3_Contractor_Quality_Control_01440.pdf

PDF 50 KB Posted

Attached to
Joint Forces Paving for Colorado DoD Installations (CODI) Federal contract opportunity
Solicitation number
FA2550-18-R-1004
Issued by
Department of the Air Force Space Command

About this file

This document includes a quality control plan template for a federal construction contract and information on a related federal contract opportunity for paving services on Colorado Department of Defense installations. The quality control plan outlines requirements for contractor personnel, procedures, inspections, documentation and coordination meetings to ensure contract compliance. The federal contract opportunity is a competitive 8(a) small business set-aside to award up to six multiple award task order contracts for a combined ceiling of $200 million. Services will include construction, maintenance and repair of paved and unpaved structures. The period of performance is five years from September 2018 to September 2023 with an optional two-year extension. Questions are due by January 2, 2018, with proposals due on March 24, 2018 and awards anticipated in September 2018.

DRAFT Contractor Quality Control

View the file

Other files for this federal contract opportunity

Other files attached to Joint Forces Paving for Colorado DoD Installations (CODI), newest first.
File Type Posted
Attach_1_-_JFP_CODI_Site_Visit_Attendance_List_(redacted)_21_Feb_18.pdf PDF
JFP_CODI_Site_Visits_MFR_21_Feb_18.pdf PDF
Attach_2_-_JFP_CODI_Site_Visit_Q&A_21_Feb_18.pdf PDF
Site_Visit_MFR_9_Feb_18.pdf PDF
2_Organizational_Guidance__01030.pdf PDF
11_PAFB_Sample_Project_SOW.pdf PDF
7_CODI_PP_Questionaire.pdf PDF
11.1_PAFB_Sample_Project_DRAWING.dwg DWG drawing
5_Airfields_&_Hangars_01540.pdf PDF
12_Acronyms.pdf PDF
1_General_Requirements_01000.pdf PDF
8_Client_Authorization_Template.docx DOCX document
6_Task_Order_Close_Out_01700.pdf PDF
11.2_PAFB_Sample_Project_SUBMITTAL_SCHEDULE.xlsx XLSX spreadsheet
4_Safety_and_Health_01510.pdf PDF
10_Ft_Carson_Sample_Project.pdf PDF
9_Consent_Letter_Template.docx DOCX document
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Joint Forces Paving for Colorado DoD Installations (CODI)

SECTION 01440

CONTRACTOR’S QUALITY CONTROL

ATTACHMENT 3

1. QUALITY CONTROL

1.1. The Contractor is responsible for an effective quality control system in compliance with contract clause 52.246-12, “Inspection of Construction.” The quality control system shall consist of plans, procedures, and organization necessary to manage all delivery orders to produce end products that comply with the contract requirements. The system shall cover all construction operations, both on site and off site, and shall be keyed to the proposed construction sequence.

1.2. Within 30 days after award of this contract, the Contractor shall submit to the Contracting Officer for approval a complete quality control plan. The Contractor shall maintain and implement the approved plan throughout the life of the contract to ensure the requirements of the contract are consistently satisfied. The Quality Control Plan shall be available to government personnel upon request.

1.3. Notification of Noncompliance. The Contracting Officer will notify the

Contractor of any detected noncompliance with the requirements of this section. The Contractor shall take immediate corrective action after receipt of such notice. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

2. QUALITY CONTROL PLAN CONTENTS

2.1. The quality control plan shall identify:

2.1.1. Personnel, procedures, instructions, tests, forms, and records to be used.

2.1.2. The authority and responsibilities of all the quality control personnel.

2.1.3. Procedures for reviewing and approving all shop drawings, product data samples or other submittals before submission to the Contracting Officer.

Procedures for obtaining field measurements.

2.1.4. Method of documenting quality control operation, inspection, and testing of both prime and subcontract work including samples of proposed forms.

2.1.5. Method of documenting and tracking deficiencies including responsibilities and procedures for correcting deficiencies.

3. COORDINATION MEETINGS

3.1. Initial Quality Meeting. After the pre-construction conference, before issuance of any delivery order under this contract, the Contractor shall meet with the cognizant Contracting Officer and discuss the contractor’s quality control plan. During the meeting, a mutual understanding of the system details shall be developed, including the forms for recording quality control operations, control activities, testing, administration of the system for both on site and off site work, and the interrelationship of contractor's management and quality control with the government's quality assurance. Minutes of the meeting will be prepared by the Government and signed by both the Contractor and the cognizant Contracting Officer. The minutes will become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the quality control system or procedures that may require corrective action by the Contractor.

3.2. Interface with Government Inspectors. The Contractor’s quality control personnel may request meetings with the Government to discuss quality issues when they arise. The Government reserves the right to conduct quality meetings at its discretion.

4. QUALITY CONTROL DOCUMENTATION

4.1. The Contractor shall maintain current records showing that required quality control activities and/or tests have been performed. These records shall include the work of subcontractors and suppliers and shall be on a form acceptable to the cognizant Contracting Officer that includes, as a minimum, the following information:

4.1.1. Contractor/subcontractor and its area of responsibility.

4.1.2. Work performed each day, giving location, description, and by whom.

4.1.3. Visitors (including inspectors) on site each day.

4.1.4. Test and/or control activities performed with results and references to specifications/ drawings requirements. List deficiencies noted along with corrective action.

4.1.5. Job safety evaluations stating what was checked, results, and instructions or corrective actions.

4.1.6. Instructions given/received and conflicts in plans and/or specifications.

4.2. These records shall indicate a description of trades working on the project, the number of personnel working, weather conditions encountered, and any delays encountered. These records shall cover both conforming and deficient features and shall include a statement that equipment and materials incorporated in the work and workmanship comply with the contract.

4.3. These records shall be available to government personnel upon request.

END OF SECTION 01440