About this file

This document is a statement of work for a task order to demolish Building 1103 at Hanscom Air Force Base. The task order requires the contractor to remove all hazardous materials from the building according to attached testing reports, including testing and disposing of a 150 Kva transformer. The contractor must demolish the entire facility including all below grade elements and properly dispose of all demolition waste off base. Additional work includes removing site pavements and utilities serving the building, restoring damaged asphalt and installing new sidewalks and curbing, and filling and grading the site according to the plans. The contractor must also adhere to the attached archaeological protection plan due to the historic district and Revolutionary War site borders. The period of performance is 210 calendar days with submittals due in 30 days, 150 days for construction, and 30 days for closeout.

FA2835-19-R-A041 Section J Attachment #08 MACC IDIQ B1103 Demolition Task Order Statement of Work (Updated)

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract Indefinite Delivery Indefinite Quantity (MACC IDIQ) Request for Proposal (RFP), newest first.
File Type Posted
MACC_IDIQ_-_RFP_QnA_9.pdf PDF
MACC_IDIQ_-_RFP_QnA_8.pdf PDF
MACC_IDIQ_-_RFP_QnA_6.pdf PDF
MACC_IDIQ_-_RFP_QnA_4.pdf PDF
MXRD_11-0077_-_Attach.6O-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6C_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6Q_-_Asbuilts.pdf PDF
Section_L_Proposal_Instructions.pdf PDF
MXRD_11-0077_-_Attach.6I_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6L_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6A_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6N_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6B_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6F_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6K_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6T_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6D_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6M_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6J_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6S_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6E_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6G_-_Asbuilts.pdf PDF
SF_30_-_FA2835-19-R-A041-0001.pdf PDF
MXRD_11-0077_-_Attach.6P_-_Asbuilts.pdf PDF
MXRD_11-0077_-_Attach.6H_-_Asbuilts.pdf PDF
MACC_IDIQ_-_RFP_QnA_3.pdf PDF
Section_L_Proposal_Instructions_-_Attachment_4_-_PPQ_Cover_Letter.pdf PDF
MACC_IDIQ_-_RFP_QnA_2.pdf PDF
MACC_IDIQ_-_Pre_Proposal_Con_SV.pdf PDF
MACC_IDIQ_-_RFP_QnA_1.pdf PDF
MACC_IDIQ_Solicitation_-_FA2835-19-R-A041.pdf PDF
MXRD_11-0077_-_DBA_05-17-2019.pdf PDF
MXRD_11-0077_-_Attach.4_-_Limit_PCB_Testing_Rpt.pdf PDF
MACC_IDIQ_SOW_Appendix_2.pdf PDF
MXRD_11-0077_-_Attach.5_-_AIL_Testing_Rpt.pdf PDF
MXRD_11-0077_-_Attach.2_-_Tech._Specs.pdf PDF
MACC_IDIQ_SOW_Appendix_4.pdf PDF
MACC_IDIQ_SOW_Appendix_3.pdf PDF
MXRD_11-0077_-_Attach.3_-_CARDNO_Testing_Rpt.pdf PDF
MACC_IDIQ__-_Task_Order_01_and__02_Price_Schedule.pdf PDF
Section_M_Evaluation_Criteria.pdf PDF
MXRD_11-0077_-_SOW.pdf PDF
MXRD_11-0077_-_Attach.1_-_Project_Plans.pdf PDF
MACC_IDIQ_SOW.pdf PDF
MACC_IDIQ_SOW_Appendix_1.pdf PDF
MXRD_11-0077_-_Attach.7_-_APP.pdf PDF
MACC_IDIQ_-_Pre-Con_Task_Order.pdf PDF
Section_L_Proposal_Instructions.pdf PDF
MACC_IDIQ_SOW_Appendix_5.pdf PDF
MXRD_11-0077_-_Attach.6_-_Asbuilts.pdf PDF
Show all 50

Multiple Award Construction Contract Indefinite Delivery Indefinite Quantity (MACC IDIQ) Request for Proposal (RFP) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MXRD 11-0070

Statement of Work

Demolish B1103 22 July 2019

TASK ORDER STATEMENT OF WORK (SOW)

CONTRACT METHOD: 100% Plans & Specs

PROJECT NUMBER: MXRD 11-0070

PROJECT TITLE: Demolish Building 1103

DATE: 12 Mar 2019

Revised: 22 July 2019

1. PROJECT DESCRIPTION

1.1 The intent of this project is to demolish Building 1103 (B1103) in accordance with the MACC IDIQ Basic Statement of Work (SOW), MACC IDIQ Appendixes, and Task Order MXRD110077 SOW and attachments.

2. LOCATION

2.1 This project is located at Building 1103 on Hanscom Air Force Base.

2.2 B1103 is located in Lexington, MA

3. GOVERNMENT PROVIDED DOCUMENTS

3.1 Attachment #1 – Project Plans, 12 Mar 2019

3.2 Attachment #2 – Task Order Technical Specifications, 12 Mar 2019

3.3 Attachment #3 – CARDNO ATC Hazardous Materials Survey Report, 8 Mar 2013

3.4 Attachment #4 – CARDNO ATC Limited PCB Sealant Survey, 25 Jun 2012

3.5 Attachment #5 – Asbestos Identification Laboratory Testing Report, 13 Jan 2012

3.6 Attachment #6 to #6T – Select Record Drawings for B1103, May 1960

3.7 Attachment #7 – Archaeological Protection Plan

4. ADMINISTRATION

Project Manager David P. Wong, P.E., PMP, CCP 781-225-2937 david.wong@us.af.mil

Alternate Project Manager Sean Shayan 781-225-2932 shahram.shayan@us.af.mil

Construction Inspector Todd Bates 781-225-6041 todd.bates.1@us.af.mil

1010659953C Highlight

1010659953C Highlight

1010659953C Highlight

1010659953C Highlight

Demolish B1103 22 July 2019

5. PERIOD OF PERFORMANCE (POP)

5.1 The POP shall total 210 calendar days based on the following:

Pre-Construction / Submittals 30 Calendar Days Physical Construction 150 Calendar Days Project Closeout 30 Calendar Days

5.2 The POP shall commence upon Task Order Award.

6. TASK ORDER SPECIFIC GENERAL REQUIREMENTS

6.1 This task order will NOT revise Division 1 Specifications included as Appendix #1 to the Basic MACC IDIQ Contract.

6.2 This task order will NOT require any additional Division 1 Specifications.

7. SCOPE OF WORK

The following items of work are included in this task order. See attachments 1 through 5 for more detailed information.

7.1 Demolish B1103 – work includes the removal and proper disposal of all hazardous materials and complete removal of the building and all subsurface foundations.

7.1.1 Hazardous Materials Abatement

Remove and properly dispose of all hazardous materials within B1103. See hazardous materials testing reports included as attachments 3, 4, & 5.

7.1.2 Building Transformer

The CARDNO ATC Hazardous materials report states that they did not observe any dry or wet transformers in B1103. B1103 has a 150 Kva transformer in the basement. The 150 Kva transformer shall be tested for PCB’s and properly disposed of.

7.1.3 Water in Basement

The basement of B1103 has known groundwater infiltration. Depending on the time of year the contractor may encounter up to 3 feet of water in the basement.

7.1.4 Facility Demolition

Remove the facility in its entirety to include all building elements below grade. All demolition waste shall be properly disposed of off base.

7.2 Site Demolition – Remove all pavements and curbing within the limits of work as shown on project plans.

7.3 Utility Demolition – Remove all utilities providing service to B1103 within the limits of work as shown on project plans. Unless otherwise specified all utilities shall be cut and capped in accordance with industry standards.

Demolish B1103 22 July 2019

7.4 Site Restoration – Patch all asphalt pavements damaged as a result of demolition or as shown on the project plans. Ensure proper grading so that there is no ponding of water. Install vertical granite curb and concrete sidewalks as shown. Provide sufficient clean fill to meet the grades and elevations shown. Provide 6” of topsoil and seed all disturbed areas within the limits of work.

7.5 Archaeological Protection – B1103 sits in a historic district and borders a Revolutionary War archaeological site. Contractor shall adhere to the Archaeological Protection Plan (Appendix #7).

END OF DOCUMENT