The document is a Working Time Analysis for a project to Replace/Upgrade (2) CRAC Units in Server Room, project number B90131. The analysis breaks down the project timeline across seven key stages, with a total allowable contract time of 173 calendar days. The detailed breakdown includes:

  1. Mobilization (including initial base clearances): 30 days
  2. Submittals (preparation and approval): 24 days
  3. Securing materials and equipment: 84 days
  4. Performing all work: 30 days
  5. Correcting punch list items: 5 days

The document notes that additional time was allocated for procuring base clearances, with typical mobilization normally taking 7 calendar days. The estimator suggests some mobilization activities may be completed during the IDIQ/MACC selection process, potentially reducing the required mobilization time.

View the file

Other files

File Type Posted
Solicitation Amendment FA441725R00170003 SF 30.pdf PDF
Solicitation Amendment - FA441725R00170003.pdf PDF
Rev. 7_30_25_Attachment 7 - Section L Instructions to Offerors - HVAC MACC.pdf PDF
Amendment FA441725R00170002 SF 30.pdf PDF
Attachment 13 - B90131 Controls Drawings Specific to CRAC Units.pdf PDF
Rev. 7_23_25_Attachment 7 - Section L Instructions to Offerors - HVAC MACC.pdf PDF
Amendment - FA441725R00170002.pdf PDF
Attachment 12 - B90131 Updates to Building Drawings (2015).pdf PDF
Attachment 15 - Bldg 90131 Asbestos Sampling 22-Jun-22.pdf PDF
Rev. 7_23_25_Attachment 8 - Section M Evaluation Factors for Award.pdf PDF
Attachment 10 - 7.29_RFI Final - FA441725R0017 - Hurlburt HVAC MACC.pdf PDF
Attachment 14 - ACM_LBP Survey Bldg 90131_1 Mar 2024_FTEV201009_Repair_Renovation.pdf PDF
Solicitation Amendment FA441725R00170001 SF 30.pdf PDF
Site Visit Brief.pdf PDF
B90131 Site Visit Sign -In _Redacted.pdf PDF
Attach 4g - 50 Division Construction Cost Estimate Worksheet.xlsx XLSX spreadsheet
Attachment 5 - PPQ.docx DOCX document
Attachment 3 - Wage Determination FL20250217.pdf PDF
4f Equipment Specs B90131 - OR EQUAL.pdf PDF
Attachment 7 - Section L Instructions to Offerors - HVAC MACC.pdf PDF
4a SOW Replace - Upgrade CRAC Units B90131 - 03-March-2025.pdf PDF
4c Existing Equipment.pdf PDF
4d Mechanical Drawing Seed Project.pdf PDF
Attachment 9 - Section H Special Contract Requirements.pdf PDF
Attachment 8 - Section M Evaluation Factors for Award.pdf PDF
4e Air Unit Schedules B90131.pdf PDF
Attachment 2 - HF HVAC-MACC Ordering Guide.pdf PDF
Attachment 1- Hurlburt HVAC MACC SOW.pdf PDF
Solicitation - FA441725R0017.pdf PDF
Attachment 6 - Financial Worksheet.docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORKING TIME ANALYSIS

PROJECT: Replace / Upgrade (2) CRAC Units in Server Room, B90131

ESTIMATOR: Marvin Mashack 850-884-8017 / 570-657-6842

ITEM No. DESCRIPTON ALLOWABLE CALENDAR DAYS

1 Mobilization - Including Initial Base Clearances 30

2 Make Required Submittals 14

3 Approve Submittals 10

4 Secure Materials & Equipment 84

5 Perform All Work 30

6 Correct Punch List Items 5

7 Other: (Testing/Authorization) 0

TOTAL ALLOWABLE CONTRACT TIME 173 DAYS

ADDITIONAL COMMENTS:

Additional time was alloted to include procuring required Base clearances from time of project award, and due to natrue of the seed project. Typical mobilization would be 7 calendar days. Note: Some mobilization activities may be completed during IDIQ/MACC selection process, and may decrease time required for mobilization.