The document is a Working Time Analysis for a project to Replace/Upgrade (2) CRAC Units in Server Room, project number B90131. The analysis breaks down the project timeline across seven key stages, with a total allowable contract time of 173 calendar days. The detailed breakdown includes:

  1. Mobilization (including initial base clearances): 30 days
  2. Submittals (preparation and approval): 24 days
  3. Securing materials and equipment: 84 days
  4. Performing all work: 30 days
  5. Correcting punch list items: 5 days

The document notes that additional time was allocated for procuring base clearances, with typical mobilization normally taking 7 calendar days. The estimator suggests some mobilization activities may be completed during the IDIQ/MACC selection process, potentially reducing the required mobilization time.

View the file

Other files for this federal contract opportunity

Other files attached to Hurlburt Field HVAC MACC, newest first.
File Type Posted
Solicitation Amendment - FA441725R00170003.pdf PDF
Rev. 7_30_25_Attachment 7 - Section L Instructions to Offerors - HVAC MACC.pdf PDF
Solicitation Amendment FA441725R00170003 SF 30.pdf PDF
Attachment 12 - B90131 Updates to Building Drawings (2015).pdf PDF
Attachment 13 - B90131 Controls Drawings Specific to CRAC Units.pdf PDF
Amendment - FA441725R00170002.pdf PDF
Rev. 7_23_25_Attachment 7 - Section L Instructions to Offerors - HVAC MACC.pdf PDF
Attachment 15 - Bldg 90131 Asbestos Sampling 22-Jun-22.pdf PDF
Rev. 7_23_25_Attachment 8 - Section M Evaluation Factors for Award.pdf PDF
Attachment 10 - 7.29_RFI Final - FA441725R0017 - Hurlburt HVAC MACC.pdf PDF
Attachment 14 - ACM_LBP Survey Bldg 90131_1 Mar 2024_FTEV201009_Repair_Renovation.pdf PDF
Amendment FA441725R00170002 SF 30.pdf PDF
Solicitation Amendment FA441725R00170001 SF 30.pdf PDF
B90131 Site Visit Sign -In _Redacted.pdf PDF
Site Visit Brief.pdf PDF
Attachment 2 - HF HVAC-MACC Ordering Guide.pdf PDF
Attachment 7 - Section L Instructions to Offerors - HVAC MACC.pdf PDF
Attachment 8 - Section M Evaluation Factors for Award.pdf PDF
Attachment 9 - Section H Special Contract Requirements.pdf PDF
4e Air Unit Schedules B90131.pdf PDF
Attachment 5 - PPQ.docx DOCX document
Attachment 6 - Financial Worksheet.docx DOCX document
Attach 4g - 50 Division Construction Cost Estimate Worksheet.xlsx XLSX spreadsheet
Solicitation - FA441725R0017.pdf PDF
Attachment 1- Hurlburt HVAC MACC SOW.pdf PDF
Attachment 3 - Wage Determination FL20250217.pdf PDF
4a SOW Replace - Upgrade CRAC Units B90131 - 03-March-2025.pdf PDF
4c Existing Equipment.pdf PDF
4d Mechanical Drawing Seed Project.pdf PDF
4f Equipment Specs B90131 - OR EQUAL.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORKING TIME ANALYSIS

PROJECT: Replace / Upgrade (2) CRAC Units in Server Room, B90131

ESTIMATOR: Marvin Mashack 850-884-8017 / 570-657-6842

ITEM No. DESCRIPTON ALLOWABLE CALENDAR DAYS

1 Mobilization - Including Initial Base Clearances 30

2 Make Required Submittals 14

3 Approve Submittals 10

4 Secure Materials & Equipment 84

5 Perform All Work 30

6 Correct Punch List Items 5

7 Other: (Testing/Authorization) 0

TOTAL ALLOWABLE CONTRACT TIME 173 DAYS

ADDITIONAL COMMENTS:

Additional time was alloted to include procuring required Base clearances from time of project award, and due to natrue of the seed project. Typical mobilization would be 7 calendar days. Note: Some mobilization activities may be completed during IDIQ/MACC selection process, and may decrease time required for mobilization.