Welcome!
Pre-Proposal Conference Briefing
Naval Air Station Pensacola Aircraft Maintenance Support Services
Develop America's Airmen Today ... for Tomorrow
The First Command
CONFERENCE AGENDA
| 0900 Welcome | Captain Brian Elliott | |
| Procuring Contracting Officer (PCO) |
| 0905 Opening Remarks/Mission Brief | Maj Michael Rafferty, 19th AF, Det 1 | |
| Combat System Officer ADVON |
0930 Pre-Proposal Brief
| Solicitation | Capt Brian Elliott (PCO) | |
| Technical Acceptability | Keith Berger (Program Manager) | |
| Performance Work Statement | Oscar Hernandez (Program Manager) | |
| Past Performance | Capt Jennifer McGee (PCAG) |
1000 Question & Answer Session (Open Forum)
1015 One-on-One Sessions (Building 581, 2nd Floor)
DISCLAIMER
The following information is a Brief Overview of the Proposal Requirements and is provided as a courtesy.
The RFP takes precedence over any information discussed in this briefing.
Offerors are Cautioned to Carefully Read the Requirements of the Solicitation and Comply accordingly Questions that address Solicitation requirements must be submitted IN WRITING. A response will be provided via FBO.
OPENING REMARKS/MISSION BRIEF
Maj Michael J. Rafferty 19th Air Force, Detachment 1, Combat System Officer, ADVON
479th Flying Training Group Combat Systems Officer (CSO) Immersion Brief Detachment One Pensacola NAS
Objectives Screen, motivate, and prepare CSO candidates Screen for physical/mental aptitude Introduce basic flight/navigation training Orient to Military Flight Training Aircraft – DA-20
10 sorties / 13.8 hrs
34.5 academic hrs 18 Training Days
INITIAL FLIGHT SCREENING
Old program was 25 hrs, allowed for opportunity to solo, preferably conducted at Pueblo but also authorized to be executed at civilian airfields using a separate “Pueblo-like IFS” AETC syllabus.
IFS since revised. Revised IFS program began 5 Jan 09. CSO candidate sorties reduced to 10 with 13.5 hours. Solo is not authorized. Last 4 sorties will be navigation flights introducing basic “clock to chart” skills (i.e. time, speed, distance relationships). Location would be Pueblo as primary, with the civilians schools still used as back-up option only.
PIPELINE
205 training days
T-6A
T-1A “Mod” T25 CSO Sim
Basic/Contact Instruments VNAV/Low-Level Task Mgmt Mission Management Advanced Nav Electronic Combat Weapons Employment
Graduation
T-6A OFT
IFS
Commissioning Source
Water Survival
PROGRAM FLOW OVERVIEW
Primary Aircraft – T-6A Objectives (IAW Air Force Instructions) Airmanship Fundamentals of Instrument Nav Introduction to Formation Fundamentals of Visual Nav / Low-Level Task / Mission Management
17 sorties / 25.5 hrs 11 sims / 16.5 hrs 287 academic hrs
Advanced Aircraft – T-1A (Multi-place trainer) Objectives (IAW Air Force Instructions) Advanced Nav Systems Principles of Electronic Warfare Fundamentals of Weapons employment Mission Management / Ownership
18 sorties / 52.2 hrs 41 sims / 80.5 hrs 306 academic hrs
PROGRAM FLOW OVERVIEW
479TH FLYING TRAINING GROUP
(Proposed FY10)
479th Flying Training Group NAS Pensacola FL
451 FTS
479 OSS
455 FTS
19th Air Force Randolph AFB TX
12th Flying Training Wing Randolph AFB TX
CSO TRAINING SYSTEMS
Modify 21 T-1A ACFT with front and rear CSO training stations Modify 22 T-6A ACFT with Navy harness & water survival equipment Purchase 2 T-1A GBTS with follow-on ECP for front training station Purchase 3 T-6A GBTS and modify with Navy harness Purchase 12 additional T25 student stations/7 additional I-CSO stations
BRAC 2005, the CSO program was directed to realign at NAS Pensacola FL Combat System Officer training program merges three training tracks formerly known as the Panel Navigator (NAV) track, the Weapon Systems Officer (WSO) track and the Electronic Warfare Officer (EWO) track into one training program 400 Students annually 25,000 flying hours annually Aircraft assigned - T-1A and T-6A 34 aircraft must be flight ready daily 65 sorties per day
AIRCRAFT MAINTENANCE OVERVIEW
This requirement includes maintenance support for select on- equipment (organizational level) maintenance for assigned T-1A and T-6A aircraft.
Organizational level support includes flightline aircraft launch, recovery, and servicing as well as scheduled and unscheduled maintenance support.
| Projected Flying Hours | ||||
| FY10 | FY11 | FY12 | FY13 | |
| T-1A | 6,600 | 12,107 | 12,107 | 12,107 |
| T-6A | 6,400 | 13,200 | 13,200 | 13,200 |
| Total Active Inventory | |
| T-1A | 21 |
| T-6A | 22 |
Note: T-1A aircraft will be modified beginning Nov 09
T-1A and T-6A aircraft maintenance Flightline support – Average sorties per day
| Sorties | |
| T-1A | 25 |
| T-6A | 40 |
CAP/Spare
| T-1A | 12/2 (2-3 goes per day) |
| T-6A | 14/2 (3-4 goes per day) |
Note: Based on FY11 flying hours Foreign Object Damage, tool control, flightline upkeep, aircraft wipe downs, aircraft ladders aircraft forms, and -21 Aircraft Equipment upkeep – QC/environmental management Note: Normal Flying includes aircraft returning on Weekends up to (8) T-1 and (10) T-6
Scheduled Maintenance
| FY10 | FY11 | FY12 | FY13 | |
| Estimated Phase Required | ||||
| T-1A | 33 | 60 | 60 | 60 |
| T-6A | 22 | 44 | 44 | 44 |
Unscheduled maintenance
| TNMCM | % due to Unsched | ||
| T-1A | 10.0% | 42% | |
| T-6A | 6.5% | 72% |
Other requirements Aircraft Ground Power Units Maintenance
Vehicles, personnel protection equipment, and tools provided by the service provider
Vehicles include flightline support vehicles to include 4 tugs, 2 trailers for off-station aircraft recovery, vehicle to transport egress seat/canopy and munitions (CAD/PAD)
Off-Station Disabled Aircraft Repairs
Pensacola Recovery area Estimated recoveries 30 per year Canada Canada
SP can expect to recover aircraft south of a line from Baton Rouge LA, Macon GA and Savannah GA.
Backshop Support (Under support agreement with Navy) Sheet metal Machine/Welding Corrosion control/paint Electrical/environmental Hydraulic Wheel and tire Aerospace Ground Equipment (AGE) Survival equipment maintenance Joint Oil Analysis Program (JOAP) Crash, Damaged or Disable Aircraft Recovery – assist Navy
HAZMART
PMEL/TMDE
Memorandum of Agreement with Eglin AFB
NEW AIRCRAFT HANGER (pictures to follow) Scope: FY08 project - 101,000 SF of new construction Contractor Operated and Maintained Base Supply (COMBS) Hangar for nine (9) aircraft Aircraft Maintenance Unit (AMU) CSO Squadron Operations Fuel Cell for T-1 22K SF Apron expansion & relocation CALA relocation
BOD: 1 Oct 09 (Phase A – MX/COMBS) 1 Nov 09 (Phase B – CSO Ops) Construction Status as of 19 May: 45/45% (Act/Sch) Currently running approx 20 days behind schedule for Phase B
Scheduled to be complete Nov 09
PRE-PROPOSAL BRIEFING
Solicitation Capt Brian Elliott Contracting Officer
ACQUISITION APPROACH
Solicitation will result in a Firm Fixed Price Contract
11 month basic period plus three 1-year option periods
Basis of Award is Performance/Price Trade-off
Offeror’s past performance history will be evaluated on a basis significantly more important than price considerations
However, price will contribute substantially to the selection decision
CONSIDERATIONS
Performance Based Service Acquisition Service Contract Act of 1965, as amended Area Wage Determination, WD 05-3033 (Rev 8) Dated 2 Jun 09
PROPOSAL MILESTONES
| Date | Action |
| 19 Jun 09 | RFP Issued |
| 8 Jul 09 | Pre-Proposal Conf |
| 10 Jul 09 | Past Performance (Volume II) |
| 21 Jul 09 | RFP (Volume I, III & Volume IV) |
| 27 Oct 09 | Contract Award |
| 02 Nov 09 | Mobilization |
| 1 Dec 09 | Performance Begins |
PROPOSAL SUBMISSION
4 Volumes Volume I – Technical Acceptability Volume II – Past Performance Volume III – Price Proposal Volume IV – Small Business Subcontracting Plan
Acceptance Period, Block 12 180 calendar days minimum
Proposal Instructions Paragraph F2, Organization Chart
Base Entry Visitor Control Procedures Anticipate Delay
THE SCHEDULE
| CLIN (X)001 – FFP | Aircraft MX Support Staff | |
| CLIN (X)002 – FFP | T-1A Aircraft MX Support | |
| (Basic Period), 5,559 Flying Hours for 10 months | ||
| CLIN (X)003 – FFP | T-6A Aircraft MX Support | |
| (Basic Period), 6,400 Flying Hours for 10 months |
CLIN (X)004 – COST Weekend/Flying Support
| CLIN (X)005 – COST | Travel-MX Support/Training |
| CLIN (X)006 – COST | Simplified MX Purchase Program |
| CLIN 0007 – FFP | Mobilization |
(X) = Base/Option Year, i.e. (1)001, (2)001
Technical Acceptability Mr. Keith Berger Program Manager
TECHNICAL ACCEPTABILITY
The proposals shall be evaluated against the following Technical Acceptability subfactors:
Manpower & Workforce Plan Management Plan During evaluations of each proposal, the Government will assign each subfactor a rating as shown in the next slide. Separate ratings will be assessed for each subfactor. A rating of unacceptable in one or more technical subfactors will constitute an overall rating of unacceptable for the technical evaluation.
| Acceptable | Meets specified minimum performance or capability requirements necessary for acceptable contract performance. |
| Reasonably Susceptible |
of
| Being Made Acceptable | An approach which, as proposed, does not meet specified minimum performance/capability requirements necessary for performance due to error(s), omissions(s) or deficiency(ies) which, in the view of the government, may be corrected through discussions without significant revision of the proposal | |
| Unacceptable | Does not meet specified minimum performance or capability requirements necessary for acceptable contract performance. |
Technical Rating/Definition
This subfactor is acceptable when the offer provides an acceptable aircraft maintenance organization work force staffing plan to support the 479th Flying Training Group mission
The offeror provides an acceptable plan:
1) Organizational structure
Manpower Matrix (by work center) Number of Full Time Equivalents
b) Number of Part-time or temporary staff
c) Manpower programmed for each contract period Projected overtime hours
TECHNICAL ACCEPTABILITY
Subfactor 1: Manpower (Work Force) Plan NOTE 1: Marginal levels of overall manpower, workforce certification and skill mix could indicate a lack of understanding concerning mission requirements and may result in the proposal receiving an unacceptable rating and/or being eliminated from the competitive range.
This subfactor is acceptable when the offer provides an acceptable aircraft maintenance organization work force staffing plan to support the 479th Flying Training Group mission
The offeror provides an acceptable plan:
1) That addresses an acceptable organizational structure, including organization charts and rationale for the proposed organization, to include roles, responsibilities, and relationships for each organizational element, e.g., branch, work center, shop in accordance with the requirements of the PWS.
2) A completed Manpower Matrix (by work center) that includes the DOL job classification/category, shift (s), and total manpower by work center for mobilization, base and all option periods. (See Section J, Attachment 5)
Number of Full Time Equivalents.
b) Number of Part-time or temporary staff-year equivalent hires.
c) Manpower programmed for each contract period.
Projected overtime man hours to include number of hours proposed and percentages above productive hours.
(Continue)
3) A technical approach describing: (Methodology used to determine manpower )
Productive and non productive labor hours
Workforce by work center to include weekends
Projected overtime hours
How your company will employ staffing to meet changing, unscheduled, urgent and surge requirements
e) Training plan (training, qualifying, and certifying )
Subfactor 1: Manpower (Work Force) Plan
3) A technical approach describing:
a) Methodology used to determine manpower as referred to in Attachment 5 to include factors used in determining the productive and non productive labor hours.
b) Methodology used to determine workforce by work center (office, shop, work area), skill (job classification), and shift(s) to include weekends.
Methodology used to determine projected overtime man hours to include number of hours proposed and percentages above productive hours.
d) How your company will employ staffing to meet changing, unscheduled, urgent and surge requirements.
e) Training plan that addresses procedures for training, qualifying, and certifying the workforce prior to assuming a position throughout the life of the contract.
4) Provide a detailed mobilization approach to ensure contract performance begins the first day of performance. The approach shall include the following information:
Detailed description for recruiting, training/validation, certification, and qualification of contract personnel during the mobilization period.
A time-line schedule which addresses start and completion of each event (e.g., interviewing, hiring, human resource actions, training, and start work dates). The time-line shall address inventory for transfer of Government equipment and facilities, assumption of work, materials, vehicles, and work procedures.
c) An approach that describes the utilization of vehicles to include the number and type of service provider furnished vehicles used in performance of this contract. Also, plans for service provider furnished supplies and materials necessary to meet the requirements of the PWS. Include type and quantity of required supplies and materials.
Staffing considerations:
T-1A -- aircraft Launch (crew show 40 minutes before taxi) T-1A -- fuel cell maintenance (-6 insp (1200 hours)) T-1A – engine change (9000 hours) T-1A – HPO (200 hours) – PE (400 hours) T-6A – HPO (100 hours) – PE (300 hours) T-6A -- egress (-6 insp (24 months)) T-6A -- canopies opening (temp above 90 degrees) T-6A – egress seat and canopy storage (end-of-day) Both – towing distance to corrosion facility (paint barn) AFI 21-101 Special Certifications vs. DOL Job descriptions
For Example only!
| Manpower Matrix | |||||||||||||||||||||||
| Labor Category | Mobilization | Basic | Option Year 1 | Option Year 2 | Option Year 3 | ||||||||||||||||||
| CLIN 0002 T-1A Aircraft Maintenance Support | Salary | AWD | Shift | Shift | Shift | Shift | Shift | ||||||||||||||||
| Duty Titles | DOL CLASSIFICATION | Total | 1 | 2 | 3 | Total | 1 | 2 | 3 | Total | 1 | 2 | 3 | Total | 1 | 2 | 3 | Total | 1 | 2 | 3 | ||
| T-1A FL Sup (Launch & Recovery) | |||||||||||||||||||||||
| Production Supervisor | None | E | 2 | 1 | 1 | 2 | 1 | 1 | 2 | 1 | 1 | 2 | 1 | 1 | 2 | 1 | 1 | ||||||
| 0 | 0 | 0 | 0 | 0 | |||||||||||||||||||
| 0 | 0 | 0 | 0 | 0 | |||||||||||||||||||
| Subtotal | 2 | 1 | 1 | 0 | 2 | 1 | 1 | 0 | 2 | 1 | 1 | 0 | 2 | 1 | 1 | 0 | 2 | 1 | 1 | 0 | |||
| T-1A Flight Line | |||||||||||||||||||||||
| Aircraft Mechanic | 23021- Aircraft Mechanic I | AWD | 0 | 0 | 0 | 2 | 1 | 1 | 2 | 1 | 1 | 2 | 1 | 1 | 2 | 1 | 1 | ||||||
| 0 | 0 | 0 | 0 | 0 | |||||||||||||||||||
| 0 | 0 | 0 | 0 | 0 | |||||||||||||||||||
| Subtotal | 0 | 0 | 0 | 0 | 2 | 1 | 1 | 0 | 2 | 1 | 1 | 0 | 2 | 1 | 1 | 0 | 2 | 1 | 1 | 0 | |||
| T-1A Scheduled Maintenance Support | |||||||||||||||||||||||
| Aircraft Mechanic | 23021- Aircraft Mechanic I | AWD | 0 | 0 | 0 | 2 | 1 | 1 | 2 | 1 | 1 | 2 | 1 | 1 | 3 | 1 | 1 | 1 | |||||
| 0 | 0 | 0 | 0 | 0 | |||||||||||||||||||
| 0 | 0 | 0 | 0 | 0 | |||||||||||||||||||
| Subtotal | 0 | 0 | 0 | 0 | 2 | 1 | 1 | 0 | 2 | 1 | 1 | 0 | 2 | 1 | 1 | 0 | 3 | 1 | 1 | 1 |
CLIN 0002 T-1A Aircraft Maintenance Support Total 2 1 1 0 6 3 3 0 6 3 3 0 6 3 3 0 7 3 3 1
Subfactor 1: Manpower (Work Force) Plan
f) Back-up one deep positions
Manpower adjustments beyond contract start date
Mobilization approach
Recruiting, training/validation, certification, and qualification of personnel
Time-line schedule for interviewing, hiring, human resource actions, training, and start work dates and inventory for transfer of Government equipment and facilities
c) Vehicles utilization and plans for service provider furnished supplies and materials
f) How your company will back-up one deep positions ensuring continuous contract performance.
g) Explanation of any manpower adjustments beyond contract start date. Workforce staffing adjustments (decrease or increase) beyond the contract basic period, shall be supported with rationale and computations for each organizational element.
This subfactor is acceptable when the offer provides an acceptable aircraft maintenance performance plan.
The offeror provides an acceptable plan:
1) How PWS requirements will be accomplished
2) Procedures/approach to flightline, scheduled and unscheduled maintenance activities
3) Ensure data integrity for data systems and forms documentation
TECHNICAL ACCEPTABILITY
Subfactor 2: Management Plan
This subfactor is acceptable when the offer provides an acceptable aircraft maintenance performance plan.
The offeror provides an acceptable plan:
1) A description of how PWS requirements for all functional service areas will be accomplished.
2) Procedures/approach to servicing, scheduled and unscheduled maintenance, pre-flights, thru-flights, basic post-flights, special inspections, corrosion control to include desalination, cleaning, ground handling, launch and recovery of aircraft, troubleshooting and adjustment, on-equipment repairs, component removal and replacement, on and off equipment maintenance of egress systems.
3) A description of your company’s approach to ensure data integrity for data systems and forms documentation required in the PWS.
Quality Control Plan. (QCP) (Identify and prevent deficiencies in the quality of service, including airworthiness, workmanship, and customer support that meet Government quality expectations)
Quality Control (QC) organization with lines of authority and how corrective actions are monitored to ensure successful and timely problem resolution
Control and audit procedure to identify and prevent deficiencies in the quality of service
System(s) for recording, computing, accessing performance measurement data and monitoring corrective action to ensure successful and timely problem resolution
d) Corporate management approach to identify negative trends and implement corrective actions to meet Government expectations (e.g., Group, Wing, 19th AF and HQ AETC) and performance thresholds.
Provide an effective Quality Control Plan. (QCP) Address the internal processes to identify and prevent deficiencies in the quality of service, including airworthiness, workmanship, and customer support that meet Government quality expectations. The plan shall:
Describe the Quality Control (QC) organization with lines of authority and how corrective actions are monitored to ensure successful and timely problem resolution.
Describe control and audit procedure approaches and processes that describe the internal processes to identify and prevent deficiencies in the quality of service.
Provide a description of system(s) for recording, computing, accessing performance measurement data and monitoring corrective action to ensure successful and timely problem resolution.
d) Provide a corporate management approach to identify negative trends and implement corrective actions to meet Government expectations (e.g., Group, Wing, 19th AF and HQ AETC) and performance thresholds.
5) Approach for recovery of disabled Cross Country assigned and non-assigned aircraft
6) Approach for natural disaster evacuation and Navy’s Blue Angel non movement periods
TECHNICAL PROPOSAL
What makes an acceptable proposal Tell us the How Your technical approach Who and how many Your workforce
| What | The services you will provide |
| When | (If applicable) |
Acceptable -- Meets specified minimum performance or capability requirements necessary for acceptable contract performance
Performance Work Statement
Mr. Oscar A. Hernandez Program Manager
PERFORMANCE WORK STATEMENT
| PROGRAM FUNCTION | T-1A | T-6A | AIMD |
| FLIGHT LINE OPERATIONS | SERVICE PROVIDER | ||
| SERVICE PROVIDER |
| SCHEDULE MAINTENANCE | SERVICE PROVIDER |
| SERVICE PROVIDER |
| UNSCHEDULE MAINTENANCE | SERVICE PROVIDER | SERVICE PROVIDER |
| AVIONICS MAINTENANCE | SERVICE PROVIDER | SERVICE PROVIDER |
| ELECTRO-ENVIRONMENTAL MAINTENANCE | SERVICE PROVIDER |
| SERVICE PROVIDER |
| BATTERY MAINTENANCE | AIMD | ||
| PNEUDRAULICS MAINTENANCE | SERVICE PROVIDER | SERVICE PROVIDER | |
| AIRCRAFT METAL TECHNOLOGY | SERVICE PROVIDER | SERVICE PROVIDER | |
| WELDING/METALS TECHNOLOGY | AIMD | ||
| FUELS MAINTENANCE | SERVICE PROVIDER | SERVICE PROVIDER | |
| EGRESS MAINTENANCE | SERVICE PROVIDER | ||
| CORROSION CONTROL- PAINT | SERVICE PROVIDER | SERVICE PROVIDER | |
| CORROSION CONTROL – WASH | SERVICE PROVIDER | SERVICE PROVIDER | |
| NDI ON-EQUIPMENT MAINTENANCE | SERVICE PROVIDER | SERVICE PROVIDER | |
| NDI OFF-EQUIPMENT MAINTENANCE | AIMD | ||
| MAINTENANCE DATA DOCUMENTATION | SERVICE PROVIDER | SERVICE PROVIDER |
| PROGRAM FUNCTION | T-1A | T-6A | AIMD | |
| STRUCTURAL REPAIR – ON EQUIPMENT | SERVICE PROVIDER | SERVICE PROVIDER | ||
| STRUCTURAL REPAIR – OFF EQUIPMENT | AIMD |
| AIRCRAFT DEBRIEF | SERVICE PROVIDER | SERVICE PROVIDER | |
| TECHNICAL ORDER DISTRIBUTION OFFICE (TODO) | SERVICE PROVIDER | SERVICE PROVIDER | |
| PMEL – USER MAINTENANCE | SERVICE PROVIDER | SERVICE PROVIDER | |
| INFORMATION SYSTEMS | SERVICE PROVIDER | SERVICE PROVIDER | |
| OFF STATION RECOVERY | SERVICE PROVIDER | SERVICE PROVIDER | |
| AEROSPACE GROUND EQUIPMENT (PICK UP, DELIVERY, SCHEDULING) | SERVICE PROVIDER | SERVICE PROVIDER | |
| AEROSPACE GROUND EQUIPMENT MAINTENANCE | AIMD | ||
| PERMANENT GROUND POWER UNITS MAINTENANCE | SERVICE PROVIDER | SERVICE PROVIDER | |
| SURVIVAL EQUIPMENT | AIMD | ||
| WHEEL & TIRE MAINTENANCE | AIMD |
| Program Function | Service Provider | Government |
| MAINTENANCE TRAINING | X | |
| QUALITY CONTROL | X | |
| IMDS DATABASE MANAGEMENT | X | X |
| ENGINE MANAGEMENT | X | |
| MAINTENANCE ANALYSIS | X | |
| AIRCRAFT PLANS, SCHEDULING AND DOCUMENTATION | X | |
| MAINTENANCE OPERATIONS CENTER | X | |
| FUNCTIONAL CHECK FLIGHT (FCF) | X | |
| AIRCRAFT WEIGHT AND BALANCE | X | |
| CRASH & RECOVERY | X | ASSIST NASP (HOST BASE) |
| TRANSIENT AIRCRAFT SUPPORT | X (NASP) | |
| SUPPLY (COMBS) | X (AFMC) | |
| FACILITY MANAGEMENT | X (NASP) |
MAINTENANCE TRAINING: The service provider shall be responsible for their personnel training requirements IAW AFI 21-101 and AETCI 21-112. The Military Maintenance Training Flight will not provide support to the service provider without FC and CO approval.
QUALITY CONTROL:The service provider is responsible for establishing a quality control program as described in this PWS.
MAINTENANCE ANALYSIS: The SP will be responsible for performing maintenance analysis functions.
TRANSIENT AIRCRAFT SUPPORT: The GOV (NAVY) will be responsible for supporting transient aircraft maintenance. The service provider shall assist when an aircraft experiences a mission-limiting condition that can be corrected within the purview of the service provider’s responsibilities in this PWS, to the extent necessary to bring the aircraft to mission capable status.
Support Agreements
PMEL
Eglin AFB, 46 MXS/MXMD Service Provider will be required to transport equipment to and from Eglin AFB.
AGE, Survival Equipment, Wheel & Tire, Battery, Off- Equipment NDI, Structural Repair & Metals/Welding NASP, Aircraft Intermediate Maintenance Department Corrosion Control (Paint) Regional Paint Facility – Coordinated through AETC/A4MS Tail Flashing & touch up paint will be done at NASP by the Service Provider
Support Agreements (Cont’d) Fire Extinguisher Maintenance, POL, Base Distribution, Air Field Management, Emergency Action Plans, HAZMAT, Communication Support Inter-Service Support Agreement (ISSA)
Micro-Purchases Contract Funds – Flying Hour Money only CPFH rules apply Purchase made by Service Provider Reimbursed monthly from CLIN Government Purchase Card (GPC) Purchased by QAE Cardholders
Quality Assurance Evaluators 5 Evaluators Fairness & objectivity is paramount Open / frequent communication with contract supervision
Past Performance Capt. Jennifer McGee Contract Negotiator
PAST PERFORMANCE
Past Performance Due Date:
Past Performance Volume 10 Jul 09, 4 PM Central Time
Submittals/Contents Include:
Summary Page Past Performance Information Sheets Consent Letters Client Authorization Letters Organization Structure Change History
Past Performance Information Sheets Submit info on no more than 3 relevant and recent contracts Information sheets limited to 5 pages for each contract
Relevancy Performs Acft Mx on DoD installations as a prime contractor in efforts of similar scope and complexity
Recency Within the past 3 years of RFP issue date At least 6 months of actual contract performance to be considered
Relevant performance information will be obtained from:
Past/Current efforts provided by the offeror Past performance questionnaires Data obtained from other Government/Commercial Sources
Performance Confidence Assessment To assess the offeror’s ability to fulfill the solicitation requirements while meeting schedule, budget, and performance quality constraints
Performance Confidence Assessment Group (PCAG) Accomplishes the past performance evaluation and assigns past performance ratings based on performance ratings of recent and relevant efforts
| Very Relevant | Same or greater magnitude of effort/complexities in RFP |
| Relevant | Involved much of magnitude of effort/complexities in RFP |
| Somewhat Relevant | Involved some of magnitude of effort/complexities in RFP |
| Not Relevant | Did not involve any magnitude of effort/complexities in RFP |
Relevancy Rating/Definition (abbreviated)
Performance Rating/Definition (abbreviated)
Exceptional Performance meets/exceeds many requirements
Performance was accomplished with few minor problems
Corrective actions taken were highly effective Very Good Performance meets/exceeds some requirements
Performance was accomplished with some minor problems
Corrective actions taken were effective Satisfactory Performance meets requirements
Performance contained some minor problems
Corrective actions taken appeared or was satisfactory
Performance Rating/Definition (abbreviated), cont’d Marginal Performance does not meet some contractual requirements
Performance reflected a serious problem for which contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented
Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner
Performance contains serious problem(s) for which corrective actions appear or were ineffective Not Applicable Unable to provide a score
Performance in this area not applicable to effort assessed
PCAG will integrate the recency, relevancy, and performance on all efforts evaluated resulting in an overall rating
| Substantial Confidence | Government has high expectation that the offeror will successfully perform the required effort. |
| Satisfactory Confidence | Government has an expectation that the offeror will successfully perform the required effort. |
| Limited Confidence | Government has a low expectation that the offeror will successfully perform the required effort. |
| No Confidence | Government has no expectation that the offeror will be able to successfully perform the required effort. |
| Unknown Confidence | No performance record is identifiable or the offeror’s performance record is so sparse that no confidence assessment rating can be reasonably assigned. |
Performance Confidence Assessment Rating/Definition (abbreviated)
Offerors without relevant past/present performance history are treated neither favorably nor unfavorably Given an “Unknown Confidence” rating
For complete guidance on past performance, refer to RFP Sections L & M
FINAL COMMENT
Captain Brian Elliott or a designated contracting officer will be the only individuals authorized to contact offerors
Submit written questions no later than 10 Jul 09, 4 p.m. CST Capt Brian Elliott, email: brian.elliott@randolph.af.mil Ms. Teresa Yancey, email: teresa.yancey@randolph.af.mil
Offerors are strongly advised to thoroughly examine their proposals for accuracy, full documentation, clear explanations and compliance with all requirements of the RFP prior to submission to PCO by no later than the due date
Question and Answer Session
Open Forum Capt Brian Elliott Contracting Officer
HQ AETC CONS
Assist in development of highest quality RFP
Address any perceived performance, cost or schedule issues associated with this work
Company information from questions/comments regarding Request for Proposal (RFP) will be confidential. Questions/Comments will be sanitized and posted to FBO
QUESTION AND ANSWER SESSION
One-on-One Sessions Capt Brian Elliott Contracting Officer
HQ AETC CONS
ONE-ON-ONE SESSIONS
Conducted in Building 581
Government panel comprised of:
Contracting Officer Program Manager Other Government Representatives
Each offeror limited to a single 20 minute session image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.jpeg image8.jpeg image9.jpeg image10.png image11.jpeg image12.jpeg image13.png image14.jpeg image15.jpeg image16.jpeg image17.jpeg image18.png image19.jpeg image20.jpeg image21.jpeg image22.jpeg image23.jpeg image24.jpeg image25.jpeg image26.jpeg image27.jpeg image28.png image29.jpeg image30.jpeg image31.jpeg image32.jpeg image1.jpeg image2.jpeg