020
NIST SP 800-171
DoD Assessment
Requirements
Regarding NIST SP 800-71 assessment requirements, please confirm that there are no proposal submission requirements related to this at the time of initial proposal.
A: Correct, nothing in the Proposal is required. However, Contractors must be registered and have a self-assessment score.
12.
Technical Proposal, Subfactor 3
In the 2.1.4.2.1 it lists a Subfactor 3, however there is no Subfactor 3 outlined after Subfactor 2 on page 7 of Section L. There are no Section L instructions or Section M Evaluation Criteria labeled "Subfactor 3." Please clarify the requirements for Technical Proposal Subfactor 3.
A: Subfactor 3 is the Geographical Area (See Section L, 3.1.3.1 under SUBFACTOR 3). Provide evidence of home or affiliated office, which is located within a 300-mile radius of 350 Tully St., Bldg. 90339, Hurlburt Field, FL 32544.
Evidence shall be in the form of the current SAM.gov registration address, a utility bill with current address, lease agreement, tax notice or official government correspondence.
13.
Section L, Section 3.1.1.2.
Please confirm that the construction schedule for the SEED project can be provided in MS Project, Primavera, or any other comparable scheduling software, as stated in Section L, Section 3.1.1.2.
A: Yes, the submitted schedule must be developed using project scheduling software such as MS Project, Primavera, or any other comparable form.
14.
Section L, Section 3.1.1.3
Price proposal for SEED project: Is there a CLIN schedule that should be filled out for this section?
A: No, IAW the revised paragraph 3.1.1.3, contractor shall utilize the summary of its 50 Division Worksheet.
15.
Section L, paragraph 3.1.2.1
Are any documents provided by the offeror as evidence of a home or affiliated office located in a 300-mile radius excluded from the page count on Volume 1?
A: No. Evidence shall be in the form of the current SAM.gov registration address, a utility bill with current address, lease agreement, tax notice or official government correspondence
16.
Section L, paragraph 4.1.1
Does the 20-page limit for Volume II (a) just apply to the combined 1- page summaries for each reference contract? For example, is the offeror able to include an introductory page to this section outside of the 20 summary pages?
A: (1) Summary page or (1) Introduction page is allowable.
17.
Section L, Paragraph 4.1.3
Please confirm that a CPAR for an IDIQ contract which references the performance of a specific task order is an acceptable past performance submission for that task order in lieu of a Past/Present Performance Questionnaire.
A: Yes, CPAR is acceptable.
18.
Section L, Paragraph 4.1.3
Are previously received Past/Present Performance Questionnaires with official signatures acceptable in lieu of the provided Questionnaire format, e.g., the USACE/NAVFAC standard format?
A: No, all past performance questionnaires must be submitted by the person completing the evaluation and sent directly to the Contracting Office.
19.
Section L, Paragraph 4.1.3
If submitting CPARS for multiple projects in fulfillment of Past Performance requirements, can these be grouped into one email when delivered to the 1st Special Operations Contracting Squadron?
A: Yes, all CPARS can be sent at one time (one file)
20.
Section L, paragraph 5.2
This paragraph states “Insert prices in Section B for each Contract Line Items.”
However, Section B of the RFP does not provide CLINS as indicated on page 11 of Section L (5.2) and states “Contract Line-Item Numbers (CLINS) shall be established at the individual Task Order level.” Is there another form other than the 50 Div? Please clarify what needs to be provided for this requirement.
A: See revised Section L, paragraph 5.2 and 5.3
21.
Section L, paragraph 5.2
Is there a complete specifications document that can be provided that outlines requirements for not only general conditions but also the affected construction divisions for this project?
A: See the updated attachment list to include Attachments 11 through 15 for details specific to the project.
22.
Attachment 4.a, SEED Project
Temporary Cooling
Statement of Work
a) Paragraph 1.7. This paragraph requires temporary heating and cooling of spaces as work proceeds. Please define the “spaces” requiring temporary heating and cooling.
b) What is the overall extent of providing temp HVAC during construction?
c) Other than maintaining optimal temperatures in the server room what other areas would be affected. Or is the CRAC units only servicing the server room.
A: The server room where the CRAC units are located will be the only areas requiring temporary HVAC cooling. The existing CRAC units provide cooling only in that server room.
They are programmed to run as Lead, Lag and Redundant. Typically, (1) CRAC is running and (1) CRAC is stand-by. However, we would want the temporary unit to be available, in the event one unit is being worked on, and we have an issue with the second unit.
23.
Attachment 4.a, SEED Project
Temporary Cooling
Statement of Work
Regarding paragraph 1.7: What are the desired temperature and humidity ranges that the temporary heating and cooling equipment would be required to maintain?
A: Recommended dry-bulb temperatures of 68 to 74 Deg. F. and RH levels between 35 to 45% RH. These are for the typical daily operations. Short-term variances above and below may be tolerable.
24.
Attachment 4.a, SEED Project
Temporary Cooling
Regarding paragraph 1.7: If temperature and humidity ranges are desired, at what time schedule would they be required; for example, “Occupied”, “Unoccupied”, “24/7”, etc.?
A: 24/7
Statement of Work
25.
SEED Project
Are there as built drawings or additional architectural drawings pertaining to the CRAC units to indicate wall and ceiling types, for penetrations of new piping? A: Yes. Drawings have been provided. (See Attachment 13)
Note 1: Existing drawings, including control drawings call out the CRAC units to be replaced as CRAC or CRU 1A and 1B, and also as CRAC 1 and 2. These should be considered as the same (2) CRAC units being replaced under this project. (**CRAC units 3 and 4 are, and AHU 1A and 1B may be referenced in the drawings but are NOT the units discussed in this project to replace.)
26.
SEED Project
Are there any drawings indicating a piping detail for the CRAC units?
A: Existing mechanical drawings have been provided. However, the available drawings do not show actual routing and location of existing piping. Piping is shown in photos, with locations of shut-off valves and drains. Piping will need to be replaced from shut-off valves to connections required by new CRAC units, as per the SOW.
27.
SEED Project
Will temporary redundant cooling be required?
A: See 22, above. The actual need for it to be connected and in service may depend on the amount of time that a CRAC unit being worked on is down, and the system is only on (1) CRAC. This may also be dependent on building mission requirements at the time of construction
28.
SEED Project Photography
a) Can a photo of the existing units’ data plate be provided? We also would like to request visible photos of the existing equipment tags/ manufacture plates that are shown to be replaced/Removed.
b) Photos taken, with measurements to means of demoing and installation of equipment.
c) Photos: existing equipment, pipes, floor, ceiling, ceiling tile space.
Particularly the spaces above each CRAC unit (to show the clear space) and chilled water lines penetrate the ceiling.
d) Photos: existing disconnects, chilled water connection and shut off valves and existing CRAC Units.
e) Please provide photographs of the hallway for delivering Crac units to the server room for access planning purposes.
A: To receive photos, please email POC Erica Eberle:
erica.eberle.1@us.af.mil
29.
SEED Project Photography
Contractor requests the RFI period be reopened once site photo-documentation is provided. Site photos may lead to additional questions.
A: N/A at this time
30.
SEED Project
What control points will be required?
A: Photos of existing control points have been provided. There are (22) identified control points for each CRAC unit. There are (2) pairs of low voltage control wires and (1) RS485 control wire for each CRAC unit, along with the smoke detector.
Each CRAC unit communicates the following back to our DDC Controls Shop:
System Status, RA Temp, RA Temp Set-Point, RA Temp Deadband, RA %RH, %RH Set-Point, %RH Deadband, CHW Valve Position, Heating Stages On, Dehumidification Status, Humidifier Status, High Temp Alarm, Low Temp Alarm, High Humidity Alarm, Low Humidity Alarm, Blower Fan Status, Blower Fan Alarm, Filter Status, Water Under Floor Alarm, FireStat Alarm, Maintenance Due Notification.
Note 2: The intent of the project is to re-use existing Controls equipment and programming. Existing wiring includes (1 to 2) RS485 COM cables per CRAC unit, and (2) Pairs of 24V DC Control wires per CRAC unit. These wires come through a junction box on the near wall to each unit and back to the Mechanical Room to an ENC-520-2 Main Controller. The intent is to re-use all existing wiring to connect to the NEW CRAC units. If the location of the connection points to the New CRAC units requires longer control wires, the 24V DC wires should be able to be spliced and lengthened from the junction box. The RS485 COM wires may require a new continuous length.
31.
SEED Project
Please provide information on the existing controls system, the controls contractor who services the existing controls system, and what controls system Hurlburt Field intends on converting too? A: Existing Controls System drawings specific to the (2) CRAC units for this project have been provided.
System is serviced by our DDC Shop in Civil Engineering, and also by System Specialists, Inc. out of Pensacola, FL. (Web address is https://ssifla.com) Intent at a later date is to convert to BACNet IP version, with updated versions of Smart-X Controllers, and Niagara JACE front-end. Upgrades are not part of this project.
32.
What is the model number of the unit used in the basis of design? A: Liebert CW, Model CW076DC1CT03DJ.
33.
SEED Project
It was mentioned at the site visit that the panel for the CRAC units shall remain if it’s still up to code, can you confirm? (Located inside server room) A: Correct. This is referring to the existing Electrical Disconnects. Photos have been provided of interior and exterior.
34.
Will the desk, equipment, tables, computers, shelves, etc., on the east wall be removed for access?
A: Yes. Building personnel have stated that they will remove.
35.
SEED Project
Can the 34" main access door be removed for equipment removal and replacement?
A: Yes.
• The door from the warehouse can be removed. It is 35” wide inside frame.
• The door from the adjoining interior offices can also be removed. It is 35” wide inside frame.
• The server room door is 47” without obstruction. The server room door can be removed.
https://ssifla.com/
• The SCIF door that is between the warehouse door and the server room door CANNOT be removed. It is 35” wide inside frame.
• Either the path from the warehouse or the path through the hallway from the North parking lot can be utilized.
36.
SEED Project
Please confirm the existing structural supports under CRAC units can be re-used?
A: Structural supports would need to be confirmed acceptable by the equipment manufacturer and confirmed to be structurally sound and of the correct height and fit. Supports have not been fully inspected but appear to be in good condition. New CRAC units used for the basis of design, however, included the appropriate matched floor stands with the unit, along with the top duct collar to connect to ceiling. Existing structural supports are approx.
12-1/2” high.
37.
SEED Project
Please confirm the height from finish floor to underside of deck for confirmation of how the new units will fit? (See photos.) Need additional dimension.
A: Dimensions provided below, and in photos. All dimensions are approximate, and must be confirmed prior to installation.
• 96” Top of Finished Floor to Ceiling.
• 12-1/2” Top of Concrete (Bottom of Air Plenum) to Top of Finished Floor. This is also the approx. height of the structural supports underneath the CRAC units.
• 12” Underside of Ceiling Tiles to Bottom of Corrugated Structural Ceiling (Top of Return Air Plenum).
• Support Height for Flooring Grid is 10”, from Top of Concrete (Bottom of Air Plenum) to Underside of Structural Flooring Grid.
Floor Tile Thickness is 1-1/4”, total thickness
38.
SEED Project
Please confirm existing disconnects can be re-used if code compliant and compatible?
A: (See #33.) Correct. Existing electrical disconnects can be re-used if code compliant and in good working order. Photos have been provided of interior and exterior.
39.
SEED Project
Does Hurlburt Field have any attic stock of raised access tile flooring in the event more tile is needed? Can product data be provided on this raised access flooring to show type of supports, ect?
A: No. Contractors should anticipate needing additional floor and ceiling tiles, cut to match New CRAC units. See photos for flooring and support system.
Floor tiles are 1-1/4” thick, structural grade floor plenum tiles. Floor tiles are steel encased, concrete filled, with vinyl surface. Specifications can be found in Architectural drawings provided. (See Attachment 12)
40.
Please provide the preferred sequence of operation of the Crac Units?
A: Sequence of operation is provided on the drawings. Sequence will be Lead, Lag, and Redundant. Primary/Secondary operation will alternate, to provide equal run-time for each CRAC unit.
41. SEED Project Please confirm where the laydown yard and staging areas will be located.
A: Laydown Yard and staging areas will be in the large parking lot to the North side of the building.
42.
Will there be concrete core drilling for new piping and condensate lines?
A: No. Concrete core drilling for piping is not anticipated.
43.
Will the White Noise Generator be provided by the owner? If not, please indicate manufacturer and model number.
A: We do not believe that a White Noise Generator is required. We are confirming and notify if this status changes.
44.
Will raised floor tiles be provided by the owner? if not please indicate manufacturer and model number, for regular tiles and Supply Air Grilles.
A: No. Tiles will be provided by Contractor. Floor tiles are structural grade floor plenum tiles. Floor tiles are steel encased, concrete filled, with vinyl surface. Specifications for ceiling tiles, floor tiles, and return air grills can be found in Architectural drawings provided. Manufacturer and model numbers are not available.
45.
Please provide details on Plexiglass Chimneys. (Thickness, Height, Width, Method on how too fast or seam, entry access points, hinges, for accessibility.)
A: I am unaware of the need for any Plexiglass Chimneys. The Return duct collar that attaches to top of CRAC unit and ceiling grid can be purchased through the CRAC unit vendor/manufacturer with the unit.
46.
Please provide details on Curtain System, manufacture, and model number.
A: Curtain system is not required as part of the project.
47.
SEED Project
Electrical Drawings for Local Operator Console (LOC) have been called out but not provided. Please advise.
A: Electrical drawings have been provided. (See Attachment 12)
48.
SEED Project
Who is the manufacturer of the existing Fire Alarm Control Panel? Where is it located?
A: Integration into the Fire Alarm Control Panel is not required. The contractor shall be responsible for re-connecting existing fire alarm/smoke detector control wiring local to the CRAC unit, along with any existing control/alarm wiring to the DDC Controller. Any additional control wiring between the CRAC units and Fire Alarm Control Panel will be handled by the CE Alarm Shop.
49.
SEED Project
Please provide details on the Curtain System install on drawings, will this interfere with sprinkler heads? Will a fire sprinkler contractor be required?
A: Curtain system is not required as part of this project. Fire sprinkler contractor is not required.
50.
SEED Project
When temporarily removing the ceiling tiles, would the Hurlburt AFB fire department help facilitate the deactivation of the sprinkler heads located in front of each unit?
A: Yes. CE Shops and Hurlburt AFB Fire Dept. will facilitate deactivation of fire suppression system for the area, during any activities that would cause the system to be discharged. CE will handle coordination with Fire Dept., once given notification from Contractor. Contractor must allow ample time for CE to coordinate.
51.
SEED Project
Please provide information on the existing power panel feeding HVAC equipment to be replaced, e.g., panel information and CB information.
A: Photos of the inside and outside of the disconnects have been provided.
This should be the primary means of disconnect and lock-out. Additional drawings for Panel circuit breakers have also been provided.
52.
Hazardous Materials
Regarding hazardous materials, should the contractor expect to encounter any?
A: No. Due to the confined scope of this project and inspection of the work area, we do not anticipate hazardous materials to be encountered.
53.
Hazardous Materials
Is the contractor required to test and abate hazardous materials?
A: We do not believe hazardous materials testing and abatement is required.
If the contractor identifies material or situation that is questionable, they should contact the COR immediately, before proceeding further with demolition.
54.
Hazardous Materials
Is there a hazardous material report available?
A: Latest report has been provided. The recent extensive building project was completed in 2012. Based on the report from that time, the more recent report made available, and the limited scope of this project, no hazardous materials are anticipated to be encountered during this project
55.
Removal/Disposal of Existing Units
Does the Government wish to retain the existing CRAC units after the contractor removes from Bldg 90131 or will the contractor be responsible for disposal? If Government intends to retain, will the contractor be responsible for transporting the units to a different location on base? Where?
A: Yes. The Government will retain the existing CRAC units. They may be re-used, if they are able to be removed intact, or for parts, if they must be removed in sections. The units will be transported by the Contractor to the CE Building 90053, next to a roll-up shed in the HVAC Shop parking lot.
Contractor will coordinate with the CE COR prior to delivery.