Vance FOS Draft PCP Q A.

View the file

Other files

File Type Posted
Vance_FOS_Draft_RFP_Questions_and_Responses_(8_Oct_13).pdf PDF
FA3002-13-R-0008_Vance_FOS_Pre-Solicitation_Notice_(1_Oct_2013).pdf PDF
18._Vance_FOS_Draft_PCP_Q A(Add_Company_Name_Here).xls XLS spreadsheet
17.__DRAFT_Vance_FOS_PCP_(28_Aug_13).pdf PDF
RFI_Vance_FOS_Draft_PCP.pdf PDF
16._Draft_Vance_FOS_Performance_Incentive_Plan_(19_June_13).pdf PDF
Vance_FOS_Draft_RFP_Q A(Add_Company_Name_Here).xls XLS spreadsheet
7.__DRAFT_Vance_FOS_Schedule_B_(14_June_2013).xlsx XLSX spreadsheet
1._02_DRAFT_Vance_FOS_PWS_All_Services.pdf PDF
DRAFT_FA3002-13-R-0008_Vance_FOS_RFP.pdf PDF
9._DRAFT_Vance_FOS_PPI_Tool_Instructions.pdf PDF
14._DRAFT_SB_SubCon_ChkLst.pdf PDF
3._DRAFT_VANCE_FOS_CBA.pdf PDF
10._DRAFT_Vance_FOS_PPI_Tool.accdb —
12._DRAFT_subcontractor_consent_letter.pdf PDF
2._DRAFT_Vance_FOS_WD_2005-2432_Rev_16.pdf PDF
4.__DRAFT_DD254_Security_Class_Spec.pdf PDF
11._DRAFT__Vance_FOS__Past_Performance_Questionnaire.pdf PDF
1._21_DRAFT_Vance_FOS_PWS_AFM.pdf PDF
13._DRAFT_client_authorization_letter.pdf PDF
1._01_01_DRAFT_Vance_FOS_PWS_Expectations.pdf PDF
8._DRAFT_Vance_FOS_Manpower_matrix_(27_Mar_13).xlsx XLSX spreadsheet
1._00_00_DRAFT_Vance_FOS_PWS_Title_Page_and_Table_of_Contents.pdf PDF
1._03_DRAFT_Vance_FOS_PWS_Acft_Mx.pdf PDF
6.__DRAFT__DD441-1_Security_Agreement_Appendage.pdf PDF
RFI_Vance_FOS_Draft_RFP.pdf PDF
1._06_DRAFT_Vance_FOS_PWS_AFE.pdf PDF
5.__DRAFT_DD441_Security_Agreement.pdf PDF
15._DRAFT_Vance_FOS_QASP_(26_June_2013).pdf PDF
Vance_FOS_Draft_PWS_Q A_Responses_(28_June_2013).pdf PDF
RFI_Vance_FOS_Draft_PWS.pdf PDF
06_Aircrew_Flight_Equipment_(22_Feb_13).pdf PDF
21_Vance_Airfield_Management_(22_Feb_13).pdf PDF
02_Vance_FOS_Section_2_V3_(22_Feb13).pdf PDF
Vance_FOS_Draft_PWS_Q A(Add_Company_Name_Here).xls XLS spreadsheet
03_Vance_Aircraft_Maintenance_V2_(22_Feb_13).pdf PDF
01_Vance_FOS__Expectations_V4_(22_Feb_13).pdf PDF
RFI FA3002VANCEOPS14 Q A.pdf PDF
Sources Sought Vance FLGHT OPS 12 Jul 2012.doc DOC document
Sources Sought Vance FLGHT OPS 12 Jul 2012.doc DOC document
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Vance FOS Draft PCP Questions and Responses

FA3002-13-R-0008

Technical Performance

Sub-Areas

1 1

2.1, Table 1

Para. 3.1

Contractors are normally given a standard that represents a reasonable period in which to respond to a CAR, i.e., 3 days.

Each CAR may be different in terms of how much time a contractor is given to respond. Because of the severity of CARs and the government’s need to emphasize quality, the plan will begin deductions on the day the CAR is issued. If the contractor is able to prove the CAR to be completely invalid, the government reserves the right to reduce the amount of deducted funds.

Comment:

Question:

Response:

Non-Proprietary

Recommend the additional deduction of 0.2% for open CARs begin on day 4, which would represent the first day the CAR response is overdue with an additional 0.2% for each day it remains open between 4-89 days.

Concern:

Type Response PCP SectionID Page Reference

Paragraph Reference

Additional Cross Reference:

Proprietary Indicator

RFP Performance Incentive Plan.

17.__DRAFT_Vance_FOS_PCP_(28_Aug_13).pdf

Concur with change from PIP to the Performance Compensation Plan. It reinforces the need for the

Contractor to consistently meet standards, with a set of clearly defined metrics.

Thank you. That is the objective.

Comment:

Question:

Response:

Concern:

Type Response PCP SectionID Page Reference

Paragraph Reference

Additional Cross Reference:

Proprietary Indicator

Tuesday, October 08, 2013 Page 1 of 4

Technical Scope3 1

Paragraphs 1 and 2

Para. 1 states, "…describes how a percentage of the contractor's Total Value of Firm Fixed Price

(TV-FFP) CLINSs will be used as compensation for quality performance." Para. 2 states, "…a percentage of the TV-FFP CLINs will be set aside as a separate CLIN each contract year to compensate performance in the area of Quality."

Is the money for the separate Performance Compensation CLIN over and above the TV-FFP CLINs?

No. The money for the Performance Compensation CLIN will be 4% deducted from the TV-FFP

CLINs as proposed by the contractor.

Comment:

Question:

Response:

We want to be clear that the percentage of the TV-FFP CLINs that is set aside as a separate CLIN each year is not taken from the FFP CLINs but is additional money set aside. In other words, the

TV-FFP CLINs are only the basis for which the 4% is calculated. If money used for the

Performance Compensation CLIN is subtracted from the TV-FFP CLINs, then the CLIN is not compensatory, but punitive.

Concern:

Type Response PCP SectionID Page Reference

Paragraph Reference

Additional Cross Reference:

Proprietary Indicator

Technical Performance

Sub-Areas

4 1

2.1

The primary focus of the plan is on the evaluation of the sub-areas of Technical Inspections (TI) and

Observation Guide Inspections (OGI); however, it also utilizes As Observed Findings (AOFs) and

Corrective Action Reports (CARs) tied to the entire services summary.

Will inspections from outside agencies be included as a performance sub area?

Yes. Inspections from outside agencies may be included as a performance sub-area for purposes of this plan. In addition, surveillance personnel may use these results as tools to focus their own contract inspections.

Comment:

Question:

Response:

Inspections from outside agencies validate processes and procedures and provide a true unbiased view into an organization.

Concern:

Type Response PCP SectionID Page Reference

Paragraph Reference

Additional Cross Reference:

Tuesday, October 08, 2013 Page 2 of 4

Technical As-Observed

Findings

5 2

3.2

As-Observed Findings are issued by the Government if deficiencies or non-compliances are identified but are not associated with a scheduled TI or OGI inspection (to include Quality Control findings).

Will the contractors Quality control finding be documented as CAR's by the COR?

Yes. If the findings are not corrected in a timely manner, contractor quality assurance findings may require COR to create a CAR.

Comment:

Question:

Response:

During some inspections the QAE will document the findings of the contractor quality personnel. If contractor QA personnel detect errors during the inspections then technically 2 inspections have been performed by the QAE. Will both inspections be documented?

Concern:

Type Response PCP SectionID Page Reference

Paragraph Reference

Additional Cross Reference:

Proprietary Indicator

Technical Determination of Sub-Areas

Quarterly

Percentage

6 3

Quarterly percentages will be computed using COR inspection results from the evaluation period for each sub-area (TI and OGI) using the total number of applicable inspections rated satisfactory divided by total number of inspections accomplished in that sub-area then multiplied by one hundred.

How will successful inspections be documented? And how will minor discrepancies be categorized?

All inspections will be documented in the Quality Management Information System (QMIS). All deficiencies will be categorized as either major or minor findings depending on the severity of the disrepancy found during surveillance.

Comment:

Question:

Response:

Current inspections are all documented on CAR forms. If as observed that are satisfactory are not documented it will skew the rates.

Concern:

Type Response PCP SectionID Page Reference

Paragraph Reference

Additional Cross Reference:

Tuesday, October 08, 2013 Page 3 of 4

Technical Determination of Sub-Areas

Quarterly

Percentage

7 3

Quarterly percentages will be computed using COR inspection results from the evaluation period for each sub-area (TI and OGI) using the total number of applicable inspections rated satisfactory divided by total number of inspections accomplished in that sub-area then multiplied by one hundred.

Will the AQL tables be included?

The AQL tables will included as part of the inspections in accordance with the QASP .

Comment:

Question:

Response:

The AQL table will allow for more objective inspection results and ratings.Concern:

Type Response PCP SectionID Page Reference

Paragraph Reference

Additional Cross Reference:

Tuesday, October 08, 2013 Page 4 of 4