About this file

This document is an amendment to a solicitation for the Front Range Multiple Award Construction Contract. The amendment provides updates to the solicitation including changes to proposal submission requirements, evaluation factors, labor rates, and past performance questionnaires. It also adds responses to questions seven through thirty-seven from interested offerors. The solicitation is for multiple award indefinite delivery indefinite quantity construction contracts with the Department of the Air Force Space Command to provide design-build and design-bid-build services at installations including Buckley Air Force Base and Cheyenne Mountain Air Force Station. The response due date remains unchanged from the original solicitation.

FA251719RA016 Amendment 0003

View the file

Other files for this federal contract opportunity

Other files attached to Front Range Multiple Award Construction Contract (FRMACC), newest first.
File Type Posted
Attachment_20_-_RFP_Questions_67-69_&_Government_Responses.pdf PDF
FA251719RA016_Amendment_0007.pdf PDF
FA251719RA016_Amendment_0006.pdf PDF
Attachment_19_-_RFP_Questions_61-66_&_Government_Responses.pdf PDF
FA251719RA016_Amendment_0006.pdf PDF
Attachment_19_-_RFP_Questions_61-66_&_Government_Responses.pdf PDF
Attachment_18_-_RFP_Questions_59-60_&_Government_Responses.pdf PDF
Attachment_7a_-_Financial_Information_Request_Contractor_(Fillable_PDF).pdf PDF
Attachment_8a_-_Bonding_Information_Request_Contractor_(Fillable_PDF).pdf PDF
Attachment_13_-_Past_Performance_Questionnaire.pdf PDF
Attachment_8b_-_Bonding_Information_Request_Surety_(Fillable_PDF).pdf PDF
Attachment_7b_-_Financial_Information_Request_Financial_Institution_(Fillable_PDF).pdf PDF
Attachment_5_-_Section_L,_Instructions,_Conditions,_and_Notices_to_Offerors.pdf PDF
Attachment_6_-_Section_M,_Evaluation_Factors_for_Award.pdf PDF
Attachment_13_-_Past_Performance_Questionnaire.pdf PDF
Attachment_5_-_Section_L,_Instructions,_Conditions,_and_Notices_to_Offerors.pdf PDF
Attachment_15_-_RFP_Questions_1-6_&_Govt_Responses.pdf PDF
FA251719RA016_Amendment_0002.pdf PDF
Attachment_14_-_Draft_RFP_Questions_1-43_&_Govt_Responses.pdf PDF
FA251719RA016_Amendment_0001.pdf PDF
RFP_FA251719RA016.pdf PDF
Attachment_7_-_Financial_Information_Request_(Fillable_PDF).pdf PDF
Attachment_1_-_FRMACC_Specifications_Div_1_-_46.pdf PDF
Attachment_6_-_Section_M,_Evaluation_Factors_for_Award.pdf PDF
Attachment_2d_-_Cheyenne_Mountain_Facilities_Excellence_Plan_(FEP).pdf PDF
Attachment_8_-_Bonding_Information_Request_(Fillable_PDF).pdf PDF
Attachment_9_-_Consent_Letter.pdf PDF
Attachment_13_-_Past_Performance_Questionnaire.pdf PDF
Attachment_4c_-_Task_Order_Procedures.pdf PDF
Attachment_2e_-_Fort_Carson_Specific_Requirements_MACC_2019_compressed.pdf PDF
Attachment_10_-_Sample_Client_Authorization_Letter.pdf PDF
Attachment_3_-_Construction_Wage_Determinations.pdf PDF
Attachment_10_-_Client_Authorization_Letter.pdf PDF
Attachment_2c_-_Cheyenne_Mountain_Environmental_Business_Practices_for_Construction_Projects_Version_7.pdf PDF
Attachment_2e_-_Fort_Carson_Specific_Requirements_MACC_2019_compressed.pdf PDF
Attachment_2b_-_Buckley_AFB_IFS_Pre-Final.pdf PDF
Attachment_9_-_Consent_Letter.pdf PDF
Attachment_8_-_Bonding_Information_Request_(Fillable_PDF).pdf PDF
Attachment_6_-_Section_M,_Evaluation_Factors_for_Award.pdf PDF
Attachment_11_-_Past_Performance_Questionnaire_(PPQ).pdf PDF
Attachment_4d_-_CAsPR_Questionnaire.pdf PDF
Attachment_1_-_FRMACC_Specifications_Div_1_-_46.pdf PDF
Attachment_5_-_Section_L,_Instructions_to_Offerors.pdf PDF
FRMACC_Draft_Solicitation_-_FA251719RA016.pdf PDF
Attachment_4a_-_Two-Tiered_Structure.pdf PDF
Attachment_2a_-_21_CES_Design_Guide.pdf PDF
Attachment_4b_-_On-Off_Ramping_Procedures.pdf PDF
Attachment_3_-_Construction_Wage_Determination.pdf PDF
Attachment_2d_-_Cheyenne_Mountain_Facilities_Excellence_Plan_(FEP)_20140422.pdf PDF
Attachment_4c_-_Ordering_Guide.pdf PDF
Show all 50

Front Range Multiple Award Construction Contract (FRMACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The Purpose of This Amendment Is:

a. To update Attachment 5 - Section L, Instructions, Conditions, and Notices to Offerors to reflect the following changes:

1. Section L, L-1., D., second sentence, deleted the words "price and".

2. Section L, L-2., K., Table 1 -Proposal Volume, Tab A, added Tabs/Subtabs

3. Section L, L-3., Tab A., 2., added Tabs/Subtabs

4. Section L, L-3., Tab C., fourth para. deleted "six (6)"

5. Section L, L-3., Tab C., 2., deleted "all" and added "up to"

b. To update Attachment 6 - Section M, Evaluation Factors for Awards to reflect the following changes:

1. Section M, C., Step 2., c., ii., Phase One, Table 2 -Unique Areas, under Pass and Fail, added "At least"

2. Section M, C., Step 2., c., ii., Phase Two, added "an evaluation of each past performance information citation will be completed to determine project relevancy."

c. To update Attachment 11 - Fully-Burdened Hourly Labor Rates, Labor Category from 'Program Manager' to 'Project Manager'.

d. To update Attachment 13 - Past Performance Questionnaire, Section 1, G. to add option for '0' year.

e. To add Attachment 16 - RFP Questions 7-37 & Government Responses.

f. All other terms and conditions, to include the proposal submission due date and time, remain unchanged.

Section J - List of Attachments

Miscellaneous text in this section has been modified to:

Attachment 1 - FRMACC Specifications Div 1 - 46

Attachment 2a - 21 Civil Engineer Squadron (CES) Design Guide

Attachment 2b - Buckley AFB Installation Facilities Standards (IFS)

Attachment 2c - Cheyenne Mountain Environmental Business Practices for Construction Projects

Attachment 2d - Cheyenne Mountain Facilities Excellence Plan (FEP)

Attachment 2e - Fort Carson Specific Requirements

Attachment 3 - Construction Wage Determinations

Attachment 4a - Two-Tiered Structure

Attachment 4b - On-Off Ramping Procedures

Attachment 4c - Task Order Procedures

Attachment 5 - Section L, Instructions, Conditions, and Notices to Offerors

Attachment 6 - Section M, Evaluation Factors for Award

Attachment 7 - Financial Information Request

Attachment 8 - Bonding Information Request

Attachment 9 - Consent Letter

Attachment 10 - Sample Client Authorization Letter

Attachment 11 - Fully-Burdened Hourly Labor Rates

Attachment 12 - Past Performance Information Citations - Unique Areas

Attachment 13 - Past Performance Questionnaire

Attachment 14 - Draft RFP Questions 1-43 & Government Responses

Attachment 15 - RFP Questions 1-6 & Government Responses

FA251719RA0160003

Attachment 16 - RFP Questions 7-37 & Government Responses

FA251719RA0160003

IDCode:
Page: 1
Pages: 3
AmendNo: 0003
EffDate: 10/2/2019
ReqNo: A002706
ProjNo: N/A
IssCode: FA2517
AdmCode:
IssuedBy: FA2517 21 CONS LGC

CP 719 556 7907

135 DOVER ST BLDG 350 STE 2225

PETERSON AFB, CO 80914-1192

United States Jemimah Griggs, Email: jemimah.griggs@us.af.mil Telephone: 719-556-6612

AdminBy:
ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA251719RA016
SolDate: 9/19/2019
AwardChg:
AwardNo:
AwardDate:
Amended: 1
OffrExt:
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G
ChgeOrd:
ChgeOrder:
Modify:
SuppAgre:
SuppAuth:
ModOthr:
OthrSpec:
NoReq: 1
Require:
Copies:
Descript:

SEE CONTINUATION PAGE

ContNameTitle:
CoNameTitle: Christina D. Leary, Contracting Officer

Email: christina.leary@us.af.mil Telephone: 719-556-7907

ContDate:
2019-10-02T13:58:17-0600
LEARY.CHRISTINA.DIANNA.1034327013

CODate: 2 Oct 2019

File details come from the government source that posted it. Updated .