About this file
This document contains a task order and related solicitation. The task order covers a pre-construction kickoff meeting for the Multiple Award Construction Contract Indefinite Delivery Indefinite Quantity at Hanscom Air Force Base. It will introduce government and contractor personnel, discuss contract and task order requirements, compliance, submittals, scheduling, payroll reporting, inspections, and site access. The related solicitation seeks proposals for the MACC IDIQ to provide construction services at Hanscom AFB. Offerors should prepare proposals according to the instructions and submit them for evaluation based on the criteria specified. Questions may be directed to the listed contracting office points of contact by the specified due date.
FA2835-19-R-A041 Section J Attachment #07 MACC IDIQ Pre-Construction Task Order
View the file
Other files for this federal contract opportunity
Show all 50
Multiple Award Construction Contract Indefinite Delivery Indefinite Quantity (MACC IDIQ) Request for Proposal (RFP) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
AIR FORCE LIFE CYCLE MANAGEMENT CENTER
HANSCOM AIR FORCE BASE MASSACHUSETTS
27 June 2019
SUBJECT: Multiple Award Construction Contract Indefinite Delivery Indefinite Quantity (MACC IDIQ), FA2835-19-R-A041, MACC IDIQ Pre-Construction Kick-Off Task Order 01 Requirement, Hanscom Air Force Base, MA.
The Contractors receiving a Multiple Award Construction Contract Indefinite Delivery Indefinite Quantity (MACC IDIQ) contract will also receive an initial Pre-Construction Kick-off Task Order which will meet the minimum order quantity and minimum order amount for the MACC IDIQ. The Pre-Construction Kick-off Task Order will cover the following information and requirements pertaining to the MACC IDIQ:
• Introduction of Government Personnel – Function and Authority
• Introduction of key Contractor Personnel – Function and Authority
• MACC IDIQ Contract Requirements
• Compliance with Contract Specifications
• Air Force Form 3000 Requirements (Material Submittals)
• Schedule Requirements
• Submission of Air Force Form 3064/3065 (AF 3064/3065)
• Process for Submitting Requests for Information (RFI)
• Notification Requirements (Utility Outage Request; Working Outside of Normal Hours;
Weekend Work)
• Contract Maintenance of Records (i.e. Daily Reports)
• Davis Bacon Act Applicability; Submission of Payroll Reports; Labor Checks
• Applicability of Liquidated Damages and Construction Warranties
• Base Access Requirements
• Briefings by the Base Safety Office and Base Fire Department
• Construction Inspection by Government Personnel
• Pre-Proposal Site Visits for Task Orders
• Final Inspection and Acceptance Requirements
• Government Property Other Than GFP (Protection of Existing Facilities, Existing
Vegetation)
• Authorized Use of Roadways